OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 12, Problem 1P
Students must complete two activities to register for class: registration and payment of fees. Because of individual differences, the processing time (in minutes) for each of these two activities for five students varies, as shown below:
Minutes | ||
Student | Registration | Pay Fees |
A | 12 | 5 |
B | 7 | 2 |
C | 5 | 9 |
D | 3 | 8 |
E | 4 | 6 |
- a. Construct a Gantt chart to determine the total time required to process all five students. Use the following sequence of students: D, E, B, C, A.
- b. Can you construct a better sequence to reduce the total time required?
- c. What problems might be encountered in using this approach to registration in colleges?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Trim-Look Company makes several lines of skirts, dresses, and sport coats. Recently, a consultant suggested that the company reevaluate its South Islander line and allocate its resources to products that would maximize contribution to profits and to overhead. Each product requires the same polyester fabric and must pass through the cutting and sewing departments. The following data were collected for the study:
PROCESSING TIME (HR)
Product
Cutting
Sewing
Material (yd)
Skirt
1
1
1
Dress
3
4
1
Sport coat
4
6
4
The cutting department has 100 hours of capacity, sewing has 180 hours of capacity, and 60 yards of material are available. Each skirt contributes $5 to profits and overhead; each dress, $17; and each sport coat, $30.
a. Specify the objective function and constraints for this problem.
b. Use a computer package such as POM for Windows to solve the problem.
b) A company receives parts from suppliers to be used in its manufacturing departments.
The quality control department must perform two operations when shipments are
received:
Operation A – draw a random sample, package, and deliver to testing; and
Operation B – test the materials and issue a disposition report.
There are currently six shipments waiting to be processed. The time estimates for
processing these six shipments through quality control are given in the table below.
Shipment
Operation A (hours)
Operation B (hours)
A
1.5
1.0
В
1.1
2.7
1.2
1.4
D
0.7
1.6
E
1.6
1.5
F
1.9
2.9
Use Johnson's Rule to set the sequence of processing the shipments through
Quality Control.
i.
ii.
How much total time is required to process all the six shipments through Quality
Control? Show all times on a Gantt Chart.
w lu
ABC Solutions is a traditional company in a textile industry with a combined workforce of 150 staff. Due to increased levels of competition, this company is now increasingly finding it difficult to compete – especially as the larger companies seem to be a little more innovative, agile and responsive to client requirements. Management have noticed that staff, especially the highly skilled ones, are now leaving the company to seek work elsewhere (in these larger companies). This has meant appointing new staff and undertaking a considerable amount of re-training to replace those that have left the company. Apart from impacting on core business operations, ABC Solutions has started witnessing a drop in its profit margin.
Given this position, senior management at ABC Solutions have decided to implement a performance measurement tool (PMT) that would allow them to align the strategic, management and operational requirements of the business. They are therefore considering the adoption of the…
Chapter 12 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 12 - What types of scheduling decisions are management...Ch. 12 - Specify the kinds of objectives that might be...Ch. 12 - Prob. 3DQCh. 12 - How is the scheduling of patients in a doctor's...Ch. 12 - Describe the differences between Gantt charting,...Ch. 12 - Why are m n ma chine-scheduling algorithms not...Ch. 12 - What is the purpose of a planning and control...Ch. 12 - Prob. 8DQCh. 12 - Prob. 9DQCh. 12 - What scheduling rule should be applied to...
Ch. 12 - Prob. 11DQCh. 12 - Students must complete two activities to register...Ch. 12 - Prob. 2PCh. 12 - Sequence the jobs shown below by using a Gantt...Ch. 12 - In problem 3, assume there are two machines of...Ch. 12 - In problem 2, assume there are two machines of...Ch. 12 - The Security Life Insurance Company processes all...Ch. 12 - At the University Hospital, five blood samples...Ch. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Using the Gantt charts developed in the following...Ch. 12 - How would the theory of constraints be used to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company receives parts from suppliers to be used in its manufacturing departments. The quality control department must perform two operation when shipments are received:i) Operation A-draw a random sample, package, and deliver to testing, andii) Operation B-test the materials and issue a disposition reportThere are currently six shipments waiting to be processed. The time estimates for processing these six shipments through quality control are:Shipment Operation A (hours) Operation B (hours)1 1.5 1.02 1.1 2.73 1.2 1.44 0.7…arrow_forwardStation 1 Machine A 20 min/unit Note: Station 1 Machine B 20 min/unit Station 2 12 min/unit Station 1 Machine A Station 1 Machine B Station 2 Station 3 Station 3 A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The process time of each machine/station is indicated in the flowchart. The unit is then processed at Stations 2 and 3 before leaving the work cell. Specify the bottleneck(s). 8 min/unit 1- These are checkboxes, you can select more than one option if needed.arrow_forwardThe table below shows the time stamps of 10 customers who visited a local bank branch from 9:00 a.m. to 9:45 a.m. What is the flow time of customers? Customer 1 2 3 4 5 6 7 8 9 10 Time in 9:2 9:5 9:6 9:8 9:8 9:10 9:12 9:15 9:18 9:19 Time out 9:7 9:10 9:17 9:23 9:36 9:21 9:41 9:41 9:28 9:42 Instruction: Round your answer to 1 decimal place. Flow time of customers 3.5 minutesarrow_forward
- A company assembles a product that consists of three pieces called AA, BB, and CC. The AA and BB parts are manufactured by the company itself, while the CC parts are purchased from another manufacturer. The process times, in hours, required for each piece in each of the processes are given in the following table: Process 1 Process 2 Process 3 Process 4 Process 5 AA 1 0.5 0.5 BB 1.5 0.5 0.5 0.5 The company has 20 machines that can carry out process 1, 5 process 2, 10 process 3, 5 process 4 and 5 process 5. Each machine works a maximum of five days each week at a rate of fifty weeks a year , in working days of 8 hours a day. Formulate and solve to determine the maximum number of assembled sets that you can produce.arrow_forwardMedical Solutions, Inc. has the following claims it must complete in the next week (40 hours). The jobs are as follows: Claim Type Spinal injury Number of Claims Setup (Changeover) to Process (Work Time per Claim Type (hours) Cancer treatment 15 Hip replacement Order Quantity) 14 10 SI Claims Workload: hours Processing Time per Claim (hours) HR Claims Workload: hours 3.0 1.1 2.5 0.9 1.5 All claims of the same type are processed together. Is 40 hours enough capacity? (Hint: use Equation 10.3.) Round your answers to one decimal place. CT Claims Workload: hours 0.5 Total workload is hours while capacity is 40 hours. The work -Select-cancannotItem 5 be completed using regular time hours.arrow_forwardWhy is it required to include an exception in the process scheduling?arrow_forward
- The National State Bank is trying to make sure that they have enough tellers to handle the Friday afternoon rush of workers wanting to cash their paychecks. They are only concerned with the last hour of the day from 4:00 to 5:00 P.M. It takes 5 minutes per customer to be processed by the tellers. The average customer arrivals are shown in the table below. TIME CUSTOMERSARRIVING 4:00 – 4:05 2 4:05 – 4:10 6 4:10 – 4:15 7 4:15 – 4:20 6 4:20 – 4:25 14 4:25 – 4:30 16 4:30 – 4:35 18 4:35 – 4:40 10 4:40 – 4:45 12 4:45 – 4:50 2 4:50 – 4:55 5 4:55 – 5:00 2 5:00 – 5:05 0 Total 100 The bank currently has 8 teller stations, and all are staffed during the Friday afternoon rush hour. a. What is the current maximum output at the bank during rush hour? b. Can the bank process all the customers by 5:00 P.M.? c. What is the maximum waiting time for customers, and what time period does it occur in? (Round your…arrow_forwardWhat is flow processing, and what are its advantages and disadvantages?arrow_forwardNumber of Processing Time for A Processing Time for B Processing Time for C (minutes) Resource Workers (minutes) (minutes) 1 2 2 2 4 4 5 1 15 3 2 6. 4arrow_forward
- How does seasonal variability in demand affect the flow and waiting time through a process? How might a company respond to reduce the effect of this variability?arrow_forwardA bank receives loan applications from 6 customers a day. The bank has promised customers that applications will be processed in the order they are received. The table below shows the applications in the order they were received, the processing time for each loan application, and the due date that customers need to hear about their application status: Customer Processing time (days) Due date (days) A 9 13 B 11 18 C 8 11 D 7 13 E 10 22 F 12 28 Average flow time days Average tardiness days Average number of jobs applicationsarrow_forwardAt the University Hospital, five blood samples must bescheduled through a blood-testing laboratory. Eachsample goes through up to four different testing stations.The times for each test and the due dates for eachsample are as follows:Sample Test Station/Hours Due Date (hours)1 A/1, B/2, C/3, D/1 62 B/2, C/3, A/1, D/4 103 C/2, A/3, D/1, C/2 84 A/2, D/2, C/3, B/1 145 D/2, C/1, A/2, B/4 12a. Using a Gantt chart, schedule these five samples in priority order of earliest due date first.b. Assume that the capacity of each test station (A, B, C and D) is doubled. Prepare an FCS for this situation.c. What are the bottleneck work centers in part a of the problem. Suggest capacity additions that might be needed.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY