Textbook Question
Chapter 3, Problem 15M
A systems analyst with a diverse set of skills—management, leadership, technical, conflict management, and customer relationship—who is responsible for initiating, planning, executing, and closing down a project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Shining Stars primary school was the recent recipient of a technology grant to source and implement a school management system. The school administrator is not technology savvy and therefore sought advice from three of the board members who were knowledgeable in the information systems and technology field.
One director advised the administrator to purchase an off-the-shelf solution that would allow the school to get the system configured and up and running in a short period with reasonable costs.
The second advised the administrator to invest in the development of a unique system to meet the custom requirements of the school’s administration. He suggested that this would create a closer fit to the school’s needs compared to purchasing software, but will cost more.
The third director suggested using an open-source solution which would have little if any upfront costs but may require some customization.
The school administrator must decide about which solution to go with.
Are…
Executing processes exclude coordinating people and other resources to carry
out the various plans and create the products, services, or results of the project
or phase
Select one:
True
False
A ______ is a series of actions directed toward a particular result.
Select one:
a. project
b. process
c. plan
d. goal
scenarios of a project activities (tables given below) and their required times to be completed in
addition to their predecessors for developing a 'Hehsite':
Activity
Description
Duration (days)
Preceding Activities
Determine user needs
Review s/w and languages
Purchase software
5
D.
Design format and style
Write programs
Review outcome product with user
Make revisions
H.
Select server site
E
Install on server
D. F
Test
G, H, I
1. Draw the path.
2. Calculate the carly finishing time (forwards calculations)
3. Highlight the total time to complete the project (days or weeks)
4. Calculate the late finishing time (backwards calculations)
5. Calculate the slack time of the non-critical path activities
6. Identify the critical path (highlight critical path activities)
7. what would happen if revised to take seven weeks instead of five weeks
Chapter 3 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Identify an information system frequently employed by people in a career field you are interested in. Discuss how you might be involved as a user in the development or acquisition of such a system for your future company. Identify three things that you could do as a project participant that would greatly improve the likelihood of a successful project. Now, identify three things that you could do (or fail to do) that could greatly diminish the probability of success of such a project.arrow_forward____________ processes include coordinating people and other resources to carry out project plans and create the products, services, or results of the project or phase. a. Initiating b. Planning c. Executing d. Monitoring and controlling e. Closingarrow_forwardThe purpose of the system investigation phase is to ________________. a. define what the information system must do to solve the problem or capitalize on the opportunity b. gain a clear understanding of the specifics of the problem to solve or the opportunity to address c. gather data on the existing system and determine the requirements for the new system d. identify, confirm, and prioritize system requirementsarrow_forward
- ____________ involves measuring progress toward project objectives and taking corrective actions. Initiating Planning Executing Monitoring and controlling Closingarrow_forwardYou and your team have been hired to perform a system investigation for a fast food restaurant that wants to implement new tools and processes to improve its customer service. Currently, the restaurant has a poor reputation for not correctly filling customers orders and for taking too long to do it. Perform a functional decomposition to define the scope and basic requirements of such a system. Brainstorm some ideas to improve the situation, and choose one to pursue based on its technical, economic, legal, operational, and schedule feasibility.arrow_forwardWhat are the roles and responsibilities of a project sponsor during the different stages of the Systems Development Life Cycle (SDLC)?arrow_forward
- A structured meeting process that can accelerate and improve the efficiency and effectiveness of the investigation, analysis, and design phases of a systems development project Direct observation Surveys All the above O Joint Application Development.arrow_forwardProject Overview The aim of this project is to demonstrate the skills and knowledge of how the processes under project management knowledge areas are carried out through the project management life cycle. You are required to select a specific IT/IS project and apply these skills and knowledge according to the requirements stated below. The project can be implementing/upgrading an infrastructure, a system or both. Major examples of these projects can be (but not limited to): Information system development Smartphone app development Hardware infrastructure development Website/web service development Remember that these are only examples. In your project proposal you need to specify what exactly the project is and what is its main objective(s). Hint: It is recommended that you discuss with your lecturer your selected project to make sure that you are in the right track. This communication is also recommended while you are developing your project proposal, progress report by time.…arrow_forwardWhat is the first step in preparing for an interview? Select one: a.Set the time and location. b.Determine project team members who will participate. c.Build a list of questions and issues to be discusseD. d.Establish the objective of the interview.arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
- Fundamentals of Information SystemsComputer ScienceISBN:9781337097536Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningFundamentals of Information SystemsComputer ScienceISBN:9781305082168Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Fundamentals of Information Systems
Computer Science
ISBN:9781305082168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
9.1.2 Software Development Approaches; Author: EIToppo;https://www.youtube.com/watch?v=Z9znuSQ7Sz8;License: Standard YouTube License, CC-BY