Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 9, Problem 42AP

(a)

Summary Introduction

Interpretation:The network diagram related to the assembly operation is to be drawn.

Concept Introduction:

The network diagram is used for the graphical representation of all tasks, projects and workflow of the assembly operation.

The following formula will be used −

  Minimum number of station=Total time (T)Minimum cycle time(C)

  Daily production rate=Available time/daycycle time

(b)

Summary Introduction

Interpretation:The minimum cycle time and the minimum number of station required for the operation is to be calculated.

Concept Introduction:

The following formula will be used −

  Minimum number of station=Total time (T)Minimum cycle time(C)

  Daily production rate=Available time/daycycle time

(c)

Summary Introduction

Interpretation: The resulting balance using a cycle time of 45 seconds is to be calculated.

Concept Introduction:

The following formula will be used −

  Minimum number of station=Total time (T)Minimum cycle time(C)

  Daily production rate=Available time/daycycle time

(d)

Summary Introduction

Interpretation: The minimum cycle time which results in four stations balance is to be calculated.

Concept Introduction:

The following formula will be used −

  Minimum number of station=Total time (T)Minimum cycle time(C)

  Daily production rate=Available time/daycycle time

(e)

Summary Introduction

Interpretation: The daily production rate is to be calculated.

Concept Introduction:

The following formula will be used −

  Minimum number of station=Total time (T)Minimum cycle time(C)

  daily production rate=Available time/daycycle time

Blurred answer
Students have asked these similar questions
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description A BCDEFGH Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Legend Code T Time (hrs) 15 55 105 30 20 15 25 15 25 ABCDEFGH Activity Planning Purchasing Excavation Sawing Placement Assembly Infill Outfill Decoration Immediate Predecessor(s) None A A B Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. D, C E F F G, H X C A+ B- C- D- E- F- Q H- 1- O. 0 20 40 60 80 100 120…
The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description A BCDEFGH G I Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Time (hrs) 20 60 100 35 20 10 20 30 Immediate Predecessor(s) None A A B D, C E F F- G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
The Southeastern Sports Company produces golf clubs on an assembly line in its plant in Marietta, Georgia. The final assembly of the woods requires the eight operations given in the following table. (given) a. Draw a network to represent the assembly operation.b. What is the minimum cycle time that can be considered? Determine the balance that results from the ranked positional weight technique for this cycle time.c. By experimentation, determine the minimum cycle time that can be achieved with a three-station balance.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY