Question
Chapter 7, Problem 17P
To determine
The arrival rate such that it remains unchanged over the observation period.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below.
(1) Calculate the sum of the flow ratios for the critical lane groups.
(2) calculate the minimum cycle length and the effective green time for each phase (balancing v/c for the critical lane groups). Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired.
Vehicles arrive at an intersection approach at 550 veh/h at the beginning of an effective red and 15 vehicles are left in the queue from the previous cycle (end of the effective green). Due to peak hour congestion, the arrival rate increases 50 veh/h/min. Therefore after 1 minute, the arrival rate will be 600 veh/h, after 2 minutes it is 650 veh/h. The saturation flow rate of the approach is 1800 veh/h, the cycle length is 65 seconds, and the effective green time is 30 seconds. Determine the total vehicle delay until complete queue clearance. (Assume D/D/1 queuing).
The saturation flow for an intersection approach is 3600 veh/h. At the beginning of cycle no vehicles are queued. The signal is timed so that what the queue is 13 vehicles the effective green begins. If the queue dissipates 8 seconds before the end of the cycle and the cycle length is 60 seconds. What is the arrival rate assuming D/D/1 queuing?
Chapter 7 Solutions
PRIN.OF HIGHWAY ENGINEERING&TRAFFIC ANA.
Ch. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10P
Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 33PCh. 7 - Prob. 34PCh. 7 - Prob. 35PCh. 7 - Prob. 36PCh. 7 - Prob. 37PCh. 7 - Prob. 38PCh. 7 - Prob. 39PCh. 7 - Prob. 40PCh. 7 - Prob. 41PCh. 7 - Prob. 42PCh. 7 - Prob. 43PCh. 7 - Prob. 44PCh. 7 - Prob. 45PCh. 7 - Prob. 46PCh. 7 - Prob. 47PCh. 7 - Prob. 48PCh. 7 - Prob. 49PCh. 7 - Prob. 50PCh. 7 - Prob. 51PCh. 7 - Prob. 52PCh. 7 - Prob. 53PCh. 7 - Prob. 54PCh. 7 - Prob. 55PCh. 7 - Prob. 56PCh. 7 - Prob. 57PCh. 7 - Prob. 58PCh. 7 - Prob. 59PCh. 7 - Prob. 60PCh. 7 - Prob. 61PCh. 7 - Prob. 62P
Knowledge Booster
Similar questions
- An approach to a pre-timed signal has 40 sec of effective green in a 75-second cycle.The approach volume is 700 veh/h and the saturation flow rate is 1600 veh/h.Calculate the time to queue clearance after the start of the effective green, themaximum number of vehicles in the queue, the total vehicle delay per cycle andthe average delay per vehicle assuming D/D/1 queuing.arrow_forward7. An approach at a pretimed signalized intersection is allocated 30 seconds of effective green in an 80-second signal cycle. The flow at the approach is 500 veh/h and the saturation flow of the approach is 2500 veh/h. Assuming D/D/1 queuing, calculate: 1) the time needed to clear the queue, 2) the average delay per vehicle, and 3) the maximum delay of any vehicle.arrow_forwardA pretimed four-phase signal has critical lane group flow rates for the first three phases of 200, 187, and 210 veh/h (saturation flow rates are 1800 veh/h/ln for all phases). The lost time is known to be 4 seconds for each phase. Assuming Xi = 0.9. If the cycle length is 60 seconds, what is the estimated effective green time of the fourth phase?arrow_forward
- Compute the average approach delay per cycle, given the saturation flow rate of 2400 veh/h and is allocated 24 seconds of effective green in an 80-second signal cycle. Flow at the approach is 500 veh/h. Assume the traffic flow accounts for the peak 15-min period and that there is no initial queue at the start of the analysis period.arrow_forward(b) An approach to a pretimed signal has 25 seconds of effective green in a 60-second cycle. The approach volume is 500 vph and the saturation flow rate is 1400 vph. Calculate the average vehicle delay assuming D/D/1 queuing.arrow_forwardAn observer notes that an approach to a pretimed signal has a maximum of eight vehicles in a queue in a given cycle. If the saturation flow rate is 1440 veh/h and the effective red time is 40 seconds, how much time will it take this queue to clear after the start of the effective green (assuming that approach capacity exceeds arrivals and D/D/1 queuing applies)?arrow_forward
- A pretimed four-phase signal has critical lane group flow rates for the first three phases of 200, 187, and 210 veh/h (saturation flow rates are 1800 veh/h/In for all phases). The lost time is known to be 4 seconds for each phase. Assuming X₁ = 0.9. If the cycle length is 60 seconds, what is the estimated effective green time of the fourth phase? 6.93 sec O 21.89 sec Ⓒ 7.78 sec Q 7.41 secarrow_forwardAn approach to a signalized intersection has a saturation flow rate of 1800 veh/h. At the beginning of an effective red, there are six vehicles in the queue and vehicles arrive at 900 veh/h. The signal has a 60- second cycle with 25 seconds of effective red. What is the total vehicle delay after one cycle (assume D/D/1 queuing)?arrow_forwardThe total cycle time of an intersection is 60 seconds, the green time for the phase is 27 seconds and the corresponding yellow time is 4 seconds. If the saturation headway is 2.4 seconds/ vehicle, the startup lost time is 2 seconds/phase and the clearance lost time is 1 second/phase then the capacity of the movement is (a) 1500 veh/hr/lane (c) 500 veh/hr/lane (b) 700 veh/hr/lane (d) 300 veh/hr/lanearrow_forward
- An observer notes that an approach to a pretimed signal, the time it will take the queue to clear after the start of the effective green (assuming that approach capacity exceeds arrivals and D/D/1 queuing applies) is 60 s. If the saturation flow rate is 1440 veh/h and the effective red time is 40 seconds, what is the maximum number of vehicles in a queue in a given cycle?arrow_forwardFor a given one-lane approach of a signalized intersection, the base free flow speed is 40 mph, flow rate is 450 vphpl, saturation flow rate is 1,800 vphgpl, cycle length and red interval are 90 seconds and 30 seconds. Compute the following: The total time duration from the first vehicle in queue to the last queued vehicle being discharged per cycle The longest queue length and total number of vehicles in queue per cycle; Total vehicle-hours of delay and average delay per vehicle per cycle.arrow_forwardAn approach at a signalized intersection with a 60-second cycle gets 30 seconds of displayed green time. Yellow time is 4 seconds and all-red is 2 seconds (lost time is to be determined from standard assumptions). At the beginning of an effective red there are 4 vehicles in the queue and the saturation flow is 876 veh/h. The arrival rate is given by v(t) = 0.20 - 0.002t [with v(t) in veh/s and t in seconds after the beginning of the effective red]. What is the average vehicle delay for this approach in seconds at the end of the cycle (until the next effective red) that started with the 4 vehicles queued at the beginning of the effective red? (Assume D/D/1 queueing. Please provide you answer in decimal form without units)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning