Concept explainers
A.
Interpretation: The sequence of jobs which minimizes the mean flow time has to be computed.
Concept Introduction:
Flow time:The time spent in a business process right from beginning to end is called the flow time. It is also called total processing time.
B.
Interpretation: The sequence of jobs which minimizes the maximum lateness has to be computed.
Concept Introduction:
EDD when expanded becomes Earliest due date. In the rule, the jobs must be arranged in increasing order according to the promised time.
C.
Interpretation: The sequence of jobs which minimizes the number of tardy jobs has to be computed.
Concept Introduction:
Tardiness is supposed to be the difference derived between the actual flow time and the required due date. Therefore, tardy jobs are finished as soon as its due date is over.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Production and Operations Analysis, Seventh Edition
- Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. 2 3 4 5 ... The total flow time for the sequence developed using the SPT rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the SPT rule = ☐ % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimal…arrow_forwardThe data for five tax analysis jobs waiting to be processed by Martha at T. R. Accounting Service has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Questions 1. Use the shortest-processing-time (SPT) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus sign to enter negative lateness values, if any. Round the average values to two decimal places. Sequence Job Processing Time Due Date Flow Time Lateness Tardiness 1 2 3 4 5 Average 2. Use the earliest-due-date (EDD) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus…arrow_forwardCourtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. Due date Duration (hours required) Job (hours hence) A 8 16 2 C 24 10 32 16 E 12 6 In what sequence would the jobs be ranked according to the following decision rules: FCFS, EDD, SPT, LPT? According to the FCFS rule, the sequence of jobs should be According to the EDD rule, the sequence of jobs should be According to the SPT rule, the sequence of jobs should be According to the LPT rule, the sequence of jobs should bearrow_forward
- What are the advantages and disadvantages of the shortest processing time (SPT) rule?arrow_forwardFive welding jobs are waiting to be processed. Their processing times and due dates are given below. Using the First Come - First Served dispatching rule, What is the Total Flow Time? All dates are specified as days from today. Job A B C D E Processing Job due date Time (days) (days) 3 2 17 14 11 15 22 4arrow_forwardIf the jobs displayed in Table 18.23 are processed using the earliest-due-date rule, whatis the average flow time?arrow_forward
- The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job W X Y Z Processing Time (hrs) 4 3 2 1 If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today? Multiple Choice 0 1 2 3 Due (hrs from now) 4 5 2 1 4arrow_forwardAn insurance claims work area has five claims waiting for processing as follows: Job Processing Time Due Date (Di ) 1 18 31 2 14 25 3 12 23 4 19 24 5 10 37 Use the Excel Sequencing template to find the average flowtime, average and maximum tardiness, and average lateness for the following sequences: SPT sequence, EDD sequence, and the sequence 4-3-2-1-5. Round your answers for the average values to two decimal places. The SPT sequence is - - - - . Average Flow Time Average Tardiness Maximum Tardiness Average Lateness The EDD sequence is - - - - . Average Flow Time Average Tardiness Maximum Tardiness Average Lateness 4-3-2-1-5 sequence: Average Flow Time Average Tardiness Maximum Tardiness Average Lateness What sequencing rule do you recommend? The ___________ is recommended as it minimizes average flow time and number of jobs in system.arrow_forwardDiablo Electronics manufactures four unique products (A, B, C, and D) that are fabricated and assembledin five different workstations (V, W, X, Y, and Z) using a small batch process. Each workstation is staffedby a worker who is dedicated to work a single shift per day at an assigned workstation. Batch setuptimes have been reduced to such an extent that they can be considered negligible. A flowchart denotesthe path each product follows through the manufacturing process as shown in Figure 5.2, where eachproduct’s price, demand per week, and processing times per unit are indicated as well. Inverted trianglesrepresent purchased parts and raw materials consumed per unit at different workstations. Diablo canmake and sell up to the limit of its demand per week, and no penalties are incurred for not being able tomeet all the demand.Which of the five workstations (V, W, X, Y, or Z) has the highest utilization, and thus serves as the bottle-neck for Diablo Electronics?arrow_forward
- The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.arrow_forwardK Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1), in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a work day. JOB A C D E DUE DATE (HOURS HENCE) 10 16 14 36 26 DURATION (HOURS REQUIRED) 6 3758 a) Sequence the jobs according to EDD. According to the EDD rule, the sequence of jobs should be A, C, B, E, D b) What is the average completion (flow) time? The average completion (flow) time is days (round your response to one decimal place).arrow_forwardWhat are the benefits and drawbacks of the shortest processing time rule (SPT)?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.