Essentials of Systems Analysis and Design (6th Edition)
Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
bartleby

Concept explainers

Expert Solution & Answer
Book Icon
Chapter 3, Problem 26PE

Explanation of Solution

Deriving Earliest Start Time, Earliest Finish Time and Slack:

Earliest Completion Time:

It is also known as Early Finish and is the amount required to complete the task of the project. The formula for calculating Early Finish is,

  EF = ES + Duration

Latest Completion Time:

It is also known as Late Finish and is the latest time for the task to be completed. The formula for calculating Late Finish is,

   LF = LS + Duration

Slack:

It is the amount of time that an activity can be delayed. It is the difference between Latest Finishing Time and Earliest Finishing Time,

  Slack = Latest Expected Time – Earliest Expected Time

Table showing earliest and latest expected time:

TaskPreceding Event

Blurred answer
Students have asked these similar questions
emaining Time: 1 hour, 23 minutes, 24 seconds. euestion Completion Status: QUESTION 13 Identify the critical path in the following Network diagram and write the total duration required to complete the project. Note: The numbers given in the diagram are days. 11 12 13 10 6. T TTArial 3 (12pt) v T- Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Answer 道 F3 F4 F5 F6 F7 F8 14 F9 F10 Pause $ & %23
in the textbook. All duration estimates or hes are in days, and the network proceeds from Node 1 to Node 9 Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, 1. labeling each arrow with the activity letter and estimated time. Draw an PDM network diagram representing the project. Determine the early start,early finish,late start and late finish date for every activity and mark them at the four corners of each activity. 2. 3. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as a guide for how to represent each path. What is the critical path for this project and how long is it? What is the shortest possible time needed to camnl 4. 5. Formation Technology Project anagement, Sevanti
Suppose you are the project manager for the following project: First,draw a network diagram for the project. Determine the critical path andslack times for all of the tasks. This completes your plan for the projectschedule. During project execution, you become aware of the need tochange the duration of Task 4 to five days.Meanwhile, Task 3 has been finished one day early, so it only took one day to do. What, ifany, effects do these changes have on your project? What would have happened if you had notbeen monitoring the status of the project?

Chapter 3 Solutions

Essentials of Systems Analysis and Design (6th Edition)

Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning