Question
Chapter 9.6, Problem 8P
Summary Introduction
Interpretation: In order to minimize the maximum lateness; the sequence of these jobs are to be determined.
Concept Introduction: The activities under a project are programmed based on the needs of the individual and attaining ease is the priority of the individual.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using the FCFS rule for scheduling, the sequence is 1-2-3
For the schedule developed using the FCFS rule, the total length of time taken to complete the three
suits (including delivery)= hours (enter your response as a whole number).
Sunny Park Tailors has been asked to make three different types of wedding suits for separate
customers. The table below highlights the time taken in hours for cutting and sewing (process 1)
and delivery (process 2) of each of the suits.
Times Taken for Different Activities (hours)
Deliver
Suit
Cut and Sew
1
2
Assume that orders for suits have been listed in the above table in the order in which they were
received
De Law Construction has a gotten some construction jobs to build some starter housing units in a few areas. The building time for each housing unit to be completed as well as the date that each unit is to be completed is shown in the table below. Today is Day 471. Which of the sequences, EDD OR SPT should the company use to sequence the order in which they do the jobs, assuming that because of resource constraints it cannot do the jobs simultaneously?
HOUSING UNIT
Building Time (days)
Due Date
Marabella
39
Day 502
Tabaquite
23
Day 528
San Juan
30
Day 515
Mayaro
33
Day 498
D’Abadie
41
Day 535
Preysal
40
Day 510
Some time after starting the jobs according to the sequence you decided on, it was found that because of inclement weather the last three housing units in the sequence have been delayed. You now have to prioritise and decide in which order to expedite those three jobs, using the Critical Ratio model. It is now…
Sunny Park Tailors has been asked to make three different types of
wedding suits for separate customers. The table below highlights
the time taken in hours for cutting and sewing (process 1) and
delivery (process 2) of each of the suits.
Using the FCFS rule for scheduling, the sequence is
For the schedule developed using the FCFS rule, the total length of
time taken to complete the three suits (including delivery) = | hours
(enter your response as a whole number).
Times Taken for Different Activities (hours)
Using Johnson's rule for 2-machine scheduling, the sequence is
Suit
Cut and Sew
Deliver
1
2
4
3
For the schedule developed using the Johnson's rule, the total length
3
6.
of time taken to complete the three suits (including delivery) =|
hours (enter your response as a whole number).
Assume that orders for suits have been listed in the above table in
the order in which they were received.
Of the two developed schedules,
rule gets the schedule
finished sooner.
Chapter 9 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 9.5 - Prob. 1PCh. 9.5 - Prob. 2PCh. 9.5 - Prob. 3PCh. 9.5 - Prob. 4PCh. 9.5 - Prob. 5PCh. 9.6 - Prob. 6PCh. 9.6 - Prob. 7PCh. 9.6 - Prob. 8PCh. 9.6 - Prob. 9PCh. 9.6 - Prob. 10P
Ch. 9.7 - Prob. 11PCh. 9.7 - Prob. 12PCh. 9.7 - Prob. 13PCh. 9.7 - Prob. 14PCh. 9.7 - Prob. 15PCh. 9.7 - Prob. 16PCh. 9.7 - Prob. 17PCh. 9.8 - Prob. 18PCh. 9.8 - Prob. 19PCh. 9.8 - Prob. 20PCh. 9.8 - Prob. 21PCh. 9.8 - Prob. 22PCh. 9.9 - Prob. 23PCh. 9.9 - Prob. 24PCh. 9.9 - Prob. 25PCh. 9.10 - Prob. 27PCh. 9.10 - Prob. 28PCh. 9.10 - Prob. 29PCh. 9 - Prob. 30APCh. 9 - Prob. 31APCh. 9 - Prob. 32APCh. 9 - Prob. 33APCh. 9 - Prob. 34APCh. 9 - Prob. 35APCh. 9 - Prob. 36APCh. 9 - Prob. 37APCh. 9 - Prob. 38APCh. 9 - Prob. 39APCh. 9 - Prob. 40APCh. 9 - Prob. 41APCh. 9 - Prob. 42APCh. 9 - Prob. 43APCh. 9 - Prob. 44APCh. 9 - Prob. 45APCh. 9 - Prob. 46APCh. 9 - Prob. 47AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Using the FCFS rule for scheduling, the sequence is 1-2-3. For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 6 5 8 Deliver 324 2 4 Assume that orders for suits have been listed in the above table in the order in which they were received.arrow_forwardUsing Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order 1 2 3 4 5 6 Job For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number). Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job A <ש ס ח ר B C E F Operation 1 (hours) 10 36254 Operation 2 (hours) 8° 4 2 7 1 13arrow_forwardFive jobs are planned to be scheduled. Each of the jobs must be processed on three machines (A, B, and C) in the same order. The processing times are listed below. Use Johnson's Rule to determine the optimal sequence of jobs. Job B 16 10 11 10 14 20 12 3 10 8 4 1 O a) 3-1-2-4-5 O b) Johnson's Rule is not an Optimal Technique O c) 1-2-3-4-5 O d) 5-4-3-1-2 O e) 5-4-3-2-1 O) 5-4-2-1-3 O e) 5-4-2-3-1 2345arrow_forward
- Eight jobs are to be processed through a single machine. The processing times and due dates are given here. (given) Furthermore, assume that the following precedence relationships must besatisfied: 2→ 6 → 3. 1 → 4 → 7 → 8.Determine the sequence in which these jobs should be done in order tominimize the maximum lateness subject to the precedence restrictions.arrow_forwardUsing Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 2 3 11 4 5 6 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number). Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job A amoa I - B C D E Operation 1 (hours) 4 10 3 14 6 7 Operation 2 (hours) 8 51112 14arrow_forwardK Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 7 4 5 Deliver 2 3 6 Assume that orders for suits have been listed in the above table in the order in which they were received Darrow_forward
- The first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD. Job ProcessingTime at EngineLathe (hours) TimeRemainingUntil Due Date(days) Number ofOperationsRemaining Shop TimeRemaining(days) CR S/RO 1 2 3 4 2.3 10.5 6.2 15.6 15 10 20 8 10 2 12 5 6.1 7.8 14.5 10.2 2.46 1.28 1.38 0.78 0.89 1.10 0.46 -0.44arrow_forwardSuppose that 12 jobs must be processed through six machines. If the jobs may beprocessed in any order, how many different possible schedules are there? If youwere to run a computer program that could evaluate 100 schedules every second,how much time would the program require to evaluate all feasible schedules?arrow_forwardUsing Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order 1 2 3 4 5 6 Job For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number). R**. Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting Processing times are as follows: Job A B C D E F Operation 1 (hours) 1 10 8 11 4 2 Operation 2 (hours) 3 12 7 9 6 13arrow_forward
- Three jobs are to be scheduled on two machines A & B . Assume that the jobs are processed in the Sequence A-B. The processing times are : The Question is : Draw a Gantt Chart that shows the Schedule Corresponding to the sequences 1-2-3 of the jobs Job A B 1 5 4 2 7 7 3 3 5arrow_forwardJobs A, B, E, F and G must go through Machines M1 and M2 in that sequence. Use Johnson’s Rule to determine the optimal sequence in which to schedule the jobs to minimise the total required time. How much total time is required to process all the seven jobs? Illustrate this using a Gant Chart. Job Processing time on M1 Processing time on M2 A 4 5 B 16 14 C 8 7 D 12 13 E 3 9 F 9 6 G 8 5arrow_forwardGiven the data below, using the SPT heuristic sequencing rule, determine the completion date and tardiness for each job as well as the average completion time and average tardiness for all four jobs. Which of the following statements is true? Job Processing time (days) Due date (in days) A 10 10 B 5 8 C 15 25 D 8 15 a.Jobs B and D will have no tardiness b.The tardiness for Job A is 12 days c.The average tardiness is 19.75 d.The average completion time is 6.5arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY