Question
Book Icon
Chapter 6, Problem 33QAP
Summary Introduction

Adequate information:

Installation cost (IC) = $645,000

Useful life of the project = 5 years

Net working capital (NWC) = $55,000

Tax rate = 21% or 0.21

Discount rate, r = 12% or 0.12

Salvage value (SV) = $50,000

To compute: The pre-tax cost saving (S)

Introduction: Cost saving refers to the benefit realized by an organization by reducing the overall spending or expenses.

Blurred answer
Students have asked these similar questions
A proposed cost-saving device has an installed cost of $730,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $140,000, the marginal tax rate is 22 percent, and the project discount rate is 10 percent. The device has an estimated Year 5 salvage value of $101,000. What level of pretax cost savings do we require for this project to be profitable? (MACRS schedule) (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) Pretax cost savings $ 216,693.04
A proposed cost-saving device has an installed cost of $905,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $65,000, the tax rate is 22 percent, and the project discount rate is 9 percent. The device has an estimated Year 5 salvage value of $125,000. What level of pretax cost savings do we require for this project to be profitable? (MACRS schedule) Note: Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16. Required cost savings
A proposed cost-saving device has an installed cost of $765,000. The device will be used in a five-year project but is classified as three-year MACRS property for tax purposes. The required initial net working capital investment is $67,000, the tax rate is 21 percent, and the project discount rate is 9 percent. The device has an estimated Year 5 salvage value of $103,000. What level of pretax cost savings do we require for this project to be profitable?

Chapter 6 Solutions

Corporate Finance

Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Text book image
Corporate Fin Focused Approach
Finance
ISBN:9781285660516
Author:EHRHARDT
Publisher:Cengage