OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 12, Problem 7P
At the University Hospital, five blood samples must be scheduled through a blood-testing laboratory. Each sample goes through up to four different testing stations. The times for each test and the due dates for each sample are as follows:
Sample | Test Station /Hours | Due Date (hours) |
1 | A/1, B/2, C/3, D/1 | 6 |
2 | B/2, C/3, A/1, D/4 | 10 |
3 | C/2, A/3, D/1, C/2 | 8 |
4 | A/2, D/2, C/3, B/1 | 14 |
5 | D/2, C/l, A/2, B/4 | 12 |
- a. Using a Gantt chart,
schedule these five samples in priority order of earliest due date first. - b. Assume that the capacity of each test station (A, B, C, and D) is doubled. Prepare an FCS for this situation.
- c. What are the bottleneck work centers in part a of the problem. Suggest capacity additions that might be needed002E
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
At the University Hospital, five blood samples must bescheduled through a blood-testing laboratory. Eachsample goes through up to four different testing stations.The times for each test and the due dates for eachsample are as follows:Sample Test Station/Hours Due Date (hours)1 A/1, B/2, C/3, D/1 62 B/2, C/3, A/1, D/4 103 C/2, A/3, D/1, C/2 84 A/2, D/2, C/3, B/1 145 D/2, C/1, A/2, B/4 12a. Using a Gantt chart, schedule these five samples in priority order of earliest due date first.b. Assume that the capacity of each test station (A, B, C and D) is doubled. Prepare an FCS for this situation.c. What are the bottleneck work centers in part a of the problem. Suggest capacity additions that might be needed.
A teller at a drive-up window at a bank had the following service times (in minutes) for 20 randomly selected customers:
SAMPLE
1
2
3
4
4.5
4.6
4.5
4.7
4.2
4.5
4.6
4.6
4.2
4.4
4.4
4.8
4.3
4.7
4.4
4.5
4.3
4.3
4.6
4.9
a.
Determine the mean of each sample.
b.
If the process parameters are unknown, estimate its mean and standard deviation.
c.
Construct control charts for means and ranges using Table 10.3. Are any samples beyond the control limits? If so, which one(s)?
d.
If the process has a known mean of 4.4 and a known standard deviation of .18, what would three-sigma control limits be for a mean chart? Are any sample means beyond the control limits? If so, which one(s)?
The following are the car repair shop data:
Ticket No.
Work
Ticket No.
Work
Ticket No.
Work
1
Tires
11
Lube & oil
21
Lube & oil
2
Brakes
12
Lube & oil
22
Tires
3
Tires
13
Tires
23
Lube & oil
4
Brakes
14
Brakes
24
Lube & oil
5
Tires
15
Transmission
25
Lube & oil
6
Lube & oil
16
Battery
26
Tires
7
Brakes
17
Lube & oil
27
Battery
8
Brakes
18
Lube & oil
28
Lube & oil
9
Lube & oil
19
Brakes
29
Brakes
10
Battery
20
Lube & oil
30
Tires
Click here for the Excel Data File
Problem 9-1 Part a (Algo)
a. Prepare a check sheet for the above car repair shop data:
Chapter 12 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 12 - What types of scheduling decisions are management...Ch. 12 - Specify the kinds of objectives that might be...Ch. 12 - Prob. 3DQCh. 12 - How is the scheduling of patients in a doctor's...Ch. 12 - Describe the differences between Gantt charting,...Ch. 12 - Why are m n ma chine-scheduling algorithms not...Ch. 12 - What is the purpose of a planning and control...Ch. 12 - Prob. 8DQCh. 12 - Prob. 9DQCh. 12 - What scheduling rule should be applied to...
Ch. 12 - Prob. 11DQCh. 12 - Students must complete two activities to register...Ch. 12 - Prob. 2PCh. 12 - Sequence the jobs shown below by using a Gantt...Ch. 12 - In problem 3, assume there are two machines of...Ch. 12 - In problem 2, assume there are two machines of...Ch. 12 - The Security Life Insurance Company processes all...Ch. 12 - At the University Hospital, five blood samples...Ch. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Using the Gantt charts developed in the following...Ch. 12 - How would the theory of constraints be used to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Union Manufacturing Company is producing two types of products: A and B. The demand forecasts, batch size, and time standards follow: Demand forecast (units/yr) Product A Product B 1,000 4,000 Batch size (units/batch) Processing time (hr/unit) 20 10 3.2 4.5 Setup time (hr/batch) 10 20 Both products are produced on the same machine, called Mark I. 11) Using Table 4.1, what is the total number of hours required of Mark I equipment for the next year? A) fewer than 29,000 hours B) between 29,000 and 30,000 hours C) between 30,000 and 31,000 hours D) more than 31,000 hoursarrow_forwardA company assembles a product that consists of three pieces called AA, BB, and CC. The AA and BB parts are manufactured by the company itself, while the CC parts are purchased from another manufacturer. The process times, in hours, required for each piece in each of the processes are given in the following table: Process 1 Process 2 Process 3 Process 4 Process 5 AA 1 0.5 0.5 BB 1.5 0.5 0.5 0.5 The company has 20 machines that can carry out process 1, 5 process 2, 10 process 3, 5 process 4 and 5 process 5. Each machine works a maximum of five days each week at a rate of fifty weeks a year , in working days of 8 hours a day. Formulate and solve to determine the maximum number of assembled sets that you can produce.arrow_forwardThe union manufacturing company is producing two types of products a and b. The demand forecasts, batch size, and time standards for Mark 1 operation are as follows: Product A. product B demand forecast (units/yr) 1,000 4,000 batch size (units/batch) 20 10 processing time (hr/unit) 3.2. 4.5 setup time (hr/batch) 10 20 the company works 250 days per yr and operates two shifts, each covering 8 hours. If a 20 percent capacity cushion is maintained how many new Mark 1 machines are required if union does not resort to any short term capacity options?arrow_forward
- Suppose you are in charge of a large mailing to the alumni of your college inviting them to contribute to a scholarship fund. The letters and envelopes have been individually addressed (mailing labels were not used). The letters are to be processed (matched with correct envelope, time estimated to be 0.2 minutes each), folded (0.12 minutes each), and stuffed into the correct envelope (0.10 minutes each). The envelopes are to be sealed (0.05 minutes each), and a large commemorative stamp is to be placed in the upper right-hand corner of each envelope (0.10 minutes each).a. Make a process chart for this activity, assuming that it is aone-person operation.b. Estimate how long it will take to stuff, seal, and stamp 2,000 envelopes. Assume that the person doing this work is paid $8 per hour. How much will it cost to process 2,000 letters?c. Consider each of the following process changes. Which changes would reduce the time and cost of the current process?▪ Each letter has the same greeting,…arrow_forwardThe sales manager of STC Telecommunication Company, conducts interviews of the sales representatives. During the interview, these questions were asked from the sales representatives which are related to the performance of their job: the percentage of the time spent in making presentations to new potential customers, telephone conversation with current customers, time spent working on the computer, and engaging in on- the job activities. What potential sources of error might be associated with the manager’s line of questioning specifically on the different tasks performed by the sales representatives?arrow_forwardBox plots – Analyze each of these cycle time data but on the same chart: C7, C8, C9. That means one chart showing three different box plots, with a single conclusion which addresses all three.arrow_forward
- b) A company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operations when shipments are received: Operation A – draw a random sample, package, and deliver to testing; and Operation B – test the materials and issue a disposition report. There are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are given in the table below. Shipment Operation A (hours) Operation B (hours) A 1.5 1.0 В 1.1 2.7 1.2 1.4 D 0.7 1.6 E 1.6 1.5 F 1.9 2.9 Use Johnson's Rule to set the sequence of processing the shipments through Quality Control. i. ii. How much total time is required to process all the six shipments through Quality Control? Show all times on a Gantt Chart. w luarrow_forward. A teller at a drive-up window at a bank had the following service times (in minutes) for 20 randomly selected customers.SAMPLE1 2 3 44.5 4.6 4.5 4.74.2 4.5 4.6 4.64.2 4.4 4.4 4.84.3 4.7 4.4 4.54.3 4.3 4.6 4.9a. Determine the mean of each sample.arrow_forwardTerex Corporation is a global manufacturer of aerial work platforms and materials processingmachinery. They design, build and support products such as large lifting equipment used inconstruction. The company makes most pieces to order and customizes them to meet customers’unique preferences.Terex maintained a manual system for yard management at their transfer centre in Washingtonthat is always full of lifting equipment, which generated excessive costs for what should have beena relatively simple process of locating customers’ units to prepare them for delivery. A wallboardand sticker system was a low-tech solution for identifying equipment items in the yard at Terex.While inexpensive in itself, the solution cost around six minutes every time an employee had tolocate a unit in the yard. It also required a considerable number of hours to be spent each monthtaking physical inventories. After a successful pilot, the company approved a new solution, replacingstickers, yard maps, and…arrow_forward
- Terex Corporation is a global manufacturer of aerial work platforms and materials processingmachinery. They design, build and support products such as large lifting equipment used inconstruction. The company makes most pieces to order and customizes them to meet customers’unique preferences.Terex maintained a manual system for yard management at their transfer centre in Washingtonthat is always full of lifting equipment, which generated excessive costs for what should have beena relatively simple process of locating customers’ units to prepare them for delivery. A wallboardand sticker system was a low-tech solution for identifying equipment items in the yard at Terex.While inexpensive in itself, the solution cost around six minutes every time an employee had tolocate a unit in the yard. It also required a considerable number of hours to be spent each monthtaking physical inventories. After a successful pilot, the company approved a new solution, replacingstickers, yard maps, and…arrow_forwardIf a tenant is evicted because of damages to the premises, a process needs to be started by the tribunal in order to hold a hearing to assess the amount of compensation the tenant owes to the owner of the premises. This process starts when a cashier of the tribunal receives a request for compensation from the owner. The cashier then retrieves the file for those particular premises and checks that the request is both acceptable for filing and compliant with the description of the premises on file. After these checks, the cashier needs to set a hearing date. Setting a hearing date incurs fees to the owner. It may be that the owner has already paid the fees with the request, in which case the cashier allocates a hearing date and the process completes. It may be that additional fees are required, but the owner has already paid also those fees. In this case the cashier generates a receipt for the additional fees and proceeds with allocating the hearing date. Finally, if the owner has not…arrow_forwardINAL SINAVI 17 - - is a parametric analysis method which allows obtaining the capacity curve from a dynamic analysis. This procedure offers to investigate, by scaling the induced base acceleration, a continuous picture of the structural behavior from elastic to yield range and eventually to collapse. Time-history representation of ground motions Hysteretic models for components behavior a) b) Time-history analysis d) Incremental dynamic analysis Boş bırak 17/20 Sonraki> Карat KÖncekiarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY