Samuel Smith's company wants to establish an assembly line to manufacture its new product, the iStar phone. Samuel’s goal is to produce 60 iStars per hour. Tasks, task times, and immediate predecessors are as follows:

Chapter 9, Problem 23P, Samuel Smith's company wants to establish an assembly line to manufacture its new product, the iStar

  1. a. What is the theoretical minimum for the number of workstations that Samuel can achieve in this assembly line?
  2. b. Use the most following tasks heuristic to balance an assembly line for the iStar phone.
  3. c. How many workstations are in your answer to (b)?
  4. d. What is the efficiency of your answer to (b)?
Blurred answer
Students have asked these similar questions
9.23 Samuel Smith’s company wants to establish anassembly line to manufacture its new product, the iStar phone.Samuel’s goal is to produce 60 iStars per hour. Tasks, task times,and immediate predecessors are as follows: What is the theoretical minimum for the number of workstations that Samuel can achieve in this assembly line?b) Use the most following tasks heuristic to balance an assemblyline for the iStar phone.c) How many workstations are in your answer to (b)?d) What is the efficiency of your answer to (b)?
Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) ABCDE 24842 12 14 20 Immediate Predecessor A A B, C D Rosenberg's goal is to produce 170 PDAs per hour. a) The cycle time for the production of a PDA = seconds (round your response to two decimal places).
Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task A BCDE Time (sec) 12 14 Workstation # 1 8 5 20 Amelio's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). Immediate Predecessor A A B, C D b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line = 3 (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Tasks Assigned to Workstation A

Chapter 9 Solutions

Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY