EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 18, Problem 14PA

(a)

Summary Introduction

Interpretation: The probability that the project is completed within 33weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(a)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 33weeks deadline.

  z=33321.69=11.3=0.769

Refer probability distribution table.

For z0.769 .

  P(z0.769)=0.77935 .

Hence, the probability that the project is completed within 33weeks is 0.77935 .

(b)

Summary Introduction

Interpretation: The probability that the project is completed within 30weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(b)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 30weeks deadline.

  z=30321.69=21.3=1.539

Refer probability distribution table.

For z1.539 .

  P(z1.539)=0.06178 .

Hence, the probability that the project is completed within 30weeks is 0.06178 .

(c)

Summary Introduction

Interpretation: The probability that the project is completed within 35weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(c)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 35weeks deadline.

  z=35321.69=31.3=2.308

Refer probability distribution table.

For z2.308 .

  P(z2.308)=0.99134 .

Hence, the probability that the project is completed within 35weeks is 0.99134 .

(d)

Summary Introduction

Interpretation: The probability that the project is completed within 32weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(d)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 32weeks deadline.

  z=32321.69=01.3=0

Refer probability distribution table.

There is no value for z=0 .

Hence, the probability that the project is completed within 32weeks cannot be determined.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
please help, project management. I need part D,Eand 2  1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited…
The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on Jan 01 2022, and be completed in time for the finals of the 2024 season. A penalty clause of $250,000 per week of delay beyond October 1st, 2024 is written into the contract. George Earnings, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they succeed, the prospects of future projects are bright since there is a projected renaissance in building classic ballparks with modern luxury boxes. ID Activity Duration Predecessor(s)   1 Baseball Stadium       2 Clear stadium site 70 days           —   3 Demolish building 30 days           2   4 Set up construction site 70 days           3   5 Drive support piling 120 days           4   6 Pour lower concrete bowl 120 days           5   7 Pour main concourse 120 days           6   8…
Project B is the development of a facility in a remote area, of about GHS 5 million in value, of approximately 18 months’ planned duration. It is 30 per cent completed. Earned Value analysis shows that the project is not achieving its planned cost or progress targets. The project is also not achieving quality requirements. Some of the specialized components used for this project are only oSbtainable from overseas suppliers and are difficult to transport over the rough terrain near the project site. There has been a delay on ordering these components. The transportation of these components, which must be booked several months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the requisite set of skills to install them. There are also several other risks associated with this project, including a quite basic business case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks and the potential for…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY