Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 8, Problem 49AP

a)

Summary Introduction

Interpretation: Determine the ordering policy is recommended by the silver-Meal heuristic.

Concept Introduction: Silver-Meal heuristic mainly focused on the manufacture planning in the production companies. It determines that within the minimum cost level, the quantities of the products will be produced by the company.

a)

Expert Solution
Check Mark

Answer to Problem 49AP

The order policy according to silver meal heuristic method is (56,0,52,0,0,114,0,0,106,0)

Explanation of Solution

Given information: The anticipated demand for an inventory is as follows:

    Week12345678910
    Demand2234321284454167630

The inventory costs 65 cents each and holding cost (h) is calculated on annual interest rate at 0.5% per week. The set up cost (K) is $200.

The order policy of the inventory under silver meal method can be calculated as follows:

According to silver meal method the average cost per period C (T) is a function of the average holding and set up cost per period for T number of Periods. The production in period 1 is equal to the demand in that period 1 to incur the order cost K.

Hence C(1)=K

And C(2)=(K+hr2)/2

  C(3)=(K+hr2+2hr3)/3

And general equation is C(j)=(K+hr2+2hr3+...+(j1)hrj)/j

Once C(j)C(j1), stop the function and set y=r1+r2+r3+....rj1

Now, calculate the order policy using the above formula as follows:

Starting in period 1:

  K=$200

  h=(0.005)(0.65)

(Since h is calculated on 0.5% annual interest rate with each unit cost at 65cents)

  h=3.25 Per thousand

  r=(22,34,32,12,8,44,54,16,76,30)

Starting from period 1

  C(1)=200

  C(2)=(200+(3.24)(34))/2=155.25

  C(3)=[200+(3.24)(34)+(2)(3.24)(32)]3=172.8

Stop the process since C(3)C(2),

  y1=r1+r2

  y1=22+34=56

Starting in period 3:

  C(1)=200

  C(2)=[200+(3.25)(12)]2=119.5

  C(3)=[200+(3.25)(12)+(2)(3.25)(8)]3=97

  C(4)=[200+(3.25)(12)+(2)(3.25)(8)+(3)(3.25)(44)]4=180

Stop the process since C(4)C(3),

  y3=r3+r4+r5

  y3=32+12+8=52

Starting in period 6:

  C(1)=200

  C(2)=[200+(3.25)(54)]2=187.75

  C(3)=[200+(3.25)(54)+(2)(3.25)(16)]3=159.8

  C(4)=[200+(3.25)(54)+(2)(3.25)(16)+(3)(3.25)(76)]4=305.12

Stop the process since C(4)C(3),

  y6=r6+r7+r8

  y6=44+54+16=114

Starting in period 9:

  y9=r9+r10

  y9=76+30=106

b)

Summary Introduction

Interpretation: Determine the ordering policy is recommended by the part period balancing heuristic.

Concept Introduction: one of the lot-sizing technique is to implementing the lowest-cost with the interconnection between costs of order and carrying cost for the inventory is generally known as Part period balancing.it is more effective for the product whose demand is unstable.

b)

Expert Solution
Check Mark

Answer to Problem 49AP

The order policy according to the part period balancing heuristic method will be

is (56,0,52,0,0,98,0,92,0,30)

Explanation of Solution

Given information: The anticipated demand for an inventory is as follows:

    Week12345678910
    Demand2234321284454167630

The inventory costs 65 cents each and holding cost (h) is calculated on annual interest rate at 0.5% per week. The set up cost (K) is $200.

The order policy according to part period balancing method can be calculated as follows:

In this method the order horizon that equates holding and setup cost over that period has to be calculated as follows:

  K=$200

  h=(0.005)(0.65)

(Since h is calculated on 0.5% annual interest rate with each unit cost at 65cents)

  h=3.25 Per thousand

  r=(22,34,32,12,8,44,54,16,76,30)

Starting from period 1:

    PeriodHolding Cost
    2110.5
    3318.5

Since the setup cost $200 is closer at period 4, stop and equate

  y1=r1+r2

  y1=22+34=56

Starting in period 3:

    PeriodHolding Cost
    225
    365
    4520

Since the setup cost $200 is closer to 4 than 3, stop and equate

  y3=r3+r4+r5

  y3=32+12+8=52

Starting in period 6:

    PeriodHolding Cost
    2175.5
    3279.5

Since the setup cost $200 is closer to 3, stop and equate

  y6=r6+r7

  y6=44+54=98

Starting in period 8:

    PeriodHolding Cost
    2247

Since the setup cost $200 is closer to 2, stop and equate

  y8=r8+r9

  y8=16+76=92

c)

Summary Introduction

Interpretation: Determine the ordering policy is recommended by the least unit cost heuristic.

Concept Introduction: Least unit cost heuristic technique is one of the time-varying demand pattern technique.one of the dynamic lot-sizing concept is that interrelated between the order cost and carrying cost of the inventory for the every lot size is defined as

Least Unit Cost (LUC).

c)

Expert Solution
Check Mark

Answer to Problem 49AP

The order policy according to the least unit cost heuristic method will be

is (56,0,44,0,106,0,0,92,0,30)

Explanation of Solution

Given information: The anticipated demand for an inventory is as follows:

    Week12345678910
    Demand2234321284454167630

The inventory costs 65 cents each and holding cost (h) is calculated on annual interest rate at 0.5% per week. The set up cost (K) is $200.

The order policy according to lease unit cost(LUC) method can be calculated as follows:

LUC divides the average cost per period C (T) by the total number of units demanded. Hence C(1)=K/r1

And C(2)=(K+hr2)+(r1+r2),

And general equation is C(j)=(K+hr2+2hr3+...+(j1)hrj)/(r1+r2...+rj)

Once C(j)C(j1), stop the function and set y=r1+r2+r3+....rj1

  r=(22,34,32,12,8,44,54,16,76,30)

Starting from period 1

  C(1)=200/22=0.09

  C(2)=(200+(3.25)(34))/(22+34)=5.54

  C(3)=[200+(3.25)(34)+(2)(32)]22+34+32=5.89

Stop the process since C(3)C(2),

  y1=r1+r2

  y1=22+34=56

Starting in period 3:

  C(1)=200/32=6.25

  C(2)=[200+(3.25)(12)](32+12)=5.43

  C(3)=[200+(3.25)(12)+(2)(3.25)(8)](32+12+8)=5.6

Stop the process since C(3)C(2),

  y3=r3+r4

  y3=32+12=44

Starting in period 5:

  C(1)=200/8=25

  C(2)=[200+(3.25)(44)](8+44)=6.60

  C(3)=[200+(3.25)(44)+(2)(3.25)(54)](8+44+54)=6.54

  C(4)=[200+(3.25)(44)+(2)(3.25)(54)+(3)(3.25)(16)](8+44+54+16)=7.97

Stop the process since C(4)C(3),

  y5=r5+r6+r7

  y5=8+44+54=106

Starting in period 8:

  C(1)=200/16=12.5

  C(2)=[200+(3.25)(76)](16+76)=4.85

  C(3)=[200+(3.25)(76)+(2)(3.25)(30)](16+76+30)=5.2

Stop the process since C(3)C(2),

  y8=r8+r9

  y8=16+76=92

  y10=r10=30

d)

Summary Introduction

Interpretation: Determine the method resulted in the lowest-cost policy for the given problem.

Concept Introduction: Least unit cost method makes the present period of the demands and evaluates the period of the future. Adding the carrying cost for the setup and the period of the inventory cost, the least unit cost will be occur.

d)

Expert Solution
Check Mark

Answer to Problem 49AP

The least expensive method is the least unit cost method with a total cost of $1351

Explanation of Solution

Given information: The anticipated demand for an inventory is as follows:

    Week12345678910
    Demand2234321284454167630

The inventory costs 65 cents each and holding cost (h) is calculated on annual interest rate at 0.5% per week. The set up cost (K) is $200.

Comparison of the three methods can be calculated as follows:

Calculate the total cost of the inventory for the three months. The method which yields less cost is the lowest cost policy.

The total cost under silver meal method can be calculated as follows:

The method required is 4 set ups

The total set up cost is 4×200=800

The total holding cost is (3.25)(22+32+44+76)=565.5

The total cost 800+565.5=1365.5

The total cost under silver-meal heuristic is $1365.5

The total cost under least unit cost method can be calculated as follows:

The method required is 5 set ups

The total set up cost is 5×200=1000

The total holding cost is (3.25)(22+32+8+16+30)=351

The total cost 1000+351=1351

The total cost under least unit cost method is $1351

The total cost under part period balancing method can be calculated as follows:

The method required is 5 set ups

The total set up cost is 5×200=1000

The total holding cost is (3.25)(22+32+44+16+30)=468

The total cost 1000+468=1468

The total cost under part period balancing method is $1468

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A component used in a manufacturing facility is ordered from an outside supplier.Because the component is used in a variety of end products, the demand is high. Estimated demand (in thousands) over the next 10 weeks isWeek 1 2 3 4 5 6 7 8 9 10Demand 22 34 32 12 8 44 54 16 76 30The components cost 65 cents each and the interest rate used to compute the holding cost is 0.5 percent per week. The fixed order cost is estimated to be $200. (Hint:Express h as the holding cost per thousand units.)d. Which method resulted in the lowest-cost policy for this problem?
A component used in a manufacturing facility is ordered from an outside supplier.Because the component is used in a variety of end products, the demand is high. Estimated demand (in thousands) over the next 10 weeks isWeek 1 2 3 4 5 6 7 8 9 10Demand 22 34 32 12 8 44 54 16 76 30The components cost 65 cents each and the interest rate used to compute the holding cost is 0.5 percent per week. The fixed order cost is estimated to be $200. (Hint:Express h as the holding cost per thousand units.)a. What ordering policy is recommended by the Silver–Meal heuristic?
A component used in a manufacturing facility is ordered from an outside supplier.Because the component is used in a variety of end products, the demand is high. Estimated demand (in thousands) over the next 10 weeks isWeek 1 2 3 4 5 6 7 8 9 10Demand 22 34 32 12 8 44 54 16 76 30The components cost 65 cents each and the interest rate used to compute the holding cost is 0.5 percent per week. The fixed order cost is estimated to be $200. (Hint:Express h as the holding cost per thousand units.)c. What ordering policy is recommended by the least unit cost heuristic?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY