Concept explainers
What types of
- a. Hospital
- b. University
- c. Moviemaking
- d. Make-to-order factory
a)
To determine: The type of scheduling decision and the type of resources to be scheduled in the operations of a hospital.
Introduction:
Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan the allocating of human resources and machinery.
Explanation of Solution
Determine the type of scheduling decisions and the type of resources to be scheduled in the operations of hospital:
Use of operating rooms, special equipment, and shifts to the nurses in each department should be assigned using the scheduling process in the hospital. Special equipment includes lab, X-ray, EEG, and EKG.
b)
To determine: The type of scheduling decision and the type of resources to be scheduled in the operations of a university.
Introduction:
Scheduling is the process of controlling and arranging the workloads of the production process by the optimized way. It is used to plan the allocating of human resources and machinery.
Explanation of Solution
Determine the type of scheduling decisions and the type of resources to be scheduled in the operations of university:
The type of classes needed for each hour, faculty needed for each class, library services, registration, and counselling must be assigned with proper scheduling method.
c)
To determine: The type of scheduling decision and the type of resources to be scheduled in the operations of moviemaking.
Introduction:
Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan the allocating of human resources and machinery.
Explanation of Solution
Determine the type of scheduling decisions and the type of resources to be scheduled in the operations of moviemaking:
It is necessary to determine the kind of property, videographers, staff, actors, and actresses who are required for the movie to be scheduled and the sequence of scenes to be filmed.
d)
To determine: The type of scheduling decision and the type of resources to be scheduled in the operations of make-to-order factory.
Introduction:
Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to the plan allocation of human resources and machinery.
Explanation of Solution
Determine the type of scheduling decisions and the type of resources to be scheduled in the operations of make-to-order factory:
It is necessary to determine the kind of product to be produced and the equipment required to produce such products. The time and place to deliver the product should be assigned.
Want to see more full solutions like this?
Chapter 12 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- Find the five essential factors that need to be considered when formulating a policy for the scheduling of processes, and list them below.arrow_forwardGiven the operation times provided: Develop a job sequence that minimizes idle time at the two work centers. b. Construct a chart of the activities at the two centers, and determine each one’s idle time, assuming no other activities are involvedarrow_forwardAt Valley Hospital, nurses beginning a new shift report to a central area to receive their primary patient assignments. Not every nurse is as efficient as another with particular kinds of patients. Given the following patient roster, care levels, and time estimates, assign nurses to patients to op- timize efficiency. Also, determine how long it will take for the nurses to complete their routine tasks on this shift.arrow_forward
- Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performied. The daily demand is 150 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires taskA to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once taskFis completed.What is the minimum number of workstations needed?arrow_forwardGive a brief explanation of five major process scheduling policy factors.arrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 100 toys. Times of the tasks are 2.73,2.01 1,2.13,2.0,2.61,2. 2.71 , and 2.95 minutes for A, B, C, D, E, F , and G , respectively . However , due to the nature of the product there are precedence rules that must be observed . Such that Task A does not need any predecessors ; task B requires task A to be completed . To start task C and task D, each require task B to be completed . Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed . Finally , task G can start only once task F is completed . What should be the calculated cycle time in minutes ? a. 0.9 b. 4.5 c. None is correct d. 4.8 e. 4.4arrow_forward
- A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 120 toys. Times of the tasks are 2.73,2.01 1, 2.13, 2.0, 2.61, 2.71 , and 2.95 minutes for A ,B,C,D,E,F, , and G, respectively . However, due to the nature of product there are precedence rules that must be observed . Such that Task A does not need any predecessors ; task B requires task be completed. To start task C and task D, each require task B to be completed . Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed . Finally, task G can start only once task F is completed . What is the minimum number of workstations needed? a. 4 b. 5 c. 6 d. None of them e. 8arrow_forwardWhat are the five (5) essential process scheduling policy variables that must be taken into consideration?arrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73,2.01,2.13,2.0.2.61,2.71 , and 2.95 minutes for A A,B,C,D,E,F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D. each require task B to be completed. Task must be completed prior to stating task E. Task F needs both task D and task Eto be completedFinally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation arearrow_forward
- Which of the following tasks within a company are related to airline operations? Select one: a. advertising b. accounts receivable c. international currency exchange to pay debts d. sales me. crew schedulingarrow_forwardA local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 100 toys . Times of the tasks are 2.73,2.01 ,2.13,2.0,2.61,2.71 and 2.95 minutes for A,B,C,D,E,F, and G, respectively . However , due to the nature of the product there are precedencerules that must be observed . Such that Task A does not need any predecessors ; task B requires task A to becompleted . To start task C and task Deach require task B to be completed . Task must be completed prior to stating task E. Task F needs both task and task E to be completed . Finally , task G can start only once task F is completed . Given we apply the most remaining tasks rule for balancing the assembly line , with ties broken according to longesttask time first , the tasks that will be assigned to the THIRD workstation are a. D and F b . None is the correct answer c. D only d. E only e. B, C , and Darrow_forwardAssign the 4 departments in Table X to locations A, B, C, and D, which are separated by the distances shown in Table y, in such a way that transportation cost is minimized. Use this heuristic: assign departments with the greatest interdepartmental workflow first. See attached tables.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,