Interpretation:The optimal sequence flavors for the minimization of the maximum lateness is to be determined by using L’s algorithm.
Concept Introduction:
Shortest processing time rule is used for the minimization of mean time flow of the project and hence it is used to minimize the time of mean flow of a process.
Tardiness is used to calculate the difference between the actual completion time and the required due date of the job. Any tardy jobs get completed after the due date of the job.
(b)
Interpretation:Evaluation and comparison of the each objective function value is to be done.
Concept Introduction:
Shortest processing time rule is used for the minimization of mean time flow of the project and hence it is used to minimize the time of mean flow of the process.
Tardiness is used to calculate the difference between the actual completion time and the required due date of the job. Any tardy jobs get completed after the due date of the job.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Production and Operations Analysis, Seventh Edition
- Dan's Auto Detailing business performs two major activities: exterior cleanup and interior detailing. Based on the size of car and condition, time estimates for six cars on Monday morning are as shown in the accompanying table. Car Number 1 5 6 Exterior Interior 55 75 4 65 35 50 60 45 90 35 40 a. Sequence the cars so that all exterior cleanup is done first and total completion time is minimized. The sequence is -Select-- -Select- -Select- -Select- -Select-- -Select- 2 3 80 20arrow_forwardSunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Using the FCFS rule for scheduling, the sequence is For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = | hours (enter your response as a whole number). Times Taken for Different Activities (hours) Using Johnson's rule for 2-machine scheduling, the sequence is Suit Cut and Sew Deliver 1 2 4 3 For the schedule developed using the Johnson's rule, the total length 3 6. of time taken to complete the three suits (including delivery) =| hours (enter your response as a whole number). Assume that orders for suits have been listed in the above table in the order in which they were received. Of the two developed schedules, rule gets the schedule finished sooner.arrow_forwardAt the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the beginning of the day 1 (today, which is a work day). All of the jobs are due at various times today. Your job is to evaluate four common sequencing rules. JOB DUE (IN HOURS) DURATION (HOURS REQUIRED) A 8 (this job is due in 8 hours) 1.65 B 5.5 (this job is due in 5.5 hours) 1.20 C 4.5 (this job is due after lunch in 4.5 hours) 0.85 D 6 (this job is due in 6…arrow_forward
- A manufacturer is designing a product layout for a new product productionIt plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namelyABC, D, E, F, and Grespectively. Task A does not have any predecessor to startTo start Task B.it requires Task A to be completedStarting tasks needs, the task B to be completed. Also, starting task Dneeded task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed task Fto be completed. The processing times for tasks, ABC, D. E. and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8 and 4.7 minutes respectively. What should be the cycle time in minutes? a 4.7 b. None is the correct answer Oc 7.5 d6.86 e.arrow_forwardA machine center in a job shop for a local fabrication company has five unprocessed jobs remaining at a particular point in time. The jobs are labeled A, B, C, D, and E in the order that they entered the shop. The respective processing times and due dates are given in the table below. What is the sequence the of jobs by CR rules? Job Processing Time Due Date A 10 32 B. 55 34 C. 11 31 60 35arrow_forwardFive jobs are planned to be scheduled. Each of the jobs must be processed on three machines (A, B, and C) in the same order. The processing times are listed below. Use Johnson's Rule to determine the optimal sequence of jobs. Job B 16 10 11 10 14 20 12 3 10 8 4 1 O a) 3-1-2-4-5 O b) Johnson's Rule is not an Optimal Technique O c) 1-2-3-4-5 O d) 5-4-3-1-2 O e) 5-4-3-2-1 O) 5-4-2-1-3 O e) 5-4-2-3-1 2345arrow_forward
- A group of six jobs is to be processed through a two-machine flow shop. The first operation involves cleaning and the second involves painting. Determine a sequence that willminimize the total completion time for this group of jobs. Processing times are as follows:PROCESSING TIME (hours)Job Work Center 1 Work Center 2A 5 5B 4 3C 8 9D 2 7E 6 8F 12 15 To employ Johnson’s rule, create a “blank” sequence first, such as:mhhe.com/stevenson13eEXAMPLE 41st 2nd 3rd 4th 5th 6tharrow_forwardUsing the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including of the suits. delivery) = hours (enter your response as a whole number). Times Taken for Different Activities (hours) Deliver Suit Cut and Sew Using Johnson's rule for 2-machine scheduling, the sequence is 1 2. For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits 3 (including delivery) = hours (enter your response as a whole number). Assume that orders for suits have been listed in the above table in the order in which they were received. Of the two developed schedules, V rule gets the schedule finished sooner.arrow_forwardIn a school, there are four teachers X1,X2,X3,X4 and five batches Y1,Y2,Y3,Y4,Y5. Given that teacher Xi is required to teach batch Yj for Pij periods, schedule a complete routine in the minimum possible number of periods. The matrix is given below: X1 X2 X3 X4 Y1 2 2 -- -- Y2 1 Y3 -- -- Y4 | 1 2 1 -- Y5 1 1 -- -- Remember there are only 3 class rooms available.arrow_forward
- Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery)= hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Deliver Suit Cut and Sew 1 2 Assume that orders for suits have been listed in the above table in the order in which they were receivedarrow_forwardA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A. B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only startupon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A. B, C, D, E, F, and G are 2.4, 2.2, 0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FIRST Workstation? O a. 0.47 O b. 0.27 Oc. 0.57 O…arrow_forwardOn Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.