Concept explainers
(a)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project
(a)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(b)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(b)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(c)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(c)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(d)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(d)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
There is no value for
Hence, the probability that the project is completed within
Want to see more full solutions like this?
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersarrow_forwardProject B is the development of a facility in a remote area, of about GHS 5 million in value, of approximately 18 months’ planned duration. It is 30 per cent completed. Earned Value analysis shows that the project is not achieving its planned cost or progress targets. The project is also not achieving quality requirements. Some of the specialized components used for this project are only obtainable from overseas suppliers and are difficult to transport over the rough terrain near the project site. There has been a delay on ordering these components. The transportation of these components, which must be booked several months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the requisite set of skills to install them. There are also several other risks associated with this project, including a quite basic business case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks and the potential for…arrow_forwardExercise regular time acceleration time Normal Cost acceleration cost Precedents A 4 3 900 1000 --- B. 8 6 300 400 --- C 4 3 500 650 --- D 6 4 900 1200 A AND 7 4 1000 1600 C a. The duration of the project in normal time and without acceleration is Response days . b. The minimum cost to accelerate the project in 2 days is Response .arrow_forward
- Your firm MS MACKAY LTD. won a contract of €1,785,000 to construct a 161kV/33kV sub-station. You have been selected as the project manager to lead the project team for the successful execution of the project. You are the project manager, there are a total of 8,400 hours of work schedule on the project. You made your checks with the accounting department, and they told you that you have spent a total of €1,144,000. According to the schedule, your team should have worked 5000 hours, but your foreman says that the team was allowed to work some overtime, and they have actually put in 5600 hours of work. (i) Write the scope of the project (ii) Provide the WBS for the project.arrow_forwardUse the following project status information to calculate each of the requested EVM numbers below (a-i).The project status is reported at the end of week 13. Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 Weeks 100 percent complete $5,000B $8,500 3 Weeks 100 percent complete $9,000C $15,000 4 Weeks 75 percent complete $14,000D $10,000 4 Weeks 50 percent complete $9,000 E $12,000 4 Weeks Not startedF $15,000 5 Weeks Not started a. Planned Valuedb. Actual costc. Cost varianced. Schedule variancee. Cost performance indexf. Schedule performance indexg. Budget at completionh. Estimation to completei. Estimation at completionarrow_forwardJustify the usage of earned value management (EVM) to control costs and monitor project success, and hypothesize on why it is not utilized more often. What are some broad guidelines for determining if a cost variation, a schedule variance, a cost performance index, or a schedule performance index is positive or negative?arrow_forward
- You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?arrow_forwardIn order to promote the College of Engineering, IT and Environment, the college asks you to organize an information session to the prospective students and parents (which can be considered as a project). The project is expected to be completed within 3 weeks and this event should be held in CDU Casuarina campus. The project budget is AUD 3,000.00. Answer the following questions (you can make assumptions in answering the questions). Question 1 a) Identify the potential risks and the corresponding responses (identify at least 2 risks). b) Identify the risk response types.arrow_forwardGeneral Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing? TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSORS NORMAL CRASH NORMAL CRASH A — 2 1 22,000 23,000 B — 3 1 30,000 34,000 C A 2 1 26,000 27,000 D B 3 2 48,000 49,000 E C 4 2 56,000 58,000 F C 3 2 30,000 30,500 G D, E 5 2 80,000 83,000 H F, G 2 1 16,000 19,000arrow_forward
- given the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.pv =$ 23,000ev = 20,000ac= 25,000bac = 130,000a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project?B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?C. use the CPI to calculate the estimate at completion EAC for this project.d. use the SPI to estimate how long it will take to finish this project.e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2arrow_forwardBased on the case below, answer the following questions:The duration for the project is two year. Recall that PV is the planned value, EV is theearned value, AC is the actual cost, and BAC is the budget at completion.PV = 38,000EV = 40,000AC = 36,000BAC = 220,000(a) What is the Cost Variance (CV), Schedule Variance (SV), Cost Performance Index(CPI), and Schedule Performance Index (SPI) for the project?arrow_forwardplease help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.