Chapter 3, Problem 31PE
Explanation of Solution
Work breakdown structure for a semester project based on the decomposition:
- The above diagram describes about the work breakdown structure of a semester project.
- The user needs to collect the information about the requirements.
- Depending upon the project scope, related objectives must be made...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Create use case diagram based on the user story
Question 3
Draw a detailed activity Diagram in draw.io and screenshot it for me. ( **Please take note is a detailed activity diagram)
Scenario
The exam unit uses the system after the subject registration period has closed. The system will display a list of subjects that have registered students. Using this list, the exam unit will plan out examination week. Examination week lasts 6 days, from Monday to Saturday. For each day, the exam unit will assign a subject to that day. Each day can have a total of 6 examination hours with subjects having 2- hour or 3-hour examinations. For example, if the subjects are 2-hour examinations, then 3 of them can be scheduled for the day and if the subjects are 3-hour examinations, then only 2 of them can be scheduled for the day. There can also be a mixture of 2-hour and 3-hour examinations. If the exam unit schedules too many examination hours for that day then the day resets and the exam unit needs to reschedule again. This process stops when…
Creating a list like this is very useful when you are specifically looking for itemsin a complex diagram, or you simply want to create some documentation and wan to make sure you are not missing an entity in your thesis or spell a word incorrectly.Write the code
Chapter 3 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Similar questions
- How should a decent data flow diagram be created?arrow_forwardKindly explain the flow of data on the diagramarrow_forwardDuring Unit Testing, distinct test-cases are used to test a specific module or unit. During Unit Testing, what distinct components of a module are tested. Only include those elements in your list.arrow_forward
- In which type of diagram fork and join terms are used?arrow_forwardReview the UML diagram provided for a game software application. A text version is available: Text Version for UML diagram Word Document. You may notice that it is incomplete - it is missing attributes and methods, and only includes a small portion of a complete game application. This is quite common! As a software developer, typically you will be given pieces of the puzzle or tasks to complete as part of a larger project and as a member of a larger team. It takes practice to focus on the information you are given to determine what you have and what steps you need to take to complete the task. Specifically, the game application requires that only one instance of the game be able to exist in memory at any given time. This can be accomplished by creating unique identifiers for each instance of the game. Complete the UML diagram to accurately represent a singleton pattern for the Game Service class. You should replace the question marks in the UML diagram with appropriate static and…arrow_forwardCreate an end of workshop evaluation form.arrow_forward
- I want Activity Diagram Sequence Diagram, Analysis Diagram for this module, pleasearrow_forwardI need help with creating Activity Diagram and Sequence Diagram for the below Use Case Diagram. Please provide Diagrams as well as an explanation.arrow_forwardScenario: The Best Events Company organizes events, and business is booming, so much so that they need your help to manage their service. They want you to create a software system to manage their employees, clients, suppliers, and events. A part of their software requirement is given below. You are required to do a self-study on how event-organizing companies work and create a design for managing the company's functions. In addition to the requirements below, you are encouraged to add more attributes and functionalities to the system. The company has different types of employees, such as, Sales Managers, Salespersons, Marketing Managers, Marketers, Accountants, Designers and Handymen. Some details required for employees include name, employee ID, department, job title, basic salary, age, date of birth, and passport details are also stored in the system. The table below provides a glimpse of how employees are managed. It is clear from the table that Susan Meyers manages both Shyam…arrow_forward
- Also Draw Schema Diagramarrow_forwardIf you're performing user research, it's a good idea to break down the overall design into many different user views.arrow_forwardA project is proposed to design an assessment management system to keep track of course assessment submission in a university. Each course has unique ID, name, instructor, at least fifteen students and at least one subject. Each subject has a number, name, description, and at least one course assessment to be done. The subject number is unique for each course. Each assessment has a number that is unique for the given subject and has due submission date and time. In addition, each assessment has at least one given type (e.g. H: Homework, P: Program, E: Essay). Each submitted assessment is given a unique ID, has a submission timestamp (date and time) and belongs to one student only. Once an assessment is submitted, the system sends a message to the student acknowledging the submission and indicating whether the submission is on time or late. For each student, it is important to track the number of submission. Each student is identified by a unique ID, has a name, university-email, and…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Np Ms Office 365/Excel 2016 I NtermedComputer ScienceISBN:9781337508841Author:CareyPublisher:CengageInformation Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Np Ms Office 365/Excel 2016 I Ntermed
Computer Science
ISBN:9781337508841
Author:Carey
Publisher:Cengage
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning