Network diagram:

The network diagram for the activities:

Explanation of Solution

Earliest expected completion time:

  • The earliest expected completion time is calculated by using time of each activity.
  • The box in a network diagram represents the activity. Each box consists of activity and time.
  • The start state is activity 1 and end state is 10. Each box consists of four values Early finish, Early start, Late start and Late finish.
  • The early start for first activity is 0 because it contains no predecessor.
  • Early finish is the sum of early start and time. Early start of the next activity is the early finish of its predecessor activity...

Explanation of Solution

Critical path:

  • For calculating critical path, select all activities that contain slack value 0...

Explanation of Solution

Activity 6 revised to take 6 weeks:

  • If the time of activity 6 is changed to 6 weeks instead of 2 weeks, then the critical will be changed...

Blurred answer
Students have asked these similar questions
Suppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?
Suppose that you are part of a project team and it becomes clear to you that one of the team members is not “pulling his weight.” What should you do if you are the project leader? What should you do if you are not the project leader?
Explain the project execution Spiral Model and V Model.

Chapter 3 Solutions

Essentials of Systems Analysis and Design (6th Edition)

Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Enhanced Discovering Computers 2017 (Shelly Cashm...
Computer Science
ISBN:9781305657458
Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:Cengage Learning