Interpretation:Compare the various lot sizing methods for their positive and negative characteristics.
Concept Introduction:Determination of the lot size to be ordered for procurement or production is one of the key outputs of any MRP system. This utilizes various lot-sizing techniques each of which has unique characteristics. Every user, therefore, has to decide which technique to use for optimum results in his/her situation.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component
combinations. Identical bicycles are produced in lots of 110. The projected demand, lot size, and time standards are
shown in the following table:
i
Item
Demand forecast
Lot size
Standard processing time
Standard setup time
Touring
4,000 units/year
130 units
0.20 hour/unit
2 hours/lot
Mountain
10,000 units/year
110 units
0.50 hour/unit
3 hours/lot
The shop currently works 8 hours a day, 5 days a week, 48 weeks a year. It operates five workstations, each producing
one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations
will be required next year to meet expected demand without using overtime and without decreasing the firm's current
capacity cushion?
The number of workstations required next year is. (Enter your response rounded up to the next whole number.)
Electro Fans has just received an order for one thousand 20Ëť fans due in week 7. Each fan consists of a housing assembly, two grills and a fan assembly. The housing assembly consists of a frame, two supports and a handle. The following table gives lead times, on-hand inventory, and scheduled receipts.
Table 1.1:Â Lead time and quantity on hand
Item
Lead Time
Qty on hand
Lot size#
Scheduled receipt
20Ëť Fan
 Housing
     Frame
      Supports (2)
      Handle
 Grills (2)
 Fan Assembly    Â
Â
1
1
2
1
1
2
3
Â
80
90
-
50
400
200*
150
Â
-
-
-
100
400
450
-
Â
Â
Â
Â
Â
Â
Â
50 fan assembly in week 2
Â
* In week 3 it was found that 50% of the on hand inventory of the grills was damaged.
# Items without any lot size given should be considered as lot-for-lot.
Â
(i) Construct a product structure.
(ii) Construct a time-phased product structure.
(iii) Prepare a net requirement plan.
Discuss the role of data analytics in optimizing inventory within the Wilson approach.
Chapter 8 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 8.1 - Prob. 1PCh. 8.1 - Prob. 2PCh. 8.1 - Prob. 3PCh. 8.1 - Prob. 4PCh. 8.1 - Prob. 5PCh. 8.1 - Prob. 6PCh. 8.1 - Prob. 7PCh. 8.1 - Prob. 8PCh. 8.1 - Prob. 9PCh. 8.2 - Prob. 10P
Ch. 8.2 - Prob. 11PCh. 8.2 - Prob. 12PCh. 8.2 - Prob. 13PCh. 8.2 - Prob. 14PCh. 8.2 - Prob. 15PCh. 8.2 - Prob. 16PCh. 8.2 - Prob. 17PCh. 8.2 - Prob. 18PCh. 8.2 - Prob. 19PCh. 8.2 - Prob. 20PCh. 8.2 - Prob. 21PCh. 8.2 - Prob. 22PCh. 8.3 - Prob. 23PCh. 8.3 - Prob. 24PCh. 8.3 - Prob. 25PCh. 8.4 - Prob. 26PCh. 8.4 - Prob. 27PCh. 8.4 - Prob. 28PCh. 8.4 - Prob. 29PCh. 8.5 - Prob. 30PCh. 8.5 - Prob. 31PCh. 8.5 - Prob. 32PCh. 8.5 - Prob. 33PCh. 8.5 - Prob. 34PCh. 8.6 - Prob. 35PCh. 8.6 - Prob. 36PCh. 8.6 - Prob. 37PCh. 8.6 - Prob. 38PCh. 8.6 - Prob. 39PCh. 8.6 - Prob. 40PCh. 8 - Prob. 41APCh. 8 - Prob. 42APCh. 8 - Prob. 43APCh. 8 - Prob. 44APCh. 8 - Prob. 45APCh. 8 - Prob. 46APCh. 8 - Prob. 48APCh. 8 - Prob. 49APCh. 8 - Prob. 50APCh. 8 - Prob. 51AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The inventory control models are often labeled independent demand models and MRP is often labeled a dependent demand system. What do the terms independent and dependent mean in this context?arrow_forwardThe ABC Company performs its expenditure cycle activities using its integrated ERP system as follows:• Employees in any department can enter purchase requests for items they note as ei- ther out of stock or in small quantity.• The company maintains a perpetual inventory system.• Each day, employees in the purchasing department process all purchase requestsfrom the prior day. To the extent possible, requests for items available from the same supplier are combined into one larger purchase order to obtain volume dis- counts. Purchasing agents use the Internet to compare prices in order to select sup- pliers. If an Internet search discovers a potential new supplier, the purchasing agent enters the relevant information in the system, thereby adding the supplier to the approved supplier list. Purchase orders above $10,000 must be approved by the purchasing department manager. EDI is used to transmit purchase orders to most suppliers, but paper purchase orders are printed and mailed to…arrow_forwardIf the the Net Requirement for a product for a particular time period in a MRP problem is 101 and the organization uses an ordering policy of Lot-for-Lot, what would be the Planned Order Receipt?arrow_forward
- Explain the practical application and significance of the Economic Order Quantity (EOQ) formula within the Wilson approach.arrow_forwardWhy do MRP computer programs store single-level bills?arrow_forwardCan the optimal stocking level in the single-period model ever be less than expected demand?Explain briefly.arrow_forward
- Why is accurate inventory such an important issue at Wheeled Coach?arrow_forwardHeather​ Adams, production manager for a Colorado exercise equipment​ manufacturer, needs to schedule an order for 50​ UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume​ lot-for-lot ordering.  Item  Lead Time  ​On-Hand Inventory  Components  Stepper  2  20  A(2)​, B(2)​, C(2)  A  1  10  D(1)​, F(2)  B  2  20  E(2)​, F(3)  C  2  10  D(2)​, E(1)  D  1  15   E  2  5   F  2  20   ​c) Develop a net material requirements plan for F ​(enter your responses as whole​ numbers).   Week   Lead Time   Item   1  2  3  4  5  6  7  8  ​(weeks)   F  Gross req          2    On hand            Net req     enter your response here  enter your response here       Order receipt     enter your response here  enter your…arrow_forwardChallenge 5: For a given item, suppose these are our net requirements over the coming 6 weeks: Week 1 2 3 4 5 6 Net Req's 140 35 85 120 60 80 Suppose we enter this schedule horizon with 60 units in inventory. Further suppose that: Setup cost is S200 Holding cost (per unit per week of average inventory) is $2 If we are using Part-Period Balancing to set order quantities, for how many units would our Week 1 arrival/receipt be?arrow_forward
- Heather​ Adams, production manager for a Colorado exercise equipment​ manufacturer, needs to schedule an order for 50​ UltimaSteppers, which are to be shipped in week 10. Subscripts indicate quantity required for each parent. Assume​ lot-for-lot ordering. Item Lead Time ​On-Hand Inventory Components Stepper 2 10 A(2)​, B(2)​, C(1) A 1 10 D(1)​, F(2) B 2 20 E(1)​, F(3) C 3 10 D(2)​, E(3) D 2 15  E 2 5  F 2 20   ​c) Develop a net material requirements plan for F ​(enter your responses as whole​ numbers).    Week  Lead Time Item  3 4 5 6 7 8 9 10 ​(weeks) F Gross req    enter your response here enter your response here    2  On hand    enter your response here enter your response here     Net req    enter your response here enter your response here     Order…arrow_forwardAssume that you are the manager of Assembly, Inc. You have just received an order for 40 units ofan industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of thoseorders, given that subassembly G must be ordered in multiples of 80 units and all other componentsare ordered lot-for-lot. Assume that the components are used only for this particular robot.Item Lead Time (weeks) On Hand ComponentsRobot 2 10 B, G, C(3)B 1 5 E, FC 1 20 G(2), HE 2 4 —F 3 8 —G 2 15 —H 1 10 —arrow_forward1. Which of the following statements about lot-sizing rules for MRP is true? a) The periodic order quantity (POQ) rule generates a higher level of average inventory since it creates inventory remnants. b) FOQ is a dynamic lot-sizing rule which reduces the amount of inventory, by doing a better job of matching the order quantity to the projected on-hand inventory quantity. c) The lot for lot rule minimizes inventory investment but maximizes the number of orders placed. d) In general, static lot-sizing rules introduce greater instability into the production process 2. Which one of the following is a reason to have small inventories? a) To improve customer service b) To reduce ordering costs c) To reduce equipment setup costs d) To reduce interest expense or opportunity costs  3. Which one of the following is the most likely example of dependent demand for an MRP controlled item? a) Demand for spare parts b) Demand directly from customers c) Demand from quality control department for…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY