Concept explainers
Interpretation: The performance according to sequencing rules FCFS, SPT, EDD and CR in relation to minimizing average tardiness has to be evaluated.
Concept Introduction:
Optimal sequence: It is supposed to be sequence or series of jobs that has to take place to minimize the idle time and at the same time all the jobs are completed.
Answer to Problem 30AP
When all the 4 sequencing rules are compared, it is found that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.
Explanation of Solution
Given information:
The information given to us is as follows:
Cars | Repair time (days) | Promised date |
1 | 3 | 5 |
2 | 2 | 6 |
3 | 1 | 9 |
4 | 4 | 11 |
5 | 5 | 8 |
Let us know calculate the mean flow time and average tardiness.
An important fact to be kept in mind is that in a situation where the due time is greater than the completion time, the tardiness should be considered as 0.
Calculation of average tardiness and number of tardy jobs using FCFS rule:
FCFS rule states that the person or job coming first will be attended first.
Cars | Repair time (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
1 | 3 |
| 5 | 0 |
2 | 2 |
| 6 | 0 |
3 | 1 |
| 9 | 0 |
4 | 4 |
| 11 | 0 |
5 | 5 |
| 8 | 7 |
Total |
| 7 |
Completion time is calculated by considering the cumulative of repair time values.
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to FCFS rule of sequencing is 1.4 days and the total number of tardy jobs is 1.
Calculation of average tardiness and number of tardy jobs using SPT rule:
SPT when expanded becomes shortest processing time. In the rule, the jobs must be arranged in increasing order according to the processing time.
Cars | Repair time (days) | Ranking done in increasing order |
(1) | (2) | (3) |
1 | 3 | 3 |
2 | 2 | 2 |
3 | 1 | 1 |
4 | 4 | 4 |
5 | 5 | 5 |
Total |
After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.
Cars | Repair time after ranking (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
3 | 1 |
| 9 | 0 |
2 | 2 |
| 6 | 0 |
1 | 3 |
| 5 | 1 |
4 | 4 |
| 11 | 0 |
5 | 5 |
| 8 | 7 |
Total | 35 | 8 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to SPT rule of sequencing is 1.6 days and the total number of tardy jobs is 2.
Calculation of average tardiness and number of tardy jobs using EDD rule:
EDD when expanded becomes Earliest due date. In the rule, the jobs must be arranged in increasing order according to the promised time.
Cars | Repair time (days) | Promised date | Ranking of promised date done in increasing order |
1 | 3 | 5 | 1 |
2 | 2 | 6 | 2 |
3 | 1 | 9 | 4 |
4 | 4 | 11 | 5 |
5 | 5 | 8 | 3 |
After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.
Cars (corresponding values according to ranks) | Repair time (days)
(corresponding values according to ranks) | Completion time | Promised date after ranking | Tardiness |
(1) | (2) | (3) | (4) |
|
1 | 3 |
| 5 | 0 |
2 | 5 |
| 6 | 0 |
5 | 5 |
| 8 | 2 |
3 | 1 |
| 9 | 2 |
4 | 4 |
| 11 | 4 |
Total | 44 | 8 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to EDD rule of sequencing is 1.6 days and the total number of tardy jobs is 3.
Finally, let us calculate the average tardiness and total number of tardy jobs according to CR rule.
CR when expanded becomes Critical Ratio. The formula to be used is as follows:
Let us that the current time is 0.
Cars | Repair time (days) | Promised date | Critical ratio |
1 | 3 | 5 |
|
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
5 | 5 | 8 |
|
Hence, the job having a minimum critical ration should be considered first. In our case, the car 5 has the minimum critical ratio of 1.6. So, it should be considered first for repair. After repair, car 5 can be ignored for further calculations.
Now, the current time for next critical ratio can be calculated as below:
Using this new current time, the critical ratio can be calculated for the rest of the cars.
Cars | Repair time (days) | Promised date | Critical ratio |
1 | 3 | 5 |
|
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, the minimum critical ratio is 0 of Car 1. Hence car 1 should be considered for repair.
Further, a new current time has to be calculated.
By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.
Cars | Repair time (days) | Promised date | Critical ratio |
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, car 2 has minimum critical ratio of -1. So, it has to be repaired after car1.
Further, a new current time has to be calculated for the remaining 2 cars
By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.
Cars | Repair time (days) | Promised date | Critical ratio |
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, car 3 has minimum critical ratio of -1. So, it has to be repaired after car 2 and the remaining job i.e., repair of car 4 should be done last.
Therefore, the sequence we get using Critical ratio rule is
After deriving the sequence, we have to calculate the completion time and tardiness.
Calculation of completion time and tardiness:
Cars | Repair time (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
5 | 5 |
| 8 | 0 |
1 | 3 |
| 5 | 3 |
2 | 2 |
| 6 | 4 |
3 | 1 |
| 9 | 2 |
4 | 4 |
| 11 | 4 |
Total | 49 | 13 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to CR rule of sequencing is 2.6 days and the total number of tardy jobs is 4.
When all the 4 sequencing rules are compared, we find that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.
Want to see more full solutions like this?
Chapter 9 Solutions
Production and Operations Analysis, Seventh Edition
- Eight jobs have arrived in the following order: Job Processing Time Due Date 1 7 23 2 3 9 3 5 8 4 2 11 5 6 16 6 9 18 7 14 40 8 4 31 Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. Process in the order they have arrived Flow Time Lateness Tardiness Averagearrow_forwardThe following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forwardin a short essay explain the advantages and disadvantages of shortest processing time (SPT) and earliest due date (EDD) sequencing rules. Under what circumstances might you prefer one over the other?arrow_forward
- The Neptune’s Den Machine Shop specializes in overhauling outboard marine engines. Some engines require replacement of broken parts, whereas others need a complete overhaul. Currently, five engines with varying problems are awaiting service. The best estimates for the labor times involved and the promise dates (in number of days from today) are shown in the following table. Customers usually do not pick up their engines early.Engine Time Since Order Arrived (days) Processing Time, Including Setup (days) Promise Date (days from now) Engine Time Since OrderArrived (days) Processing Time,Including Setup (days) Promise Date (daysfrom now) 50-hp Evinrude 7-hp Johnson 100-hp Mercury 50-hp Honda 75-hp Nautique 4 6 8 1 15 5 4 10 1 3 8 15 12 20 10 a. Develop separate schedules by using the SPT and EDD rules.b. Compare the two schedules on the basis of average flow time, percentage of past due jobs, and maximum past due days for any engine.arrow_forwardA manutacturer is designing a product layout for a new product production. It plans to use a production line for B hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 lasks in total. These tasks are namely, A, 8, CD, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed Starting tasks Cneeds, the tack B to be completed. Also, starting task D needed task B to be completed Task E can only start upon completion of Task C. Whescas starting lask F needs the completion of both the tasks D and E Finally, starting task G needed, task Fto be completed. 1the processing times for tasks, A BC D, E F, andG are 28, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks nule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one OaAB, and C ODAB Oc None…arrow_forwardSix patients are waiting in a hospital emergency room to receive care for various complaints, ranging from a sprained ankle to a gunshot wound. The patients are numbered in the sequence that they arrived and are given a priority weighting based on the severity of the problem. There is only one doctor available.Consider the situation of the emergency room mentioned. Determine the sequence in which patients should be treated in order to minimize the weighted value of the mean flow time.arrow_forward
- As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows: Task Duration(minutes) ImmediatePredecessor a 0.5 - b 0.4 a c 0.5 b d 0.3 - e 1.8 d f 1.9 c g 2 e, f Do each of the following: a. Determine the number of followers for each task. (Please answer number of tasks following task for A-G)arrow_forwardIt has just been completed by a university (or collegesenior )'s management team to implement university-wide computing systems that will support all core business processes, such as a student management information system, payroll and finance systems, and resource management (including a class scheduling system), over a five-year period. This increase in the usage of computer systems has coincided with an increase in the collection of transactional data regarding university business operations, and top management is aware of the potential value of the information contained within this data. As a matter of fact, the university's senior management has set a long-term objective of providing key decision-makers across the institution with business intelligence (BI) tools that would enable them to monitor key performance indicators (KPI) on their desktops. Senior management, on the other hand, recognizes that numerous milestones must be achieved before this objective can be achieved. It is…arrow_forwardA medical equipment testing and calibration service is shown below. The customer usually brings the equipment to the service center. The service process requires service technicians to perform three process steps #1 to #3. Each technician is cross-trained so they can perform any of the three steps. The inspector does step #4 alone. After step #4, two parallel work activities are performed. That is, a shipping clerk packs the work (step #7), while simultaneously, a billing clerk prepares the invoice (step #5), and the customer is contacted by phone for pick-up (step #6). The average throughput is three equipment units per hour. The table below shows the work content of the process steps, activity times in minutes per unit, shared and non-shared work activities, and the type of resource required. There are three service technicians on duty, one inspector, one billing clerk, and one shipping clerk. Activity Time Activity Activity (minutes) Performed By Start - 1 7 Service…arrow_forward
- In a variety of test criteria, the SOT rule contains the best solution. Should the SOT rule be used as a priority rule by a bank's manager? What is the reason for this?arrow_forwardThomas has four assignments due in class tomorrow, and his class times are as follows. Class Time Marketing 304 8 am OM 385 10 am Finance 216 2 pm Psychology 4:30 pm Each class lasts one hour, and Thomas has no other classes. It is now midnight, and Thomas estimates that the marketing, OM, finance, and psychology assignments will take him six, three, four, and two hours, respectively. Use the Excel Sequencing template to determine how he should schedule the work. Can he complete all of it on time? (Hint: Using SPT and EDD. First, convert times to due dates past midnight).arrow_forwardUsing the information presented in the following table, identify the processing sequence that wouldresult using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each method, determine (1) average jobflow time, (2) average job tardiness, and (3) average number of jobs in the system. Jobs are listedin order of arrival. (Hint: First determine the total job time for each job by computing the total processing time for the job and then adding in the setup time. All times and due dates are in hours.)JobProcessingTime per UnitUnitsper JobSetupTimeDueDatea .14 45 0.7 4b .25 14 0.5 10c .10 18 0.2 12d .25 40 1.0 20e .10 75 0.5 15arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,