Concept explainers
(a)
Interpretation: The product structure diagram is to written in indented bill of material list.
Concept Introduction:
The planned order release can be called as method which is based on the specified lead time till the planned receipt date is not received.
(b)
Interpretation: The planned order release of the component F is to be determined.
Concept Introduction:
The planned order release can be called as method which is based on the specified lead time till the planned receipt date is not received.
(c)
Interpretation: The planned order release of the component I is to be determined.
Concept Introduction:
The planned order release can be called as method which is based on the specified lead time till the planned receipt date is not received.
(d)
Interpretation: The planned order release of the component H is to be determined.
Concept Introduction:
The planned order release can be called as method which is based on the specified lead time till the planned receipt date is not received.
Want to see the full answer?
Check out a sample textbook solutionChapter 8 Solutions
Production and Operations Analysis, Seventh Edition
- Best-Appliance makes high-powered industrial strength microwave oven and wants to create an MRP for their oven assembly with a minimum cost possible. Following table show gross requirements of their product for twelve weeks. Develop a Part Period Balancing (PPB) solution and calculate the total relevant costs for the plan. Week Gross requirements 1 30 Week Gross requirements On-hand at beginning of week 40 On-hand at end of week Order receipt Order release Total relevant cost for this plan is = $ 2 3 30 1 30 4 2 5 40 70 20 Also, for this plan the Holding cost = $2.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40 units. Use the table below to develop a PPB solution for MRP (enter your responses as whole numbers). 3 30 6 7 8 4 5 40 (enter your response as a whole number). 6 ॥ 70 9 10 70 7 20 10 11 8 D 12 50 9 10 11 12 10 70 50arrow_forwardThe MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $10. There is a carrying cost of $0.010 per unit per week. Beginning inventory is 100 units. WEEK 4 10 Gross requirements 40 205 40 20 30 60 80 20 60 100 Use the least total cost and the least unit cost lot-sizing methods to determine the quantity to order with the first order released with each method and which periods' requirements will be covered by that order. Quantity Ordered Periods Covered Least total cost Least unt costarrow_forwardAssume material A calls out material B. Material A has a stock quantity of 20. Material A has a demand for 100 due on 7/2 and there is an order for 80 with a due date of 7/2 and start date of 6/25. What is the requirement date that will be generated for (Enter your answer as a date in the format M/DD; eg product B? 8/1 or 7/12)arrow_forward
- Complete the master productin schedule based on thefollowing information:Week 1 2 3 4 5 6 7 8 9Forecast 320 100 30 110 40 240 290 60 410Customer Orders 60 50 80 20 60 60 0 0 0Projected On-Hand Inventory 600MPS ReleasedMPS DueAvailable-to-promise (ATP) Scheduled production whenever projected on-had inventory drops below 30MPS lot size: 300Production lead time or lead time for MPS releases 1arrow_forwardA firm has the following gross requirements for Item F. If ordering costs are $60 per order and carrying costs are $0.50 per period. If Mult. 60 lot sizing is used, the planned order releases is Group of answer choices 60 in period 2 and 80 in period 3 120 in period 2 and 60 in period 3 80 in period 1 and 0 in period 3 0 in period 1 and 40 in period 3arrow_forwardAssume material A calls out material B (qty per = 1). Material A has a stock quantity of 10. Material A has a demand for 100 due on 7/1 and there is an order for 90 with a due date of 7/1 and start date of 6/15. What is the requirement QUANTITY that will be generated for product B?arrow_forward
- MRP II stands for:a) material resource planning.b) management requirements planning.c) management resource planning.d) material revenue planning.e) material risk planning.arrow_forwardCourtney Kamauf schedules production of a popular Rustic Coffee Table at Kamauf Enterprises, Inc. The tablerequires a top, four legs, 18 gallon of stain, 116 gallon of glue, 2 shortbraces between the legs and 2 long braces between the legs, anda brass cap that goes on the bottom of each leg. She has 100 gallons of glue in inventory, but none of the other components. Allitems except the brass caps, stain, and glue are ordered on a lotfor-lot basis. The caps are purchased in quantities of 1,000, stainand glue by the gallon. Lead time is 1 day for each item. Schedulethe order releases necessary to produce 640 coffee tables on days5 and 6, and 128 on days 7 and 8.arrow_forwardDraw a simple bill-of-materials (BOM) for a smart phone given the following requirements: (a) clearly label the end item and each component, (b) the BOM must contain no more than ten items, (c) the BOM must contain at least three levels (you may count the end-item level zero).arrow_forward
- Exercise 2: The demand per year (D) for product X is 12,100 units. The costs of placing an order (S) are $4.50. The unit cost (C) of the item is $25.00. The maintenance cost (H) per unit per year is 30% of the item's cost. 1. Use the economic order quantity (EOQ) model to determine: *Optimal quantity to order* The expected number of orders*Optimal time between orders*The total annual cost of maintaining that optimal amountNOTE: Show calculations of how you arrived at each amount 2. Answer, what are the potential benefits of using EOQ analysis for inventory management? How can you help businesses strike a balance between inventory holding costs and ordering costs?arrow_forwardA company manufactures two wheeler passengers’ helmets. The initial stock on hand is 5000 units. The carrying cost is Rs. 2 per helmet per week and the lead time is two weeks. The ordering cost per order is Rs. 5000. The MPS of the final requirements is shown below. Develop a Material Requirement Plan (MRP I) by using EOQ method and determine the total inventory cost for the same. Week 1 2 3 4 5 6 7 8 Projected requirements 10000 8000 15000 7000 16000 5000 15000 11000arrow_forward1. Speedy, Inc. is a company that produces automotive electrical components. AI5I is a common part for all its products. Consider the following grass requirements and inventory data for AISI part: Week 3 6 7 Grass requirements 40 30 30 70 20 Inventory Data: Lead time Beginning inventorry Scheduled receipts Holding cost Setup cost 1 week 40 $2.50/unit/week S150 Based on the L4L. lot-sizing rule, develop a Material Requirements Plan (MRP) for the next 8 weeks for A15I part. Item: A151 Week 5 Lot size: L4L 1 2 4 7 8 Lead time: 1 Gross Requirements Scheduled Receipts On Hand Inventory Net Requirements Planned Order Receipts Planned Order Releases (ii) Based on the FOQ - 57 units lot-sizing rule, develop a Material Requirements Plan (MRP) for the next 8 weeks for A151 part. Item: A151 Lot size: FOQ 57 Lead time: 1 Gross Requirements Scheduled Receipts On Hand Inventory Net Requirements Planned Order Receipts |Planned Order Releases Week 1 2 4 5 7 8arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.