Consider a four-step serial process with processing times given in the following list. There is one machine at each step of the process, and this is a machine-paced process.
- Step 1: 25 minutes per unit
- Step 2: 15 minutes per unit
- Step 3: 30 minutes per unit
- Step 4: 20 minutes per unit
Assuming that the process starts out empty, how long will it take (in hours) to complete a batch of 105 units? [LO3-5]
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the following batch-flow process consisting of three process stepsperformed by three machines.
Process steps
step 1
step 2
step 3
processing time
0.25min./unit
0.20 min./unit
0.15 min./unit
setup time
30 min
20 min
45 min
Work is processed in batches at each step. Before a batch is processed at a step, the machine atthat step must be set up. (During a setup, the machine is unable to process any product.) Assumethat there is a dedicated setup operator for each machine (i.e., there is always someone availableto perform a setup at each machine.)a. What is the capacity of step 1 if the batch size is 35 parts?b. For what batch sizes is step 1 (2, 3) the bottleneck?
Consider a parallel process with two stages where the processing time of each stage is 15 minutes
per unit. What is the minimum cycle time of the parallel process in minutes per unit? Answer with
one decimal place (e.g., 20.1), if your answer involves any decimals. Provide only the number (do not
put "min/unit").
Consider a production line with five stations in serial. The stations have the following process times in minutes (or minutes/unit).
Station 1's process time is 9 minutes/unit. Station 2's process time is 10 minutes/unit. Station three has two identical machines, each of which process a unit in 12 minutes (each unit only needs to be processed on one of the two machines). Station 4's process time is 5 minutes/unit. Station 5's process time is 8 minutes/unit. Which station is the bottleneck station?
a)
Station 3
b)
None of the other options
c)
Station 2
d)
Station 5
Chapter 3 Solutions
Operations Management
Ch. 3 - Prob. 1CQCh. 3 - Prob. 2CQCh. 3 - Prob. 3CQCh. 3 - Prob. 4CQCh. 3 - You observe a long line at the airport security....Ch. 3 - Prob. 6CQCh. 3 - What is the maximum utilization a resource can...Ch. 3 - Is the capacity of the bottleneck larger than,...Ch. 3 - Prob. 9CQCh. 3 - You observe a vehicle registration department at...
Ch. 3 - Prob. 1PACh. 3 - A community health systems nurse team consists of...Ch. 3 - Consider a process consisting of three resources....Ch. 3 - Prob. 4PACh. 3 - Prob. 5PACh. 3 - Prob. 6PACh. 3 - Prob. 7PACh. 3 - Consider a four-step serial process with...Ch. 3 - Consider a four-step serial process with the...Ch. 3 - Prob. 10PACh. 3 - Prob. 11PACh. 3 - The Tesla Model S, one of the most sought-after...Ch. 3 - The Tesla Model S, one of the most sought-after...Ch. 3 - The Tesla Model S, one of the most sought-after...Ch. 3 - The Tesla Model S, one of the most sought-after...
Additional Business Textbook Solutions
Find more solutions based on key concepts
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (11th Edition)
What is precedent, and how does it affect common law?
Business in Action
The Big Black Bird Company (BBBC) has a large order for special plastic-lined military uniforms to be used in a...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 67. The number of resources requested by a process : a. must always be less than the total number of resources available in the system b. must always be equal to the total number of resources available in the system c. must not exceed the total number of resources available in the system d. must exceed the total number of resources available in the systemarrow_forwardA cell-phone repair shop consists of three processes. Step 1 requires 4 minutes per unit, step 2 requires 6 minutes per unit and step 3 requires 2 minutes per unit. 40% of units that complete the third step require rework, which means those units must start the process over at step 2 (processing times are the same for units being reworked) and rework is always successful. Demand at the shop is 0.8 units per minute. Instruction: Round your answer to three decimal places. What is the capacity of the shop (in units per units per minute)? units per minutearrow_forwardThe ClickClock corporation produces clocks with six stations. Each station is manned by a human worker, who do the following tasks: These workers get paid $ 10 an hour. Ignore any Station Task Sequence Processing Time (secs) Task Heat-stake lens to bezel Inspect bezel Clean switch holes Install set switch in bezel Total time for A Check switch travel Clean inside bezel Install module in bezel Total time for B Install battery clip in module Heat-stake battery clip in module Install two batteries in module Check switch 14 2 26 A 3 10 Preparation 1 4 18 68 23 B 6 12 Preparation 2 7 25 60 8 20 9 20 Battery 10 22 Installation 11 8. Total time for C 70 Install band Inspect band Total time for D Cosmetic inspection Final test D 12 45 Band 13 13 Installation 58 E 14 4 Packaging 15 71 Preparation Total time for E 75 Place watch and cuff in display box Place cover in display box base 16 20 17 14 Watch 18 Place owner's manual and box into tub 30 packaging Total time for F 64arrow_forward
- While designing a process, we try to ensure that unpleasant experiences such as filling forms or taking shots are located towards the beginning/middle, primarily because: O It is usually more convenient to complete such tasks early on None of the above We do not wish to end on an unpleasant note. The memory of unpleasant experiences stays much longer relative to other kinds of experiences. O The customer may refuse to do/participate in such unpleasant tasks at the end of the processarrow_forwardThis is a step in a process that is the slowest compared tothe other steps. This step limits the capacity of the process.arrow_forwardA lab provides ultrasound service to patients. The service process consists of two steps: 1. Registration. Performed by a receptionist (Salary rate = $25/hr; Process time = 6 minutes/patient) 2. Ultrasound scan. Performed by a technician (Salary rate = $30/hr; Process time = 20 minutes/patient) Note that the ultrasound images need to be read by radiologists, but we assume that they have an ample capacity and thus will not model the role in the service process. Currently, the lab has 2 receptionists and 3 technicians. The manager anticipates demand to grow to 14 patients/hr in the near future. Thus, he plans to hire more receptionists and/or technicians to increase the service capacity to at least 14 patients/hr. What would be the extra payroll cost (in dollars per hr)?arrow_forward
- Which of the following statements best represents a concise definition of an operations process? It is a conversion activity that Select one: a. involves technical analysis b. involves workers and equipment c. transforms inputs to outputs d. produces competitive advantage for the firm Which of the following situations will tend to increase customer dissatisfaction with waiting in line the most? Select one: a. Large numbers of customers b. The physical location of an operation c. Bright lights in the banking hall d. Idle workers in the view of customersarrow_forwardWe measure, monitor and improve process cycle time because: a. It is an easy measurement to make *b. Increasing cycle time helps us improve the capacity of the process and reduce costs c. Everyone understands cycle time d. Customers are interested in how long it takes to make a product e. All of the above f. None of the abovearrow_forwardA stepper is a piece of equipment in semiconductor manufacturing. Each wafer's initial pass through the stepper requires 15 minutes. For 40 percent of wafers, they make only a single pass through the stepper. But 60 percent of wafers need to make a second pass through the stepper. The processing time on the second pass is 40 minutes. Instruction: Round your answer to 2 decimal places. How many wafers does the stepper complete per hour (wafers/hr)? per hourarrow_forward
- There is a manufacturing company that has a dedicated production line to make one specific product. The line has three stations working in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3. The output from station 3 is the finished product. Station 1 can process 500 units per week, station 2 can process 300 units per week, and station 3 can process 400 units per week. illustrates this problem. Question Answer ↓ What is the maximum output number per week?arrow_forwardClients are served in a process with two resources. The processing time of the first resource is 6 minutes. The processing time of the second resource is 6 minutes. The first resource has 9 worker and the second resource has 5 workers. The cycle time of the process is 11.8 minutes. Instruction: Round your answer to one decimal place. What is the average labor utilization (%)? percent ation CRook Airarrow_forwardYou observe a bank and notice that a customer leaves the bank about every five minutes.These five minutes between customers are:a. the capacity of the process.b. the processing time of the last resource.c. the cycle time.d. the lead timearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY