Question
Chapter 8, Problem 9PA
Summary Introduction
Interpretation:Assembly line needs to be balanced using longest task time method with the help of given precedence diagram.
Concept Introduction: Assembly line balancing is an important task that helps to reduce the cycle time by keeping the precedence relationships as it is.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
RSports is a major retailer of sportswear and equipment in Singapore. It has just signed a lease with a major shopping mall to be one of the anchor tenants and will occupy a floor area of 7,000 square meter (sqm). According to the regulatory requirement, 2% of the floor area must be set aside for emergency assembly purpose. The store layout has 8 major zones, and the company analyst has provided the information (based on other stores’ past data) in Figure 1.1 which shows the annual profit contribution for each zone per sqm.Based on the corporate guidelines, each sports zone requires at least 600sqm of floor space, and none of the sports zone should occupy more than 15% of usable floor space. The Cycling, Home gym, and Fitness sports zones keep some items in inventory (such as bicycles, treadmills, weights) and an equivalent space of 10 to 20% of the floor space allocated to these three sports zones must be set aside for stocking the spares. Administrative office and checkout counters…
Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce
five
poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows:
Task
Performance Time (mins)
Task Must Follow Task Listed Below
A
8
−
B
11
A
C
10
A, B
D
9
B, C
E
8
C
F
4
D, E
A
C
F
B
E
D
In the diagram, there are 6 circles labeled using the letters from A to F. There are 8 of arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: A to B, A to C, B to C, C to D, B to D, C to E, D to F, and E to F.
Part 2
a) The theoretical minimum number of
workstations=55
(round your response up to the…
The following assembly tasks (with performance time in minutes and task precedence) are to be configured into a balanced assembly line layout. There are 12 separate assembly elements (A-L) to complete
the product. Note: The target is to produce 6 units per hour (60 min). please select more than 5 workstations in this problem as per the guidelines of the lecture note.
Element (Min)
Preceded Bv
A
B
C
D
E
F
G
H
1
J
K
L
Time
2.5
4.5
3.5
4.0
3.2
2.0
2.7
7.0
6.0
3.8
5.0
4.3
A
A
A
B
B. C
D
D
ΤΑ
E
F, G
H
I. J. K
a) Construct the precedence diagram
b) Determine the total work content time.
c) Use the "Longest Task Time" rule to assign work elements to stations (also known as "Largest Candidate Method".
d) Calculate the efficiency of your solution.
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear What is the maximum possible output of the line? What is the theoretical minimum number of workstations using the cycle time computed in” b “above Assign tasks to workstations using the cycle time in “b” above.arrow_forwardThe desired daily output for an assembly line is 360 units. This assembly line will operate 450 minutes per day. The following table contains information on this product’s task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 35 A C 30 A D 35 B E 15 C F 65 C G 40 E, F H 25 D, G What is the required workstation cycle time to meet the desired output rate? Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. Note: Leave no cells blank - be certain to enter "0" wherever required.arrow_forwardXYZ company provides labor and space for the manufacturing and assembly operations and stocking various inventory items for production such as wire, cables, some electronic components, etc. XYZ company orders a variety of components and raw materials by contract. The company recently hired 100 part-time employees working four to six-hour shifts. Skilled employees must do several raw material conversions for packaging—there are currently three (3) such employees. The plant layout is a typical process layout - machines of similar types are located together. Each machine and employee must be scheduled over the day and the standard time period for planning is one (1) hour. Material handling is mainly done manually, although the company would like to consider conveyors or other automation to aid in automating their processes. XYZ company forecasts planned production for two (2) years on a rolling quarterly basis. Often, the customer changes the forecast, and these changes can occur as…arrow_forward
- The photo shows the layout of a fish smoking plant doing batch production. The smokehouse and the smoking protocol that they are using can have three (3) production runs in an eight-hour workday. However, due to constraints and delays, their actual output is only 2 production runs/batches (design capacity: 4 runs; effective capacity: 3 runs; actual capacity: 2 runs). Based on the existing plant facility layout, identify the parts that cause the constraints like delays. Solve for Efficiency and Utilization. Suggest an alternative layout by moving/transferring the processing areas (blue boxes) to make the production system more efficient. Take note, though, that the smokehouse and the drying facility (yellow boxes) are built-in and immovable. Give a short rationale for each recommendation.arrow_forwardAn industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) A none 10 B A 14 В 20 B 16 E C,D 12 8 Design this layout using the decision rule of Longest Processing Time (LPT). What is the theoretical minimum number of work stations? a. Three b. One Oc. Two d. Five e. Fourarrow_forwardConsider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes: TASK ELEMENT TIME (MINUTES) PRECEDING TASK A 1 — B 1 A C 2 B D 1 B E 3 C, D F 1 A G 1 F H 2 G I 1 E, H Given a cycle time of four minutes, develop two alternative layouts. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the highest efficiency of your layout, assuming the 4-minute cycle time? Note: Enter your answer as a percentage rounded to 2 decimal places.arrow_forward
- Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task A B с D E Amelio's goal is to produce 175 PDAs per hour. a) The cycle time for the production of a PDA = Time (sec) 12 14 8 4 20 Immediate Predecessor A A B, C D seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Amelo can achieve in this assembly line fround your response up to the next whole number). = Were you able to assign all the tasks to the theoretical minimum number of workstations? c) For one to assign the tasks to the actual workstations and be able to use the theoretical minimum number, the activity assignment should be Workstation Tasks Assigned to Workstationarrow_forwardManagement wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forwardAn industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) A none 10 В A 14 20 D В 16 E C,D 12 E 8 Design this layout using the decision rule of Longest Processing Time (LPT). What is the cycle time of this assembly line? a. 30 seconds b. 36 seconds O. 8 seconds d. 74 seconds e. 24 secondsarrow_forward
- Given in the following table are the tasks necessary for final assembly of a hospital bed, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations. Construct a precedence diagram and balance the assembly line for a desired cycle time of 14 minutes. Draw a schematic diagram of the balanced line. How many beds can actually be assembled in an eight-hour period? Element Precedence Time (min) A None 4 B None 5 C None 8 D A 4 E A, B 3 F B 3 G D, E 5 H F 7 I G, H 1 J I 7 K C, J 4arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description A BCDEFGH Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Legend Code T Time (hrs) 15 55 105 30 20 15 25 15 25 ABCDEFGH Activity Planning Purchasing Excavation Sawing Placement Assembly Infill Outfill Decoration Immediate Predecessor(s) None A A B Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. D, C E F F G, H X C A+ B- C- D- E- F- Q H- 1- O. 0 20 40 60 80 100 120…arrow_forwardGibson Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, immediate predecessors, and precedence diagram for producing one Micro Popcorn Popper are as follows Task A B C D E F Time (min) 10 12 8 10 7 5 Immediate Predecessors A AB B,C С D.E a) The theoretical minimum number of workstations (Round your response up to the next whole number)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY