At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the beginning of the day 1 (today, which is a work day). All of the jobs are due at various times today. Your job is to evaluate four common sequencing rules. JOB DUE (IN HOURS) DURATION (HOURS REQUIRED) A 8 (this job is due in 8 hours) 1.65 B 5.5 (this job is due in 5.5 hours) 1.20 C 4.5 (this job is due after lunch in 4.5 hours) 0.85 D 6 (this job is due in 6 hours) 1.30 E 4 (this job is due at noon, in 4 hours) 1.85 F 7 (this job is due in 7 hours) 1.55 Part 2 a) Sequence the jobs according to the following decision rules: FCFS, EDD, SPT, and LPT. According to the FCFS rule, the sequence of jobs should be ▼ C, B, D, F, A, E B, E, A, D, F, C B, C, F, D, A, E E, C, B, D, F, A E, A, F, D, B, C A, B, C, D, E, F . Part 3 According to the EDD rule, the sequence of jobs should be ▼ B, C, F, D, A, E A, B, C, D, E, F C, B, D, F, A, E E, A, F, D, B, C B, E, A, D, F, C E, C, B, D, F, A . Part 4 According to the SPT rule, the sequence of jobs should be ▼ C, B, D, F, A, E A, B, C, D, E, F E, C, B, D, F, A B, E, A, D, F, C B, C, F, D, A, E E, A, F, D, B, C . Part 5 According to the LPT rule, the sequence of jobs should be ▼ A, B, C, D, E, F B, C, F, D, A, E E, A, F, D, B, C E, C, B, D, F, A C, B, D, F, A, E B, E, A, D, F, C . Part 6 b), c), d) & e) Compute the average completion (flow) time, average lateness, and average number of jobs in the system for each rule. Construct the table of measures of effectiveness for each rule (round your responses to two decimal places). Rule Average Completion (Flow) Time Average Lateness Average Number of Jobs in System FCFS enter your response here enter your response here enter your response here EDD enter your response here enter your response here enter your response here SPT enter your response here enter your response here enter your response here LPT enter your response here enter your response here enter your response here Part 7 f) Which is the best decision rule based on average completion (flow) time? The best decision rule based on average completion (flow) time is ▼ FCFS SPT EDD LPT . Part 8 g) Which job is late with the SPT rule? The job that is late with the SPT rule is job ▼ E A B F D C
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
JOB
|
DUE (IN HOURS)
|
DURATION (HOURS REQUIRED)
|
A
|
8
(this job is due in 8 hours)
|
1.65
|
B
|
5.5
(this job is due in 5.5 hours)
|
1.20
|
C
|
4.5
(this job is due after lunch in 4.5 hours)
|
0.85
|
D
|
6
(this job is due in 6 hours)
|
1.30
|
E
|
4
(this job is due at noon, in 4 hours)
|
1.85
|
F
|
7
(this job is due in 7 hours)
|
1.55
|
Part 2
Part 3
Part 4
Part 5
Part 6
Rule
|
Average Completion (Flow) Time
|
Average Lateness
|
Average Number of Jobs in System
|
FCFS
|
enter your response here
|
enter your response here
|
enter your response here
|
EDD
|
enter your response here
|
enter your response here
|
enter your response here
|
SPT
|
enter your response here
|
enter your response here
|
enter your response here
|
LPT
|
enter your response here
|
enter your response here
|
enter your response here
|
Part 7
Part 8