EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 11PA
Summary Introduction
Interpretation:Production line needs to be designed to achieve an output rate of 90 per hour.
Concept Introduction: Assembly line balancing is an important task that helps to reduce the cycle time by keeping the precedence relationships as it is.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the supply chain involved with an Amazon customer ordering a book. Determine the push/pull boundary and two processes for each step (push and pull).
The company has the following information about its two service departments and two production departments, Cutting and Assembly:
Departments
SquareFeet
Number ofEmployees
Maintenance Department
500
20
Cafeteria Department
1,400
10
Cutting Department
1,500
60
Assembly Department
7,100
20
What is the percentage (proportional) usage of the Maintenance Department by the Cutting Department?
The figure below shows the process for customers arriving at a local hobby store for several advertised crafts demonstrations. After signing in, customers are routed to
different locations in the store for the two different programs provided. The numbers in parentheses are the time in minutes for each step of the process.
A
(5)
B
(10)
Answer:
с
(15)
E
(30)
D
(20)
F
(15)
G
(10)
How many customers can be processed through the A-B-C-D-G routing during a 4-hour evening session?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 3.Consider the following three-stage production process of glass ceramics. The process is experiencing severe quality problems related to insufficiently trained workers. Specifically, 20 percent of the parts going through operation 1 are badly processed by the operator. Rather than scrapping the unit, it is moved to a highly skilled rework operator, who can correct the mistake and finish up the unit completely within 15 minutes. The same problem occurs at station 2, where 10 percent of the parts are badly processed, requiring 10 minutes of rework. Station 3 also has a 10 percent ratio of badly processed parts, each of them requiring 5 minutes by the rework operator. a)What is the utilization of station 2 if work is released into the process at a rate of 5 units per hour? b)Where in the process is the bottleneck? Why? (Remember, the bottleneck is the resource with the lowest capacity, independent of demand.)arrow_forwardWilliams Performance Co. manufactures sports cars. After making a sale, the salesperson sends thecar to be detailed before the customer takes it home. Detailing the car takes 30 minutes at a cost of$15 per hour for direct labor and $5 per car for materials. If the company is open 5 days per week andsells an average of five cars per day, what is the average cost per 5-day week for detailing cars?arrow_forwardThe Swanky Hotel provides room service for its guests. The process for room service begins with a room service manager who takes orders by phone at an average of 2 minutes per order. The manager then sends the order to the kitchen, where it takes a cook an average of 16 minutes to prepare the food for each order. There are four cooks in the kitchen. If the customer orders a beverage, the room service manager sends the order to the bar at the same time the order is sent to the kitchen. It takes 3 minutes for a bartender to fill the order, and 80 percent of the orders require a beverage. When the kitchen and bar orders are both ready, a waiter takes them to the room and bills the guest. There are six waiters to provide the service, and each order takes 20 minutes for the waiter to complete.a. What is the capacity of the process, and what is the bottleneck?b. What is the throughput time of a typical order?c. Assume that on Friday evenings an average of 10 room-service orders per hour are…arrow_forward
- The Swanky Hotel provides room service for its guests. The process for room service begins with a room service manager who takes orders by phone at an average of 5 minutes per order. The manager then sends the order to the kitchen, where it takes an average of 16 minutes to prepare the food for each order. There are four chefs in the kitchen. If the customer requires a beverage (alcoholic or nonalcoholic), the room service manager sends the order to the bar at the same time the order is sent to the kitchen. It takes 3 minutes to fill the order by one bartender, and 80 percent of the orders require a beverage. When the kitchen and bar orders are both ready, a waiter will take them to the room and bill the guest. There are six waiters to provide the service, and each order takes 20 minutes for the waiter to complete. What is the capacity of the process, and what is the bottleneck? What is the throughput time of a typical order? Assume that on Friday evenings an average of 10…arrow_forwardThe Swanky Hotel provides room service for its guests. The process for room service begins with a room service manager who takes orders by phone at an average of 5 minutes per order. The manager then sends the order to the kitchen, where it takes an average of 16 minutes to prepare the food for each order. There are four chefs in the kitchen. If the customer requires a beverage (alcoholic or nonalcoholic), the room service manager sends the order to the bar at the same time the order is sent to the kitchen. It takes 3 minutes to fill the order by one bartender, and 80 percent of the orders require a beverage. When the kitchen and bar orders are both ready, a waiter will take them to the room and bill the guest. There are six waiters to provide the service, and each order takes 20 minutes for the waiter to complete. Assume that on Friday evenings an average of 10 room-service orders per hour are placed. How many orders are in the system on average on Friday nights?arrow_forwardA procedure at Mercy Hospital has fixed costs of $10,000 per year and variable costs of $50 per test. If the procedure is automated, its fixed cost will be$21,500 per year, but its variable cost will be only $10 per test. The number of tests that must be performed each year for the two operations to break even is closest to:arrow_forward
- Refer to Exhibit 7.5 on page 143. (Please see exhibit 7.5 in the attachment) Study the Automobile Flow Chart and review the concept of Process and Value Stream Mapping. Select a Service process (other than auto repair) and create a Process Map for the Service that you have chosen. Be sure to be specific and complete in the steps that you include in your Process Maparrow_forwardThe following flow chart shows the entire manufacturing process at KD Manufacturing, which consists of six independent operations processes (i.e. sawing, sanding, drilling, reshaping, welding, and assembly). The entire process flow starts with the input of three different parts, Part I, Part II and Part III, each entering a different input line. Three parts meet later for the welding, whichever welding station is available (two identical welding stations work independently). After welding is completed, the product is sent to one of the three assembly stations (which are in parallel). The chart also shows the processing time per unit (in minutes) for each operation. Each of sawing, sanding, drilling and reshaping stations is handled by a different worker. Two workers handle welding, each at one welding station. Another three workers handle the assembly process independently, one at each assembly station. To improve the capacity of the entire manufacturing process, the manager decides to…arrow_forwardHow does seasonal variability in demand affect the flow and waiting time through a process? How might a company respond to reduce the effect of this variability?arrow_forward
- Consider a production process described by the following flowchart, on which the process time of each station is indicated. Station 1 Station 2 Station 3 10 min 15 min 20 min Suppose that the fixed cost for build the process is $15,000 (including the cost to build the facility, purchase of the machines, recruiting the operators, etc.). After the process is established, it is expected that it will operate at its capacity rate. The marginal profit for each unit produced is $5 (revenue minus variable cost). What is the break-even time in hours?arrow_forwardDraw the ER diagram for the following business rules: a customer may buy many houses theater must show at least one movie a house should have at least one room and the room is belonging to only one housearrow_forwardDr. Gulakowicz is an orthodontist. She estimates that adding two new chairs will increase fixed costs by $150,000, including the annual equivalent cost of the capital investment and the salary of one more technician. Each new patient is expected to bring in $3,000 per year in additional revenue, with variable costs estimated at $1,000 per patient. The two new chairs will allow Dr. Gulakowicz to expand her practice by as many as 200 patients annually. How many patients would have to be added for the new process to break even?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY