EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8PA
Summary Introduction
Interpretation:Assembly line needs to be balanced using longest task time method with the help of given precedence diagram.
Concept Introduction: Assembly line balancing is an important task that helps to reduce the cycle time by keeping the precedence relationships as it is.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation.
The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 3,000 bottles of this product.
TASK
TIME (MINUTES)
PRECEDING TASK
1
0.1
—
2
0.1
1
3
0.1
2
4
0.2
2
5
0.1
2
6
0.2
3, 4, 5
7
0.1
1
8
0.1
7
9
0.2
8
10
0.1
9
11
0.2
6
12
0.2
10, 11
13
0.1
12
Using the following data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria.
Note: Round your answer to the nearest whole percent.
Natura has to fill 7 orders for its clients. He requires placing the required product in work boxes and subsequently closing them properly so that the product reaches the customer correctly. The process consists of filling the box and later closing it. As the content of each box and the size of these is different, the filling and closing times of each order is different. These times are shown in the table below.
Orders
Place in box (minutes)
Closing Box
(minutes)
1
9
6
2
8
5
3
7
7
4
6
3
5
1
2
6
2
6
7
4
7
a) Find the sequence to complete the orders in the shortest time possible. b) Using a Gantt chart, find the total time in which all orders will be completed using the sequence from part a.
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the totaltime for all tasks is 18 minutes. The line will operate for 450 minutes per day.a. What are the minimum and maximum cycle times?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 2-The process of making hotdogs involves six activities: “grind”, “mix”, “stuff”, “cook”, “peel”, and “inspect”. If the capacity of activity “cook” determines the process capacity, which of the following statements are true? a- Activity “cook” is a bottleneck activity. b- The activity time of all the other five activities is shorter than activity "cook". c- Cycle time of the process of making hotdogs is equal=1/capacity of activity “cook”. d- Increasing the capacity of activity “grind” can increase the capacity of the process of making hotdogs. All statements are correct Only statement 'b' is correct Only statements 'a' and 'b' are correct Only statements 'a', 'b' and 'c' are correct Only statement 'a' is correct Only statement 'd' is correctarrow_forwardFrancis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forwardFiona cleans offices. She is allowed 5 seconds per square foot. She cleans building A, which is 3,024 square feet, and building B, which is 2,424 square feet. Will she finish these two buildings in an 8-hour shift? Will she have time for a break? Round intermediate calculations to two decimals and final answer to whole number. (yes or no), she (will or will not) finish in an 8-hour shift, and she (can or cannot) have a break of _____ minutes.arrow_forward
- As the Cottrell Bicycle Co. of St. Louis completes plans for its new assembly line, it identifies 25 different tasksin the production process. VP of Operations Jonathan Cottrell now faces the job of balancing the line. He lists precedencesand provides time estimates for each step based on work-sampling techniques. His goal is to produce 1,000 bicycles perstandard 40-hour workweek.Balance this operation using the shortest operation time rule and compute the efficiency of the line.arrow_forwardcan someone help me with this: As Patrick Sportwear Co. completes plans for its new assembly line in Liverpool, it identifies 30 different tasks in the production process. VP of Operations Kevin Keegan now faces the job of balancing the line. He lists precedences and provides time estimates for each step based on work-sampling techniques. His goal is to produce 1.000 football shoes per standard 35-hour workweek. Task Time (sec) Immediate Predecessors Task Time (sec) Immediate Predecessors B1 50 - E2 18 G5, F3 K4 24 B1 A4 10 E1 K9 27 B1 E3 109 F3 J1 66 B1 D6 53 F4 C2 12 - D7 72 F9, E2, E3, K9 J2 22 B1 C1 78 F7, A4 J3 3 C2 D8 78 E3, D6 D5 6 - D9 37 D6, A4 G4 79 K4, K9 C3 40 F9, D7 G5 29 K9, J1 B3 72 D7, D8, D9, C1 F3 32 J2 B5 108 C1 F4 92 J2 A1 52 B5 F7 21 J3 B7 18 A1, B3, C3 E1 20 C2…arrow_forwardScenario C: Suppose you are given the process flowchart shown below. There are no buffers between tasks. Task 1 and 2 produce "Part A", and Task 3 and 4 produce "Part B"; Task 5 assembles each unit of a finished product by combining one unit of "Part A" with one unit of "Part B". Using this, answer the next 3 questions: Tpt Cap. = 10 units/hour- Tpt Cap. = 15 units/hour Task 1 5 ● 8 10 15 20 Task 3 Tpt Cap. = 5 units/hour Task 2 Tpt Cap. = 8 units/hour Task 4 Tpt Cap. = 20 units/hour Task 5 In this scenario, how many units would Task 5 actually produce each hour? Pick the closest answer. FGIarrow_forward
- A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 1.8 units/hr Sawing 5 units/hr Sanding Drilling 6 units/hr a) Sawing is the bottleneck. b) The bottleneck time is minutes per unit (round your response to two decimal places). Welding 2.2 units/hr Assembly 0.7 units/hr →→Assembly 0.7 units/hr Assembly 0.7 units/hr Qarrow_forwardThe table below shows the time for each work element in an manual assembly process, along with the predecessor(s) required for each element. The ideal cycle time is 1.4 minutes, the repositioning time is 0.1 minutes, and there is one worker at each station. Work element A B C D E F G H I J Time (minutes) 0.7 0.4 0.2 0.3 0.5 0.4 0.6 0.5 0.3 0.2 Immediate predecessors - A A B B C E,F D,E G,H I 1. Using the ranked positional weights method, assign work elements to stations.arrow_forwardManagement of the Just Like Home Restaurant has asked you to analyze some of its processes. One of these processes is making a single-scoop ice cream cone. Cones can be ordered by a server (for table service) or by a customer (for takeout). Process: Making one ice cream cone Summary Subject: Server at counter Activity # of Step Time Distance Beginning: Walk to cone storage area Operation Ending: Give it to service or customer Transport Inspect Insert Step Delay Append Step Store Remove Step Step #. Time (min) Distance (feet) Step Description 1 0.2 5 X Walk to Cone Storage Area 2 0.05 X…arrow_forward
- A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Time Task Predecessor (seconds) A 50 A 36 26 22 E B, D 70 F C, E 30 What is the required cycle time in seconds in order to meet the projected demand? (Answer with two decimal places i.e. 26.00, 326.80) Answer: B C Darrow_forward. Bill's Barbershop has two barbers available to cut customers' hair. Both barbers provide roughly the same experience and skill, but one is just a little bit slower than the other. The process flow in Figure 6.90 shows that all customers go through Steps B1 and B2 and then can be served at either of the two barbers at Step B3. The process ends for all customers at Step B4. The numbers in parentheses indicate the minutes it takes that activity to process a customer. Figure 6.9 Process Flow for Bill's Barbershop B1 (10) B2 B3-a (15) B3-b (10) B4 (9) 1. On average, how long does it take a customer to complete this process? ›. What single activity is the bottleneck for the entire process? c. How many customers can this process serve in an hour?arrow_forward5. Flo's Quick-Lube performs fast oil changes (A) and checks for tire pressure and wear (B) and brakes and alignment (C) according to the process flow indicated by the diagram below. Each incoming car is put on a jack while one technician performs task A and another simultaneously performs task B and a third performs task C (which must follow task B due to the limited space under the vehicle on the jack). The server for task A takes on average 3 minutes to process a job, the server for task B takes on average 2 minutes to process a job, and the server for task C takes on average 2 minutes to process a job. Server A can be operated in parallel with Servers B and C. All processing times are random and exponentially distributed, and jobs are allowed to queue in front of each server. (You can assume that the number of jacks is sufficient to allow any length of queue.) (a) AND B A C Figure 1: Flo's Process Flow What is the capacity of the process (in orders/minute)?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY