Interpretation: Minimum number of workstations for the assembly line is to be discussed.
Concept Introduction: An assembly line is a sequence of work in which an output is produced by adding inputs to semi-finished goods that move from the work station to another work station.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An assembly line is to operate eight hours per day with a desired output of 250 units per day. The following table contains information on this product’s task times and precedence relationships:
TASK
TASK TIME (SECONDS)
IMMEDIATE PREDECESSOR
A
50
—
B
20
A
C
25
A
D
35
A
E
60
B, C
F
60
C, D
G
50
E, F
H
90
G
What is the required workstation cycle time to meet the desired output rate?
Note: Round your answer to the nearest whole number.
Balance this line using the longest task time.
Note: Leave no cells blank - be certain to enter "0" wherever required.
What is the efficiency of your line balance, assuming it is running at the cycle time determined in part b?
Note: Round your answer to 1 decimal place.
An assembly line is to operate eight hours per day with a desired output of 200 units per day. The following table contains information on this product’s task times and precedence relationships:
TASK
TASK TIME(SECONDS)
IMMEDIATEPREDECESSOR
A
60
—
B
60
A
C
50
A
D
70
A
E
30
B, C
F
110
C, D
G
70
E, F
H
70
G
b. What is the required workstation cycle time to meet the desired output rate? (Round your answer to the nearest whole number.)
c. Balance this line using the longest task time. (Leave no cells blank - be certain to enter "0" wherever required.)
d. What is the efficiency of your line balance, assuming it is running at the cycle time determined in part b? (Round your answer to 1 decimal place.)
A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product:
Without regard to projected demand, what is the maximum possible cycle time for this assembly line?
Task
Time (secs)
Immediate Predecessor
a
3
none
b
4
none
c
5
a,b
d
7
none
e
9
c,d
Chapter 6 Solutions
Practical Operations Management
Ch. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 1PCh. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Prob. 5P
Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 22PCh. 6 - Prob. 23PCh. 6 - Prob. 24PCh. 6 - Prob. 25PCh. 6 - Prob. 26PCh. 6 - Prob. 27PCh. 6 - Prob. 28PCh. 6 - Prob. 29PCh. 6 - Prob. 30PCh. 6 - Prob. 31PCh. 6 - Prob. 32PCh. 6 - Prob. 1.1QCh. 6 - Prob. 1.2QCh. 6 - Prob. 1.3QCh. 6 - Prob. 1.4QCh. 6 - Prob. 2.1QCh. 6 - Prob. 2.2QCh. 6 - Prob. 2.3QCh. 6 - Prob. 3.1QCh. 6 - Prob. 3.2QCh. 6 - Prob. 3.3Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The table below shows the time for each work element in an manual assembly process, along with the predecessor(s) required for each element. The ideal cycle time is 1.4 minutes, the repositioning time is 0.1 minutes, and there is one worker at each station. Work element A B C D E F G H I J Time (minutes) 0.7 0.4 0.2 0.3 0.5 0.4 0.6 0.5 0.3 0.2 Immediate predecessors - A A B B C E,F D,E G,H I 1. Using the ranked positional weights method, assign work elements to stations.arrow_forwardAmelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task A BCDE Time (sec) 12 14 Workstation # 1 8 5 20 Amelio's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). Immediate Predecessor A A B, C D b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line = 3 (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Tasks Assigned to Workstation Aarrow_forwardThe desired daily output for an assembly line is 360 units. This assembly line will operate 690 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TIME IMMEDIATE TASK (SECONDS) PREDECESSOR 30 55 A 50 A 55 E 35 100 G 60 E-F 45 D-G b. What is the required workstation cycle time to meet the desired output rate? Workstation cycle time seconds per unitarrow_forward
- Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 14 A C 8 A D 4 B, C E 20 D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). Part 3 b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line=3(round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to Workstation 1 A ▼…arrow_forwardMarilyn Hart, operations manager at Hart Electronics,faces assembly-line balancing problems. She has been told thatthe firm needs to complete I ,400 electronic relays per day. Thereare 420 minutes of productive time in each working day (which isequivalent to 25,200 seconds). Group the assembly-line activitiesin the following table into appropriate workstations and calculatethe efficiency of the balance.arrow_forwardManagement wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forward
- Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 15 A C 7 A D 4 B, C E 20 D Rosenberg's goal is to produce 175 PDAs per hour. a) The cycle time for the production of a PDA = nothing seconds (round your response to two decimal places). B) what's the minimum number of workstations in the assembly line? C) Can the minimum actually be reached when workstations are assigned?arrow_forwardStanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Time (sec) Immediate Predecessor A 11 − B 15 A C 7 A D 4 B, C E 20 D Rosenberg's goal is to produce 170 PDAs per hour. a) The cycle time for the production of a PDA = enter your response here seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Rosenberg can achieve in this assembly line=enter your response here (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Workstation # Tasks Assigned to…arrow_forwardAmelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task A B с D E Amelio's goal is to produce 175 PDAs per hour. a) The cycle time for the production of a PDA = Time (sec) 12 14 8 4 20 Immediate Predecessor A A B, C D seconds (round your response to two decimal places). b) The theoretical minimum number of workstations that Amelo can achieve in this assembly line fround your response up to the next whole number). = Were you able to assign all the tasks to the theoretical minimum number of workstations? c) For one to assign the tasks to the actual workstations and be able to use the theoretical minimum number, the activity assignment should be Workstation Tasks Assigned to Workstationarrow_forward
- Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly-line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line activities ace: Task Time (min) Predecessors A 3 B 6 7 A А, В B D 5 E 2 F 4 C G 5 F D,E H H 1 6 J E K 4 G, I, J 50 (e) With a 10-minute cycle time and six workstations, what is the efficiency? (1) What is the total idle time per cycle with a 10-minute cycle time and six workstations? (g) What is the best work station assignment you can make without exceeding a 10-minute cycle time and what is its efficiency?arrow_forwardA company needs to rebalance a product layout for producing sweet sour lollipop wrap. They plan to use the assembly line for an output rate of 4 units per minute each day. The following table describes the tasks involved in the production of this product: Work Element Time (seconds) Immediate Predecessor(s) A 12 -- B 6 A C 8 A D 4 B E 7 B, C F 10 E G 6 D, F Determine how many stations are required for the line to produce the desired output. Select one: A. 5.0 workstations B. 4.0 workstations C. 3.0 workstations D. 3.5 workstations E. 4.5 workstationsarrow_forwardThe theoretical maximum cycle time of a product layout is the sum of the task times.How might it be argued that this would then no longer be a product layout? Product layouts are vulnerable to disruption. What can a manager do to protect a highly efficient product layout from disruption?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY