Textbook Question
Book Icon
Chapter 9, Problem 22P

The preinduction physical examination given by the U.S. Army involves the following seven activities:

ACTIVITY AVERAGE TIME (MIN)
Medical history 10
Blood tests 8
Eye examination 5
Measurements (e.g., weight, height, blood pressure) 7
Medical examination 16
Psychological interview 12
Exit medical evaluation 10

These activities can be performed in any order, with two exceptions: Medical history must be taken first, and Exit medical evaluation is last at present, there are three paramedics and two physicians on duty during each shift. Only physicians can perform exit evaluations and conduct psychological interviews. Other activities can be carried out by either physicians or paramedics.

  1. a. Develop a layout and balance the line.
  2. b. How many people can be processed per hour?
  3. c. Which activity accounts for the current bottleneck?
  4. d. What is the total idle time per cycle?
  5. e. If one more physician and one more paramedic can be placed on duty, how would you redraw the layout? What is the new throughput?
Blurred answer
Students have asked these similar questions
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The​ activities, immediate​ predecessors, and times appear in the accompanying​ table:                                                                                       Activity Immediate​ Predecessor(s) Time​ (days) A − 4 B − 6 C − 1 D B 10 E A, D 5 F C 5 G E, F 8 This exercise contains only parts​ b, c, and d. Part 2 ​b) The critical activities for the leadership training program development project are ▼   B - D - E - G C - F - G A - E - G . Part 3 ​c) The project length for the leadership training program development project​ =   enter your response here days. Part 4 ​d) Slack time for each of the activities​ is:           Part 5     Part 6     Part 7…
Peter Minn is planning to go to the Department of Motor Vehicles to have his driver’s license renewed. His friend, Patricia, who is accompanying him, is applying for a new license. In both cases there are five steps that are required: (A) having a picture taken, (B) signing a signature verification form, (C) passing a written test, (D) passing an eye test, and (E) passing a driving test.For renewals the steps are performed in the order A, B, C, D, and E with average times required, respectively, of 0.2, 0.1, 0.3, 0.2, and 0.6 hour. In the case of new applications, the steps are performed in the sequence D, B, C, E, and A, with average times required of 0.3, 0.2, 0.7, 1.1, and 0.2 hour, respectively. Peter and Pat go on a day when the department is essentially empty. How should they plan their schedule in order to minimize the time required for both to complete all five steps?
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The​ activities, immediate​ predecessors, and times appear in the accompanying​ table:                                                                                       Activity Immediate​ Predecessor(s) Time​ (days) A − 2 B − 6 C − 1 D B 10 E ​A, D 3 F C 6 G ​E, F 8   This exercise contains only parts​ b, c, and d. ​b) The critical activities for the leadership training program development project are ▼   C - F - G A - E - G B - D - E - G . ​c) The project length for the leadership training program development project​ = enter your response here days. ​d) Slack time for each of the activities​ is:   Activity Slack Time A enter your response here B enter your response…

Chapter 9 Solutions

Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY