Textbook Question
Chapter 5, Problem 12E
Comparing High-Low Method and Least-Squares Regression Results
Consider Camp Rainbow’s Cost estimated in E5- 10 using the high-low method and in E5-11 using regression. The two methods yielded very different results, especially in their estimates of fixed cost.
1. Describe the differences in the cost estimates generated by these two methods.
2. Explain why you believe the differences exist.
3. Explain which method is more reliable and why.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following statements related to cost estimation methods is true?
O a. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified
with the highest and lowest volume levels.
O b. The high-low method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and
least-squares regression methods.
O c. None of the given answers.
O d. Only high-low method has a slope and an intercept.
e.
The most complex method of cost estimation is the high-low method.
Which of the following methods of cost estimation relies on only two data points?A. the high-low methodB. account analysisC. least-squares regressionD. SWOT analysis.
Which of the following statements related to cost estimation methods is true ?
a . Only high -low method has a slope and an intercept .
b. The scatter - graph method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels .
c. The most complex method of cost estimation is the high - low method .
d. The least -squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter -graph plot and high -low methods .
e. None of the given answers
Chapter 5 Solutions
Managerial Accounting
Ch. 5 - Define each of the following terms variable cost,...Ch. 5 - Prob. 2QCh. 5 - Prob. 3QCh. 5 - Prob. 4QCh. 5 - Prob. 5QCh. 5 - Describe the three methods used to estimate cost...Ch. 5 - Prob. 7QCh. 5 - Prob. 8QCh. 5 - Prob. 9QCh. 5 - Prob. 10Q
Ch. 5 - Prob. 11QCh. 5 - Prob. 12QCh. 5 - Prob. 13QCh. 5 - Prob. 14QCh. 5 - Which of the following increases when activity...Ch. 5 - Prob. 2MCCh. 5 - Prob. 3MCCh. 5 - Consider the following information for a local...Ch. 5 - Prob. 5MCCh. 5 - Prob. 6MCCh. 5 - Prob. 7MCCh. 5 - Prob. 8MCCh. 5 - Prob. 9MCCh. 5 - Hathaway Corp, manufactures garden hoses. Last...Ch. 5 - Identifying Cost Behavior Heather Oak is trying to...Ch. 5 - Prob. 2MECh. 5 - Defining Cost Behavior Match each of the following...Ch. 5 - Prob. 4MECh. 5 - Defining Terms for the High-Low Method Indicate...Ch. 5 - Prob. 6MECh. 5 - Prob. 7MECh. 5 - Prob. 8MECh. 5 - Prob. 9MECh. 5 - Prob. 10MECh. 5 - Prob. 11MECh. 5 - Prob. 12MECh. 5 - Prob. 13MECh. 5 - Prob. 14MECh. 5 - Prob. 15MECh. 5 - Prob. 16MECh. 5 - Compare full absorption costing to variable...Ch. 5 - Identifying Cost Behavior Patterns Steve...Ch. 5 - Prob. 2ECh. 5 - Prob. 3ECh. 5 - Prob. 4ECh. 5 - Estimating Cost Behavior Using High-Low Method...Ch. 5 - Prob. 6ECh. 5 - Prob. 7ECh. 5 - Prob. 8ECh. 5 - Prob. 9ECh. 5 - Estimating Cost Behavior Using Scattergraph and...Ch. 5 - Estimating Cost Behavior Using Least-Squares...Ch. 5 - Comparing High-Low Method and Least-Squares...Ch. 5 - Preparing Contribution Margin Income Statement...Ch. 5 - Determining Cost Behavior, Preparing Contribution...Ch. 5 - Prob. 15ECh. 5 - Prob. 16ECh. 5 - Prob. 17ECh. 5 - Prob. 18ECh. 5 - Comparing Full Absorption Costing and Variable...Ch. 5 - Estimating Cost Behavior Using Least-Squares...Ch. 5 - Prob. 1.1GAPCh. 5 - Prob. 1.2GAPCh. 5 - Prob. 1.3GAPCh. 5 - Prob. 1.4GAPCh. 5 - Prob. 1.5GAPCh. 5 - Prob. 1.6GAPCh. 5 - Prob. 2.1GAPCh. 5 - Prob. 2.2GAPCh. 5 - Prob. 2.3GAPCh. 5 - Prob. 2.4GAPCh. 5 - Prob. 2.5GAPCh. 5 - Prob. 2.6GAPCh. 5 - Prob. 2.7GAPCh. 5 - Prob. 3.1GAPCh. 5 - Prob. 3.2GAPCh. 5 - Prob. 3.3GAPCh. 5 - Prob. 3.4GAPCh. 5 - Prob. 3.5GAPCh. 5 - Prob. 4.1GAPCh. 5 - Prob. 4.2GAPCh. 5 - Prob. 4.3GAPCh. 5 - Comparing Full Absorption and Variable Costing...Ch. 5 - Comparing Full Absorption and Variable Costing...Ch. 5 - Prob. 5.3GAPCh. 5 - Prob. 6.1GAPCh. 5 - Prob. 6.2GAPCh. 5 - Prob. 6.3GAPCh. 5 - Prob. 6.4GAPCh. 5 - Prob. 6.5GAPCh. 5 - Prob. 6.6GAPCh. 5 - Prob. 1.1GBPCh. 5 - Prob. 1.2GBPCh. 5 - Prob. 1.3GBPCh. 5 - Prob. 1.4GBPCh. 5 - Estimating Cost Behavior Using Scattergraph,...Ch. 5 - Prob. 1.6GBPCh. 5 - Prob. 2.1GBPCh. 5 - Estimating Cost Behavior Using Scattergraph,...Ch. 5 - Prob. 2.3GBPCh. 5 - Prob. 2.4GBPCh. 5 - Prob. 2.5GBPCh. 5 - Prob. 2.6GBPCh. 5 - Prob. 2.7GBPCh. 5 - Prob. 3.1GBPCh. 5 - Prob. 3.2GBPCh. 5 - Prob. 3.3GBPCh. 5 - Prob. 3.4GBPCh. 5 - Prob. 3.5GBPCh. 5 - Prob. 4.1GBPCh. 5 - Prob. 4.2GBPCh. 5 - Prob. 4.3GBPCh. 5 - Prob. 5.1GBPCh. 5 - Prob. 5.2GBPCh. 5 - Prob. 5.3GBPCh. 5 - Prob. 6.1GBPCh. 5 - Prob. 6.2GBPCh. 5 - Prob. 6.3GBPCh. 5 - Prob. 6.4GBPCh. 5 - Prob. 6.5GBPCh. 5 - Prob. 6.6GBP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Explain why cost predictions based on the same cost driver can differ when applying the high-low method and regression analysis. State one advantage and one disadvantage of the high-low method.arrow_forwardWhich of the following statements related to cost estimation methods is true? O a. The most complex method of cost estimation is the high-low method. O b. The high-low method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and least-squares regression methods. O c. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. O d. Only high-low method has a slope and an intercept. O . None of the given answers.arrow_forwardWhich of the following statements related to cost estimation methods is false? a. The least-squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and high-low methods. O b. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. O c. The most complex method of cost estimation is the high-low method. O d. None of the given answers. O e. The three methods determine a slope and an intercept.arrow_forward
- Which of the following statements related to cost estimation methods is false? The least-squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and high-low methods. O b. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. The three methods determine a slope and an intercept. O d. None of the given answers. The most complex method of cost estimation is the high-low method.arrow_forwardHigh-low and regression cost estimation methods are alike in that they both: Select one: O a. Have a slope term but not an intercept term. O b. Provide the same accuracy and reliability O c. Have an intercept term but not a slope term. O d. Have an intercept term and a slope term.arrow_forwardWhich of the following is NOT true of regression techniques for estimating costs? a) They permit the inclusion of more than one predictor. b) They typically use the highest and lowest activity points to estimate the relation between cost and activity. c) They help develop estimates that have a broader base than those based on a few select points. d) They are designed to generate a line that best fits a set of data points.arrow_forward
- Which of the following statements related to cost estimation methods is false? O a. The most complex method of cost estimation is the high-low method. The low-high method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels. None of the given answers. O d. The least-squares regression method is the most accurate and reliable method to determine the cost behavior compared to scatter-graph plot and high-low methods. e. The three methods determine a slope and an intercept.arrow_forwardAn easy way to estimate the variable and fixed costs components of a mixed cost is by: 1. a scatter plot 2. the high-low method 3. a regression analysis 4. a guesstimatearrow_forwardLeast-squares regression is a statistical method for identifying cost behavior. True or False Truearrow_forward
- 7. Which of the following charts best represent total variable costs? For each chart, the line represents the cost behavior pattern, the vertical axis represents costs, and the horizontal axis represents total volume, (A) Your answer is (B) (C) (D) Explain your answer: 8. Which of the following is NOT a cost estimation method? A) High-low cost estimation B) Scatter diagrams C) Least-square regressions D) CVP analysis Your answer is Explain your answer: 9. Assume a local Cost Cutters provides cuts, perms, and hairstyling services. Annual fixed costs are $120,000, and variable costs are 40 percent of sales revenue. Determine its break-even point in sales dollars. A) $250,000 B) $200,000 c) $240,000 D) $360,000 Your answer is Explain your answer:arrow_forwardObtaining regression estimates for cost estimation requires establishing the existence of a logical relation between activities and the cost to be estimated. Which of the following is not used to refer to these activities? Multiple Choice predictors. dependent variables. X terms. independent variables.arrow_forwardWhich of the following statements related to cost ?estimation methods is true .a None of the given answers .b The most complex method of cost .estimation is the high-low method .c The scatter-graph method is used to derive an estimated line of cost behavior by graphically connecting the two cost amounts identified with the highest and lowest volume levels .d The three methods determine a slope and an .intercept .e The high-low method is the most accurate Ox and reliable method to determine the cost behavior compared to scatter-graph plot and least-squares regression methodsarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
How to Estimate Project Costs: A Method for Cost Estimation; Author: Online PM Courses - Mike Clayton;https://www.youtube.com/watch?v=YQ2Wi3Jh3X0;License: Standard Youtube License