Textbook Question
Book Icon
Chapter 11, Problem 7P

The forecasted requirements for an electric hand drill for the next 6 weeks are 15, 40, 10, 20, 50, and 30 units. The marketing department has booked orders totaling 20, 25, 10, and 20 units for delivery in the first (current), second, third, and fourth weeks. Currently, 30 hand drills are in stock. The policy is to order in lots of 60 units. Lead time is 1 week.

  1. Develop the MPS record for the hand drills.
  2. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order?

Blurred answer
Students have asked these similar questions
On Week a) Item: P24 hand 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 45 Customer Orders 13 8 4 PAB 20 Available to Promise MPS b) Determine if each customer order will be accepted. Order Amount Week Accept (Y/N) 1 40 2 30 3 4 30 25 462M 3 Update the MPS time-phased record for accepted orders. Item: P24 Forecast Customer Orders Problem 3: The MPS planner at Murphy Motors uses MPS time-phased records for planning end-item production. The planner is currently working on a schedule for the P24, one of Murphy's top-selling motors. The planner uses a production lot size of 70 and a safety stock of 5 for the P24 motor. a) Complete the MPS time-phased record for product P24. Use the table on the left. b) Determine if Murphy Motors can accept each of the following customer orders. Update the MPS time- phased record for accepted orders. Order 1234 Amount 40 Desired Week 4 30 30 25 623 8 4 On Week hand 1 2 3 4 5 6 30 30 30 40 40 40 74 45 45 PAB 20 Available to Promise MPS On hand = 20
3. The MPS planner at Murphy Motors uses MPS time-phased records for planning end-item pro- duction. The planner is currently working on a schedule for the P24, one of Murphy's top-selling motors. The planner uses a production lot size of 70 and a safety stock of 5 for the P24 motor. Week On hand 30 30 30 1 2 3 4 5 6 7 8 40 40 40 45 45 13 8 4 Item: P24 Forecast Orders Projected available balance 20 Available-to-promise MPS a. Complete the MPS time-phased record for product P24. b. Can Murphy accept the following orders? Update the MPS time-phased record for accepted orders. Amount 40 Order Desired Week 1 4 2 6 3 30 2 4 25 3 30 4882 7623
PROBLEM-3) The Sales&Operations (S&OP) process is designed to produce a plan that all departmentswithin the organization, as well as suppliers to the organization, can work. The process is also sometimes referred toas sales, inventory, and operations planning (SIOP) to emphasize the important role that inventory can play as abuffer between sales planning and operations planning. The S&OP department of the XYZ company, that producesKLM products, estimates the sales over the next six years in thousands of packages will be as follows: Assume that each worker stays on the job for at least one year and XYZ currently has eight workers. XYZ estimatesthat they will have 600000 packages on hand at the end of the current year. Assume that, on average, eachworker is paid TL 60000 per year and is responsible for producing 80000 packages. Inventory costs have beenestimated to be 20 KRS per package per year, and shortages are not allowed. XYZ estimates that it costs TL 2500for each…

Chapter 11 Solutions

Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)

Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY