Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Expert Solution & Answer
Chapter 3, Problem 26PE
Explanation of Solution
Deriving Earliest Start Time, Earliest Finish Time and Slack:
Earliest Completion Time:
It is also known as Early Finish and is the amount required to complete the task of the project. The formula for calculating Early Finish is,
Latest Completion Time:
It is also known as Late Finish and is the latest time for the task to be completed. The formula for calculating Late Finish is,
Slack:
It is the amount of time that an activity can be delayed. It is the difference between Latest Finishing Time and Earliest Finishing Time,
Table showing earliest and latest expected time:
Task | Preceding Event |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
emaining Time: 1 hour, 23 minutes, 24 seconds.
euestion Completion Status:
QUESTION 13
Identify the critical path in the following Network diagram and write the total duration
required to complete the project.
Note: The numbers given in the diagram are days.
11
12
13
10
6.
T TTArial
3 (12pt)
v T-
Click Save and Submit to save and submit. Click Save All Answers to save all answers.
Save All Answer
道
F3
F4
F5
F6
F7
F8
14
F9
F10
Pause
$
&
%23
in the textbook. All duration estimates or
hes are in days, and the network proceeds from Node 1 to
Node 9
Draw an AOA network diagram representing the project. Put the
node numbers in circles and draw arrows from node to node,
1.
labeling each arrow with the activity letter and estimated time.
Draw an PDM network diagram representing the project. Determine
the early start,early finish,late start and late finish date for every
activity and mark them at the four corners of each activity.
2.
3.
Identify all of the paths on the network diagram and note how long
they are, using Figure 6-8 as a guide for how to represent each
path.
What is the critical path for this project and how long is it?
What is the shortest possible time needed to camnl
4.
5.
Formation Technology Project
anagement, Sevanti
Suppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?
Chapter 3 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- set of concurrent activities are meant to pass a course. The process is as the following: 1- Student has to attend all classes and not to miss more than 25% of the classes. 2- Students selects a paper for presentation and gives a presentation on an assigned date. 3- Student has to choose a project topic and submits at the end of the course Draw a State Machine Diagram. Make sure to define events, conditions, actions for transitions in your diagram, where appropriate.arrow_forwardExample 11: - Draw the network diagram using the arrows method for the project whose activities are listed in the table below, then calculate the early and late beginnings and ends, the free and surplus time for the activities, then determine the critical events, the critical path, and the project completion time Activity A В B C D E F Duration (day) | Dependency 10 18 12 15 А C B.D В 8 17arrow_forwardAt Riverside Financial, where you work as a project manager, you have been asked to conduct user training sessions during the implementation phase for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): First, you need to send an e-mail message to all department managers announcing the training sessions (3 days). After the e-mail message goes out, two tasks can begin at the same time: You can develop the training material (7 days) and confirm arrangements for the training facility you plan to use (15 days). As soon as the training material is complete, you can work on two tasks at once: Arrange to have copies of handout material printed (7 days) and develop a set of PowerPoint slides (8 days). When the PowerPoint slides are ready, you conduct a practice training session with the instructor who will assist you (3 days). Finally, when the practice session is over, the handout material is ready, and…arrow_forward
- Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided. Project 1 Activity Immediate Predecessor Duration A none 3 В A 4 none 6 D none 2 D 5 F В, С, Е 2 Project 2 Activity Immediate Predecessor Duration A none 6 B none 3 A 9 B E в 4 D 2 G E 8. *Note: please use this format. Early Start Duration Early Finish Activity Float Late Start Late Finisharrow_forwardCreate an ER/EER diagram for the following 1. Professors have an SSN, a name, an age, a rank, and a research specialty. Projects have a project number, a sponsor name (e.g., NSF), a starting date, anending date, and a budget. Graduate students have an SSN, a name, an age, and a degree program (e.g., M.S.or Ph.D.). Each project is managed by one professor (known as the project’s principalinvestigator). Each project is worked on by one or more professors (known as the project’s co-investigators). Professors can manage and/or work on multiple projects. Each project is worked on by one or more graduate students (known as the project’sresearch assistants). When graduate students work on a project, a professor must supervise their work on the project. Graduate students can work on multiple projects, in which case they will have a (potentially different) supervisor for each one. Departments have a department number, a department name, and a main office. Departments have a professor (known…arrow_forwardYour task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided." Project 1arrow_forward
- Heading 3 Title Homework 2 Consider Table 6-2 on P263 in the textbook. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9 Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. Draw an PDM network diagram representing the the early start,early finish,late start activity and mark th 1. 2. 3. ldarrow_forward1. Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration. 2. Identify all the paths on the network diagram and note how long they are. 3. What is the critical path for this project and how long is it? 4. What is the shortest possible time needed to complete the project?arrow_forwardGCS has many customers. Each customer has a customer ID, name, phone number, and region. GCS works by projects. A project is based on a contract between the customer and GCS to design, develop, and implement a computerized solution. Each project has specific characteristics such as the project ID, the customer to which the project belongs, a brief description, a project date (the date the contract was signed), an estimated project start date and end date, an estimated project budget, an actual start date, an actual end date, an actual cost, and one employee assigned as the manager of the project. The actual cost of the project is updated each Friday by adding that week’s cost to the actual cost. The week’s cost is computed by multiplying the hours each employee worked by the rate of pay for that skill. The employee who is the manager of the project must complete a project schedule, which effectively is a design and development plan. In the project schedule (or plan), the manager must…arrow_forward
- a) A network diagram is an important scheduling tool that graphically portrays the logical relationship and sequencing of activities and events on a project. Task Immediately Preceding Activity A B с D A E B F B G C H D I G J F, H, I Based on the information in the table above, draw an Activity-on-Arrow network diagram to depict the logical relationships among the activities of the project. b) One of the logical rules on a network diagram states that "No two activities may share the same 'head' and 'tail' events". Explain why this is the case and STATE any TWO implications for the project if this rule is disregarded.arrow_forwardConsider the following project activities: Activity Name A B C D E F G Activity Name A B C D E F G Immediate Predecessor (list number/ name, separated by ',') Answer Activity Time 6 9 12 8 9 Fill the given table with the required data and draw the network diagram for the above project activities to find the critical path. 6 5 Project Completion Time = The Critical Path is= A A, B D C, E E Normal Time 6 Days 9 12 8 9 6 5 Earliest Earliest Latest Latest Slack Start Finish Start Finish (LS) (EF) (ES) (LF) (LS-ES)arrow_forwardFor a particular project, consider following list of Activities, their duration in Days and their Predecessor activities. Activity Days Precedents A 3 - B 15 A C 5 A D 60 A E 6 D F 40 B G 10 C,E H 7 F I 6 G J 12 H,I By using network schedule technique, draw a Network Diagram of above enlisted activities.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning