EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 18, Problem 13PA
Summary Introduction
Interpretation: The total project completion time is to be calculated along with the lowest cost solution if the project is to be completed
Concept Introduction:
Project
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You are the Project Analyst for Nairobi Project Advisors who have been asked by a client to advise on which of the following two projects should be accepted. Each project costs US$ 10,000 and each entails a 12% cost of capital:
Year
Expected Net Cash flows
Project X
Project Y
0
($ 10,000)
($ 10,000)
1
6,500
3,500
2
3,000
3,500
3
3,000
3,500
4
1,000
3,500
a) Advise on which project should be undertaken using the Pay Back Period (PBP), Net Present Value (NPV), Internal Rate of Return (IRR), and Modified Internal Rate of Return (MIRR) assuming:
i. The projects are independent
ii. The projects are mutually exclusive
As an IT Project Manager what are two issues or project challenges unique to the IT industry that may affect the management of a vaccine rollout project.
Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table attached as an image.
Determine the minimum cost-schedule for this project to be completed in 18 weeks.
Assume a linear relationship between crash cost and crash time. For example, crash cost per week for activity A can be calculated as: ($650 - $200)/(4-2) = $225.
2. What is the difference in total project costs between the earliest completion time of the project using normal times and the minimum cost-schedule you found in part 1?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- In making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? Group of answer choices: - the LS of the following activity plus the activity time of T - the smallest EF for the three activities that are immediate predecessors for activity T - the LF of the following activity minus the activity time of T - the LS of the following activity minus the activity time of T - the largest EF for the three activities that are immediate predecessors for activity Tarrow_forwardWorld Vision International-Ghana has secured a 50 million Ghana Cedis from the Mastercard Foundation for a 3-year youth employment project. The project seeks to develop the capacity of Ghanaian Youth aged (15-24) years in entrepreneurial skills to enable them access capital and set up their own businesses. The youth entrepreneurial development and employment initiative covers various sectors like construction, agriculture, agro-processing, manufacturing, services among others. The first phase of the project which is the pilot is expected to cover some selected Ghanaian youth in Accra, Kumasi, Koforidua, Ho, Takoradi, Sunyani, and Tamale. Prior to approval of the project, Care International Ghana Project Management Unit devoted sometime to conduct a literature review in order to understand the current economic wellbeing of Ghanaian youth in terms employment and income levels among others. These were followed by needs assessment studies on current employment need of the Ghanaian youth.…arrow_forwardThe chart below shows the initial investment and expected yearly payback for Project A and Project B Project A Project B Initial Investment $ 300,000 $ 450,000 Expected Yearly PayBack $ 45,000 $ 90,000 For Project A, There has been a change in the expected yearly payback. Years 1 and 2 – you are expecting $45,000 each year. For the next three years, you are expecting $70,000 each year. What would be the average ROI for this alternative?arrow_forward
- The ABC Manufacturing Company has set up a weighted scoring matrix for evaluating some potential projects. Following are five projects under consideration. Using the scoring matrix below which project would you rate highest? Lowest? If the weight for “Sponsor Support” is changed from 2.0 to 5.0, will the project selection change? What are the three highest-weighted project scores with this new weight? Why is it important that the weights mirror critical strategic factors? Project Screening Matrix Criteria Weight Project 1 Project 2 Project 3 Project 4 Project 5 Sponsor Support 2 9 3 6 1 3 Strategic Alliance 5 5 7 8 0 10 Urgency 4 2 2 2 5 10 Fills a market gap 3 0 0 3 10 1 Sales 3 2 5 6 6 8 Competition 1 5 1 8 9 0arrow_forwardThe North Carolina Department of Transportation is undertaking a construction project to widen a large section of interstate highway near Charlotte, NC, which includes the construction of a number of new bridges, interchanges, and overpasses. The first step in the project is the appointment of a project manager and the development of a project team, some of which will be departmental employees and others will be private consultants and operatives. The team of a project of this size also requires a large support staff with varying technical skills. Once the team is selected and the staff is in place the first task is to select a primary contractor to manage and oversee the actual construction. The following table gives the standard activities required for the planning and scheduling of this process. Activity Description Predecessor Time (weeks) Optimistic a Most Likely m Pessimistic b a b c d e f g h i j k L M Select project manager Develop a team recruitment…arrow_forwardRare Agri-Products Ltd. is considering a new project with a projected life of seven (7) years. The project falls under the government’s subsidy program for encouraging local agricultural products and is eligible for a one-time rebate of 25% on any initial equipment installed for the project. The initial equipment (IE) will cost $41,000,000. An additional equipment (AE) costing $3,500,000 will be needed at the end of year 3. At the end of seven (7) years, the original equipment, IE, will have no resale value but the supplementary equipment, AE, can be sold for $50,000. A working capital of $1,350,000 will be needed. The project is forecast to generate sales of agri-products over the seven years as follows: Year 1 70,000 units Year 2 100,000 units Years 3-5 250,000 units Years 6-7 325,000 units A sale price of $150 per unit for the first two years is expected and then decline to $90 per unit thereafter as the newness of the product loses some sheen. The variable expenses will amount to…arrow_forward
- P & B Energy Systems Limited (P & B), a wholly owned Zambian company proposes to construct two solar photovoltaic power plants in Lusaka and Serenje Districts (one plant in each district) to address the power shortages being experienced as a result of low water levels at Kariba Dam and Kafue Gorge. The project is estimated to cost One hundred Million United States Dollars (US$40,000,000.00) and is projected to be completed in one year. P & B proposes to embark on the project in June 2023. You are the Project Manager for New Concepts Consultants who have been contracted by the P & B to undertake the detailed design and construction supervision of the project. 1. As the Project Managers, you have two options for the procurement of contractors to construct the power plants, namely, Open Open Bidding Bidding and Negotiations. Which method would you recommend to the P & B and why? Outline the procedure you would follow, for the recommended procurement method, to arrive at contract award.arrow_forwardA new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 2 4 6 A, B A, B 5 6 7 D 7 9 10 E B 2 4 6 F 1 2 3 G D 5 8. 10 H D, F 6. 8. 10 I E, G, H 3 4 5 a) What is the…arrow_forwardA new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6. в 4 6 А, В A, B 5 6 7 D 7 9 10 E в 2 4 6 F 1 2 3 G D 5 8 10 H D, F 6 8 10 I E, G, H 3 4 5 a) What is the…arrow_forward
- A new motorway project is being planned in Ireland, with its construction expected to cost €1 billion. The 100km route will connect Ireland's second largest city, Cork, with the city of Limerick. The intended alignment for the motorway runs alongside the existing N20, which runs through Blarney, Mallow and Charleville. The new motorway forms part of the Project Ireland 2040 programme of infrastructure works. The first step in the project is to appoint a project manager and develop a project team. Once the team is selected and the staff is in place, the next task is to select a primary contractor to manage and oversee the construction. The following activities, their immediate predecessors, as well as the activity time estimates (in days) are standard for the planning and scheduling of this project: Activity Immediate predecessor Optimistic Most probable Pessimistic A 3 5 6 B 4 6 А, В А, В 5 6 7 D 7 9 10 E B 4 6 F 1 2 G 5 8 10 H D, F 8 10 I E, G, H 3 4 5 a) What are the critical…arrow_forwardThe Peabody Coal Corporation recently completed the final feasibility report for a new general ledger accounting system. It has hired a consulting firm to program and install the new system. The consulting firm is charging $350,000 for the remaining tasks to be performed. These tasks are to be performed over the next 10 months as detailed in the Gantt chart in the diagram. The consulting firm is extremely concerned with the project staying on schedule because it is receiving a flat fee. The release of the final payment is contingent upon the system performing as stated in the contract and upon Peabody receiving appropriate documentation of the system.Requireda. Prepare a PERT diagram and indicate the critical path.b. What happens to the time frame of the implementation of the project if the manufacturer is 4 weeks late shipping the hardware?c. What happens if the data conversion does not go smoothly and takes an additional 3 weeks? d. Who should conduct the postimplementation review?…arrow_forwardConstruct the project network for this project and determine the following: d) Expected project duration and variance e) The probability that the mill will be fined $300,000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY