Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 29P

The bill of materials and the data from the inventory records for product A are shown in Figure 11.47. Assume that the MPS start quantities for A are 50 units in weeks 1, 2, and 3, and 150 units in weeks 6 and 8. Derive an MRP plan for the components going into product A using the data in Table 11.17.

Chapter 11, Problem 29P, The bill of materials and the data from the inventory records for product A are shown in Figure

Blurred answer
Students have asked these similar questions
The bill of materials and the data from the inventory records for product A are shown in the figure to the right. Assume that the MPS start quantities for A are 70 units in weeks 1, 2, and 7. Derive an MRP plan for the components going into product A using the data in the table below. Item D Data Category Lot-sizing rule Lead time Scheduled receipts Beginning inventory Complete the material requirements plan. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: C Item: D L4L 1 week None 155 с Gross requirements Scheduled receipts Projected on-hand inventory 155 Planned receipts Planned order releases Item: E L4L 2 weeks 70 (week 2) 230 Gross requirements Scheduled receipts Projected on-hand inventory 230 Planned receipts Planned order releases Gross requirements Scheduled receipts Projected on-hand inventory Planned receipts Planned order releases 160 1 10 10 0 0 1 0 0 0 10 1 0 ܘ ܘ ܘ E FOQ = 200 2 weeks None 160 2 0 0 0 0 NOOOO 2 70 0 ON 2…
Figure 1 shows the BOM for product A. Table 1 shows the MPS quantity start dates for product A, and Table 2 contains data from inventory records for items B, C, and D. The production planner wants to determine the material requirements plan for items B, C, and D for the next 8 weeks. What is the planned receipts quantity for item D for week 6? C (3) D (2) 8 (1) D (2) C2) Figure 1. BOM for product A Table 1. MPS quantity start dates for product A Week Product 1 3 70 4. 6. 7. 8. 80 100 70 100 Table 2. Inventory record data Item Data category Lot-sizing rule Lead time Scheduled receipts Beginning inventory Safety stock LAL 2 weeks 100 (week 3) FOQ= 500 1 week 150 (week 1) POQ (P-4) 1 week 500 (week 1) 600 100 200 None 130
Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.

Chapter 11 Solutions

Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)

Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY