Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 9, Problem 30AP
Summary Introduction

Interpretation: The performance according to sequencing rules FCFS, SPT, EDD and CR in relation to minimizing average tardiness has to be evaluated.

Concept Introduction:

Optimal sequence: It is supposed to be sequence or series of jobs that has to take place to minimize the idle time and at the same time all the jobs are completed.

Expert Solution & Answer
Check Mark

Answer to Problem 30AP

When all the 4 sequencing rules are compared, it is found that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.

Explanation of Solution

Given information:

The information given to us is as follows:

    CarsRepair time (days)Promised date
    135
    226
    319
    4411
    558

Let us know calculate the mean flow time and average tardiness.

  Tardiness = Completion time – Promising time

  Average tardiness= Total TardinessTotal number of jobs

An important fact to be kept in mind is that in a situation where the due time is greater than the completion time, the tardiness should be considered as 0.

Calculation of average tardiness and number of tardy jobs using FCFS rule:

FCFS rule states that the person or job coming first will be attended first.

    CarsRepair time (days)Completion timePromised dateTardiness
    (1)(2)(3)(4)

      (5)= (3)(4)

    13

      0+3 =3

    50
    22

      3+2=5

    60
    31

      5+1=6

    90
    44

      6+4=10

    110
    55

      10+5=15

    87
    Total

      39

    7

Completion time is calculated by considering the cumulative of repair time values.

Since, we have derived the tardiness value; let us now calculate the average tardiness.

Calculation of Average Tardiness:

  Average tardiness= Total TardinessTotal number of jobs

  =75=1.4 days

Therefore, the average tardiness according to FCFS rule of sequencing is 1.4 days and the total number of tardy jobs is 1.

Calculation of average tardiness and number of tardy jobs using SPT rule:

SPT when expanded becomes shortest processing time. In the rule, the jobs must be arranged in increasing order according to the processing time.

    CarsRepair time (days)Ranking done in increasing order
    (1)(2)(3)
    133
    222
    311
    444
    555
    Total

After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.

    CarsRepair time after ranking (days)Completion timePromised dateTardiness
    (1)(2)(3)(4)

      (5)= (3)(4)

    31

      0+1 =1

    90
    22

      1+2=3

    60
    13

      3+3=6

    51
    44

      6+4=10

    110
    55

      10+5=15

    87
    Total358

Since, we have derived the tardiness value; let us now calculate the average tardiness.

Calculation of Average Tardiness:

  Average tardiness= Total TardinessTotal number of jobs

  =85=1.6 days

Therefore, the average tardiness according to SPT rule of sequencing is 1.6 days and the total number of tardy jobs is 2.

Calculation of average tardiness and number of tardy jobs using EDD rule:

EDD when expanded becomes Earliest due date. In the rule, the jobs must be arranged in increasing order according to the promised time.

    CarsRepair time (days)Promised dateRanking of promised date done in increasing order
    1351
    2262
    3194
    44115
    5583

After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.

    Cars (corresponding values according to ranks)Repair time (days)

    (corresponding values according to ranks)

    Completion timePromised date after rankingTardiness
    (1)(2)(3)(4)

      (5)= (3)(4)

    13

      0+3 =3

    50
    25

      3+2=5

    60
    55

      5+5=10

    82
    31

      10+1=11

    92
    44

      11+4=15

    114
    Total448

Since, we have derived the tardiness value; let us now calculate the average tardiness.

Calculation of Average Tardiness:

  Average tardiness= Total TardinessTotal number of jobs=85=1.6 days

Therefore, the average tardiness according to EDD rule of sequencing is 1.6 days and the total number of tardy jobs is 3.

Finally, let us calculate the average tardiness and total number of tardy jobs according to CR rule.

CR when expanded becomes Critical Ratio. The formula to be used is as follows:

  Critical ratio=(Due time- Current time)Processing time 

Let us that the current time is 0.

    CarsRepair time (days)Promised dateCritical ratio
    135

      503=1.67

    226

      612=3

    319

      901=9

    4411

      1104=2.75

    558

      805=1.6

Hence, the job having a minimum critical ration should be considered first. In our case, the car 5 has the minimum critical ratio of 1.6. So, it should be considered first for repair. After repair, car 5 can be ignored for further calculations.

Now, the current time for next critical ratio can be calculated as below:

  Current time= Current time + repair time of current job.=0+5=5 days.

Using this new current time, the critical ratio can be calculated for the rest of the cars.

    CarsRepair time (days)Promised dateCritical ratio
    135

      553=0

    226

      622=0.5

    319

      951=4

    4411

      1154=1.5

Hence, the minimum critical ratio is 0 of Car 1. Hence car 1 should be considered for repair.

Further, a new current time has to be calculated.

  Current time= Current time + repair time of current job.=5+3=8 days.

By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.

    CarsRepair time (days)Promised dateCritical ratio
    226

      682=1

    319

      981=1

    4411

      1184=0.75

Hence, car 2 has minimum critical ratio of -1. So, it has to be repaired after car1.

Further, a new current time has to be calculated for the remaining 2 cars

  Current time= Current time + repair time of current job.=8+2=10 days.

By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.

    CarsRepair time (days)Promised dateCritical ratio
    319

      9101=1

    4411

      11104=0.25

Hence, car 3 has minimum critical ratio of -1. So, it has to be repaired after car 2 and the remaining job i.e., repair of car 4 should be done last.

Therefore, the sequence we get using Critical ratio rule is 51234.

After deriving the sequence, we have to calculate the completion time and tardiness.

Calculation of completion time and tardiness:

    CarsRepair time (days)Completion timePromised dateTardiness
    (1)(2)(3)(4)

      (5)= (3)(4)

    55

      0+5=5

    80
    13

      5+3=8

    53
    22

      8+2=10

    64
    31

      10+1=11

    92
    44

      11+4=15

    114
    Total4913

Since, we have derived the tardiness value; let us now calculate the average tardiness.

Calculation of Average Tardiness:

  Average tardiness= Total TardinessTotal number of jobs=135=2.6 days

Therefore, the average tardiness according to CR rule of sequencing is 2.6 days and the total number of tardy jobs is 4.

When all the 4 sequencing rules are compared, we find that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0
a/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7
وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY