Chapter 3, Problem 25PE
Explanation of Solution
Network Diagram:
The network diagram showing critical path is:
Explanation:
- In a network diagram, activities are represented in circles and arrows represent the flow of activities.
- In the above network diagram, there are 7 activities which are A, B, C, D, E, F and G...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Draw a Gantt chart for the tasks shown inProblem and Exercise 3-26.
Your task for this assignment is to create a network diagram for two projects. The activity,
immediate predecessor and duration are given. You are to layout-long-hand or using some
software-a network diagram for each project. For each diagram conduct a forward and
backward pass, calculate the slack, and identify the critical path. When noting your early start,
early finish, late start, late finish and slack, please use the format provided.
Project 1
Activity
Immediate Predecessor
Duration
A
none
3
В
A
4
none
6
D
none
2
D
5
F
В, С, Е
2
Project 2
Activity
Immediate Predecessor
Duration
A
none
6
B
none
3
A
9
B
E
в
4
D
2
G
E
8.
*Note: please use this format.
Early
Start
Duration Early
Finish
Activity
Float
Late
Start
Late
Finish
Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided."
Project 1
Chapter 3 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Suppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?arrow_forwardDraw Activity diagram for this scenario When the employee ( customer to us ) encounters an issue he cant solve he goes to tawasol ( the company ticketing system ) and open a ticket for the issue in the correct section and select the issue genre, explain it and add his contact info then the ticket get assigned automatically by the system to the right IT support team, from there the team in head quarter office in Riyadh assign the task to specific member based on geographic location of the issue and the nature of the issue and the competence needed. After that the team member can see it in his/her ticketing system and can assign the status of the process is it active, pending for some reason or resolved . Then the assigned member will contact the customer to further understand the issue and decide if it could be done remotely or physically, if remotely then the assigned member need to contact the network team to allow access for remote applications on that network. Then when the issue is…arrow_forwardMake a SDLC Gantt Chart with 10 phases and add as much sub-tasks in them as you can. (of any duration)arrow_forward
- As a project manager of a Software project, you have received given data about the different type of Issues identified in the project: – Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences. Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forwardFor the following activities, draw the network diagram and by using forward and backward pass, determine:-1. Project duration.2. Critical path.arrow_forwardDraw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated durationarrow_forward
- Draw an Activity-on-Arrow diagram using the following task diagram below. information. The task names have been shortened to just letters. Also label the critical path. Task A, no dependency, 5 days Task B, no dependency, 2 days Task C, no dependency, 7 days Task D, depends on Task A, 4 days Task E, depends on Task B and Tack C, 11 days Task F, depends on Tack C, 6 days Task G, depends on Task D and Task E, 5 days Task H, depends on Task E, 2 days Task I, depends on Task E and Task F, 4 days Task J, depends on Task H and Task I, 3 daysarrow_forward1-Draw the network diagram of the activities listed in the table below using Activity on Node. 2-Find the critical path and the duration of the project. 3-Find the values of ES, EC, LS, and LC of the events 4- Find the values of TF and FF for the activitiesarrow_forward1. Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration. 2. Identify all the paths on the network diagram and note how long they are. 3. What is the critical path for this project and how long is it? 4. What is the shortest possible time needed to complete the project?arrow_forward
- Draw an activity diagram using the information belowarrow_forwardAs a senior studying IT at CTU, your supervisor has requested that you present a plan for consideration and approval. Produce a research proposal of about 1600 words on a topic that interests you, paying special attention to the following: Five sections make up a research paper: the introduction (1), the methods (II), the issue statement (II), the goals (III), the significance (IV), and the literature review (V).arrow_forwardemaining Time: 1 hour, 23 minutes, 24 seconds. euestion Completion Status: QUESTION 13 Identify the critical path in the following Network diagram and write the total duration required to complete the project. Note: The numbers given in the diagram are days. 11 12 13 10 6. T TTArial 3 (12pt) v T- Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Answer 道 F3 F4 F5 F6 F7 F8 14 F9 F10 Pause $ & %23arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning