Question
Chapter 6, Problem 1.4Q
Summary Introduction
Case Summary:
A huge contract has been given by an organization which mainly deals in electronic product to the company BT tech regarding the memory boards. To accomplish the demand of the client, BT tech has to establish a new manufacturing unit or assembly line to produce 300 products an hour. To accomplish the whole task, the organization has divided the task into 9 categories which are A1, A2, A3, B1, C1, C2, D1, D2, and E1. All the tasks will be performed as per they are
Interpretation:
Theoretical minimum number of workstationsfor BT tech’s manufacturing unit along with the conclusion derived from the design.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Given in the following table are the tasks necessary for final assembly of a hospital bed, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations. Construct a precedence diagram and balance the assembly line for a desired cycle time of 14 minutes. Draw a schematic diagram of the balanced line. How many beds can actually be assembled in an eight-hour period?
Element
Precedence
Time (min)
A
None
4
B
None
5
C
None
8
D
A
4
E
A, B
3
F
B
3
G
D, E
5
H
F
7
I
G, H
1
J
I
7
K
C, J
4
How do bottlenecks increase the work in process inventory of manufacturing plants?
Which among the types of plant layouts is best for a manufacturing company? Support your answer.
Chapter 6 Solutions
Practical Operations Management
Ch. 6 - Prob. 1DQCh. 6 - Prob. 2DQCh. 6 - Prob. 3DQCh. 6 - Prob. 4DQCh. 6 - Prob. 5DQCh. 6 - Prob. 1PCh. 6 - Prob. 2PCh. 6 - Prob. 3PCh. 6 - Prob. 4PCh. 6 - Prob. 5P
Ch. 6 - Prob. 6PCh. 6 - Prob. 7PCh. 6 - Prob. 8PCh. 6 - Prob. 9PCh. 6 - Prob. 10PCh. 6 - Prob. 11PCh. 6 - Prob. 12PCh. 6 - Prob. 13PCh. 6 - Prob. 14PCh. 6 - Prob. 15PCh. 6 - Prob. 16PCh. 6 - Prob. 17PCh. 6 - Prob. 18PCh. 6 - Prob. 19PCh. 6 - Prob. 20PCh. 6 - Prob. 21PCh. 6 - Prob. 22PCh. 6 - Prob. 23PCh. 6 - Prob. 24PCh. 6 - Prob. 25PCh. 6 - Prob. 26PCh. 6 - Prob. 27PCh. 6 - Prob. 28PCh. 6 - Prob. 29PCh. 6 - Prob. 30PCh. 6 - Prob. 31PCh. 6 - Prob. 32PCh. 6 - Prob. 1.1QCh. 6 - Prob. 1.2QCh. 6 - Prob. 1.3QCh. 6 - Prob. 1.4QCh. 6 - Prob. 2.1QCh. 6 - Prob. 2.2QCh. 6 - Prob. 2.3QCh. 6 - Prob. 3.1QCh. 6 - Prob. 3.2QCh. 6 - Prob. 3.3Q
Knowledge Booster
Similar questions
- How can facility layout design help in improving productivity and reducing production lead time?arrow_forwardGiven in the following table are the tasks necessary forfinal assembly of a hospital bed, the length of time needed to perform each task, and the operations that must be com-pleted prior to subsequent operations. Construct a prece-dence diagram and balance the assembly line for a desired cycle time of 14 minutes. Draw a schematic diagram of thebalanced line. How many beds can actually be assembledin an eight-hour period?arrow_forwardManagement wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forward
- Trinity Valley Furniture Warehouse has purchased a retail outlet with six departments, as shown below. The anticipated number of customers that move between departments each week is given in the load summary chart. Each department is 30 ft x 30 ft. Present Layout A В C D E F Proposed Layout Distance, feet Present Layout Load Distance, feet From/To А — В А - F В -Е С - В D - C E - A Е -F F - B # Customers Load * Distance Load * Distance 70 50 100 70 80 40 30 60 F- E 100 Total a) Determine the total distance travelled by customers through the retail outlet on a weekly basis according to the present layout. b) Re-arrange the six departments such that the weekly total customer movement (distance) is minimized. c) Evaluate each of your proposed layouts. d) Even if you might be analyzing several possible layouts, choose only one of them based on their evaluations; i.e., which of them has the minimum Load * Distance. Draw a diagram of your proposed layout. Present the results of your…arrow_forwardIdentify the store layout of your chosen retail business. Do you think the store layout helps the business to achieve its retail objectives? Explain and justify your answer.arrow_forwardIn manufacturing layout design, the key concern is the resulting efi ciency of the operation. In retail service operations, what is the primary concern or objective?arrow_forward
- RSports is a major retailer of sportswear and equipment in Singapore. It has just signed a lease with a major shopping mall to be one of the anchor tenants and will occupy a floor area of 7,000 square meter (sqm). According to the regulatory requirement, 2% of the floor area must be set aside for emergency assembly purpose. The store layout has 8 major zones, and the company analyst has provided the information (based on other stores’ past data) in Figure 1.1 which shows the annual profit contribution for each zone per sqm.Based on the corporate guidelines, each sports zone requires at least 600sqm of floor space, and none of the sports zone should occupy more than 15% of usable floor space. The Cycling, Home gym, and Fitness sports zones keep some items in inventory (such as bicycles, treadmills, weights) and an equivalent space of 10 to 20% of the floor space allocated to these three sports zones must be set aside for stocking the spares. Administrative office and checkout counters…arrow_forwardEach process type and layout type has advantages and limitations that should be clearly understood when making process selection and layout decisions.arrow_forwardExplain the term traditional assembly line operations? how are these operations efficient?arrow_forward
- The Build-Em-Fast Company has agreed to supply its best customer with three widgets during each of the next 3 weeks, even though producing them will require some overtime work. The relevant production data are as follows: Week Maximum Production, Regular Time Maximum Production, Overtime Production Cost per Unit, Regular Time 1 2 2 $300 2 3 2 $500 3 1 2 $400 The cost per unit produced with overtime for each week is $100 more than for regular time. The cost of storage is $50 per unit for each week it is stored. There is already an inventory of two widgets on hand currently, but the company does not want to retain any widgets in inventory after the 3 weeks. Management wants to know how many units should be produced in each week to minimize the total cost of meeting the delivery schedule. Formulate this problem as a transportation problem by constructing the appropriate parameter table.arrow_forwardThe following assembly tasks (with performance time in minutes and task precedence) are to be configured into a balanced assembly line layout. There are 12 separate assembly elements (A-L) to complete the product. Note: The target is to produce 6 units per hour (60 min). please select more than 5 workstations in this problem as per the guidelines of the lecture note. Element (Min) Preceded Bv A B C D E F G H 1 J K L Time 2.5 4.5 3.5 4.0 3.2 2.0 2.7 7.0 6.0 3.8 5.0 4.3 A A A B B. C D D ΤΑ E F, G H I. J. K a) Construct the precedence diagram b) Determine the total work content time. c) Use the "Longest Task Time" rule to assign work elements to stations (also known as "Largest Candidate Method". d) Calculate the efficiency of your solution.arrow_forwardGordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A BU A с D Workpieces moved per week between work areas are: A A B с D B 4 B 900 с 10 5 800 400 D 8 D 600 300 700 It costs Gordon $1 to move 1 work piece 1 foot. The weekly total material handling cost of the layout = $ (enter your response as a whole number).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.