Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 5P

Tabard Industries forecasted the following demand for one of its most profitable products for the next 8 weeks: 120, 120, 120, 100, 100, 100, 80, and 80 units. The booked customer orders for this product, starting in week 1 are: 100, 80, 60, 40, 10, 10, 0, and 0 units. The current on-hand inventory is 150 units, the order quantity is 200 units, and the lead time is 1 week.

  1. Develop a MPS for this product.
  2. The marketing department revised its forecast. Starting with week 1, the new forecasts are: 120, 120, 120, 150, 150, 150, 100, and 100 units. Assuming that the prospective MPS you developed in part (a) does not change, prepare a revised MPS record. Comment on the situation that Tabard now faces.
  3. Returning to the original forecasted demand level and the MPS record you developed in part (a), assume that marketing accepted a new customer order for 200 units in week 2, and thereby booked orders in week 2 is now 280 units. Assuming that the prospective MPS you developed in part (a) does not change, prepare a revised MPS record. Comment on the situation that Tabard now faces.

Blurred answer
Students have asked these similar questions
A forecast of 240 units in January, 320 units in February, and 240 units in March has been approved for the seismic-sensory product family manufactured at the Rockport facility of Maryland Automated, Inc. Three products, A, B, and C, comprise this family. The product mix ratio for products A, B, and C for the past 2 years has been 35 percent, 40 percent,and 25 percent, respectively. Management believes that the monthly forecast requirements are evenly spread over the 4 weeks of each month. Currently, 10 units of product C are on hand. The company produces product C in lots of 40, and the lead time is 2 weeks. A production quantity of 40 units from the previous period is scheduled to arrive in week 1. Thecompany has accepted orders of 25, 12, 8, 10, 2, and 3 units of product C in weeks 1 through 6, respectively. Prepare a prospective MPS for product C and calculate the availableto-promise inventory quantities.
minco inc is a small manufaturer of fused magnesia and silica. Minco's continuous improvement efforts led to a capacity and production planning software. to prepare for the use of software, a spreadsheet was first used to determine the capacity requirements for the main equipment (the fusion furnances) and the production schedule for the main products. A major product had the following forecast and committed orders (all in thousand dollars):                                      January                                              Feburary Week 2 3 4 1 2 3 4   Forecast 56 56 56 66 66 66 66   Committed order 44 0 18           The initial inventory was 119,000 pounds and the minimum stock at the end week was to be 83,000 pounds. Calculate the economic production quantity (EPQ) if the annual demand is 3,000,000 pounds, setup cost is $350 per setup, inventory holding cost rate is 20 percent per year, unit cost is $2 per pound, demand rate is 500 pounds per hour, and production…
Eight Glasses A Day:   The EGAD Bottling Company has decided to introduce a new line of premium bottled water that will include several designer flavors. Marketing manager Georgianna is predicting an upturn in demand based on the new offerings and the increased public awareness of the health benefits of drinking more water. She has prepared aggregate forecasts for the next six months, as shown, Month May June July Aug Sep Oct Total Forecast 50 60 70 90 80 70 420   Production manager Mark Mercer, has developed the following information. (Note: Costs are in thousands of dollars). Regular production cost: $1 per tankload Regular production capacity: 60 tankloads Overtime production cost: $1.6 per tankload Subcontracting cost: $1.8 per tankload Holding cost: $2 per tankload per month Back ordering cost: $5 per month per tankload Beginning inventory: 0 units   Among the strategies being considered are: 1. Level production supplemented by up to 10 tank loads a month from overtime 2. A…

Chapter 11 Solutions

Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)

Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...

Additional Business Textbook Solutions

Find more solutions based on key concepts
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY