The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is
4,800 units per 40-hour workweek:
Task |
Performance Time (seconds) |
|
Predecessors |
A |
20 |
|
− |
B |
30 |
|
A |
C |
14 |
|
A |
D |
15 |
|
A |
E |
12 |
|
B, C |
F |
27 |
|
D, E |
This exercise only contains parts b, c, d, e, and f.
b) Given the demand, the cycle time for the production of the new train set = ____ (round your response to one decimal place).
c) The theoretical minimum number of workstations is ___
d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.)
e)How much is the total idle time per cycle for the process? ____ seconds
f) What is the efficiency of the assembly line with 5 workstations? ___%
Step by stepSolved in 5 steps with 5 images
- A machine cycle, also known as a process loop, comprises four components. Which aspects of machine cycles are most valued? Is it necessary to be concerned about replacing individual components of machine cycles? Does the addition of another module assist in resolving the problem of switching between modules?arrow_forwardThere are six wires which need to be attached to a circuit board. A robotic device will attach the wires. The wires can be attached in any order, and the production manager wishes to determine which order would be fastest for the robot to use. Use the multiplication rule of counting to determine the number of possible sequences of assembly that must be tested. (Hint: There are six choices for the first wire, five for the second wire, four for the third wire, etc.)arrow_forwardssarrow_forward
- The production process shown below consists of five stages. The numbers in parentheses are the times in minutes to complete one unit before it moves on to the next stage. The demand rate is 46 units per hour. 2 workers workers workers Stage A (4 workers Stage B (3) a. How many workers are needed at each stage if management wants a utilization of at least 90 percent? Round your answers down to the nearest whole number. Stage A: workers Stage B: Stage C: Stage D: Stage E: Stage C (6) Stage D (5 Stage E (4arrow_forwardQ6 need in 10 minutearrow_forwardA production process at Brianna Bryant Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 6 units/hr 2.5 units/hr Sawing Sanding Q Assembly 0.8 units/hr Welding 5 units/hr Assembly 0.8 units/hr Drilling 2.1 units/hr a) is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). c) The throughput time of the overall system is minutes (round your response to two decimal places). Assembly 0.8 units/hr d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the manufacturing process is units (enter your response as a whole number).arrow_forward
- An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times: TASK PRECEDINGTASKS PERFORMANCE TIME (SECONDS) TASK PRECEDINGTASKS PERFORMANCETIME (SECONDS) a — 48 g d 43 b — 58 h e 38 c — 73 i f 23 d a 63 j g 33 e b 88 k h, i 53 f c 23 l j, k 67 A) What is the efficiency of your line balance? B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)arrow_forwarda. what is the bottleneck of this process? b. what is the hourly capacity of the process?arrow_forwardAt Feebo Company, components U, V, W, and X are assembled in a cell in daily quantities of 70, 140, 280, and 35, respectively. Assuming a 480-minute workday, assume lot-for-lot, LT = 0. What is the MMP sequence? For the toolbar, press ALT F10 (PC) or ALT-FN+F10 (Mac)arrow_forward
- A production process at Brianna Bryant Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). a) is the bottleneck. 1.8 units/hr Sawing minutes per unit (round your response to two decimal places). 5 units/hr Sanding Drilling 5 units/hr b) The bottleneck time is c) The throughput time of the overall system is minutes (round your response to two decimal places). d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the manufacturing process is Welding 2.5 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr units (enter your response as a whole number). Qarrow_forwardA production process at Brianna Bryant Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). a) is the bottleneck. 1.8 units/hr Sawing minutes per unit (round your response to two decimal places). 5 units/hr Sanding Drilling 5 units/hr b) The bottleneck time is c) The throughput time of the overall system is minutes (round your response to two decimal places). d) If the firm operates 11 hours per day, 20 days per month, the monthly capacity of the manufacturing process is Welding 2.5 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr Assembly 0.8 units/hr units (enter your response as a whole number). Qarrow_forwardWhat components are required to assemble a control unit with vertical coding, and how is it constructed?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.