Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more stability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 40D minutes available for manufacturing the shoes in the plant each day. Daily demand is 60. The information for the tasks is as follows:
TASK | PERFORMANCE TIME (MIN) | TASK MUST FOLLOW TASK LISTED BELOW |
A | 1 | − |
B | 3 | A |
C | 2 | B |
D | 4 | B |
E | 1 | C, D |
F | 3 | A |
G | 2 | F |
H | 5 | G |
I | 1 | E, H |
J | 3 | I |
- a. Draw the precedence diagram.
- b. Assign tasks to the minimum feasible number of workstations according to the “ranked positioned weight” decision rule.
- c. What is the efficiency of the process you completed in (b)?
- d. What is the idle time per cycle?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind
shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more
stability and better protection against knee, foot, and back injuries. Manufacturing the shoes
requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in
the plant each day. Daily demand is 60. The information for the tasks is as follows:
Performance Time
Task
(in minutes)
1
Н
ABCDEFGH
Task Must Follow
This Task
C, D
ABB GAFG
324-325-
E, H
25
312
|
Required:
a. Draw the precedence diagram showing the task precedence and their times
b. Determine the cycle time associated with the rate of output required.
c. What is the theoretical minimum number of work stations required to satisfy this output rate?
d. Allocate the tasks to work stations taking into consideration the precedence requirements and using
the LOT rule to break ties between feasible tasks.
e. What is the…
Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more stability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are
400
minutes available for manufacturing the shoes in the plant each day. Daily demand is
64.
The information for the tasks is as follows:
Task
Performance
Time (mins)
Predecessors
A
1
−
B
3
A
C
1
B
D
4
B
E
1
C, D
F
3
A
G
2
F
H
5
G
I
1
E, H
J
3
I
a) The efficiency of the assembly line with 5 workstations shown in the figure chosen above=(enter your response as a percentage rounded to one decimal place).
b) The idle time for the assembly line per cycle =minute(s) (enter your…
Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more stability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 400minutes available for manufacturing the shoes in the plant each day. Daily demand is 62.The information for the tasks is as follows:
Task
Performance
Time (mins)
Predecessors
A
1
−
B
3
A
C
1
B
D
4
B
E
1
C, D
F
3
A
G
2
F
H
5
G
I
3
E, H
J
2
I
a-b) The correct precedence relationship with one of the possible assignments of tasks using the "ranked positionedweight" to workstations is shown in Fig 1, 2 or 3
c) The efficiency of the assembly line with 5 workstations shown in the figure…
Chapter 9 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 18PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 20PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Tailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwindshoe, which sells for $210, contains both gas- and liquid-filled compartments to provide morestability and better protection against knee, foot, and back injuries. Manufacturing the shoesrequires 10 separate tasks. There are 400 minutes available for manufacturing the shoes inthe plant each day. Daily demand is 60. The information for the tasks is as follows: Task Performance Time (In minutes) Task Must Follow This task A 1 ___ B 3 A C 2 B D 4 B E 1 C.D F 3 A G 2 F H 5 G I 1 E,H J 3/25 I 1. What is the theoretical minimum number of work stations required to satisfy this output rate? 2. Allocate the tasks to work stations taking into consideration the precedence requirements and usingthe LOT rule to break ties between feasible tasks.arrow_forwardThe Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation. The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 3,000 bottles of this product. TASK TIME (MINUTES) PRECEDING TASK 1 0.1 — 2 0.1 1 3 0.1 2 4 0.2 2 5 0.1 2 6 0.2 3, 4, 5 7 0.1 1 8 0.1 7 9 0.2 8 10 0.1 9 11 0.2 6 12 0.2 10, 11 13 0.1 12 Using the following data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria. Note: Round your answer to the nearest whole percent.arrow_forwardVikiki Furniture, Inc. produces all types of office furniture. The "Executive Secretary" is a sofa-bed that has been designed using ergonomics to provide comfort during long work hours. The sofa-bed sells for $138. There are 580 minutes available during the day, and the average daily demand has been 65 items. There are eight tasks: Task performance time (min) task must follow task listed A 4 -- B 7 -- C 6 A, B D 5 C E 6 D F 7 E G 8 E H 6 F, G Total 49 min What is the Cycle time for this operation?arrow_forward
- Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?arrow_forwardTailwind, Inc., produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide more stability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 60. The information for the tasks is as follows: Performance Time Task Must Follow This Task ABCDEFGHI · Task (in minutes) А В Е Н 1 -324-325- - A B B C, D A F G E, H J 3 | Total 25 Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. c. What is the theoretical minimum number of work stations required to satisfy this output rate? d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks.…arrow_forwardCanine Kernels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see Figure). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product’s price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone, and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Which of the three workstations, W, X, or Y, has the…arrow_forward
- Canine Kernels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the following figure). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product’s price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to working on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day or 40 hours/week. The senior management at Canine…arrow_forwardK Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Product A $2 Step 1 Station W (11 min) Raw…arrow_forwardXYZ Company produces and sells 2 products, Lambda and Gamma, and the production process goes through two departments. Traditionally Manufacturing Overhead (M/O) cost is applied on the basis of direct labor hours (DLH); estimated M/O cost is $ 5,757,500 and the estimated DLH is $12,250 for the most recent period.The team decided to replace traditional plantwide costing system to activity-based costing system. There are 3 activity cost pools which represent 3 activity areas at the plant. Direct Labor wage rate is $ 30 per hour. Compute total cost per unit (for lambda and gamma) using activity-based approach. (round your numbers).arrow_forward
- The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek: Task Performance Time (seconds) Predecessors A 20 − B 30 A C 14 A D 15 A E 12 B, C F 27 D, E This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the production of the new train set = ____ (round your response to one decimal place). c) The theoretical minimum number of workstations is ___ d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) e)How much is the total idle time per cycle for the process? ____ seconds f) What is…arrow_forwardThe Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation. The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 2,500 bottles of this product. TASK 1 4 6 8 9 10 11 12 13 PERFORMANCE TIME TASK MUST (MINUTES) FOLLOW 0.1 0.2 Efficiency 0.2 0.2 0.1 0.3 0.3 0.1 0.3 0.2 0.1 0.1 0.1 2 7 B 9 6 10, 11 12 Using the above data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria. (Enter your answer as a percentage rounded to 1 decimal place.)arrow_forwardThe Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Task Performance Time (seconds) Predecessors A 24 − B 30 A C 12 A D 15 A E 12 B, C F 30 D, E This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the production of the new train set = seconds (round your response to one decimal place).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY