Question
Chapter 11, Problem 3P
Summary Introduction
Interpretation: Creating Master production
Concept Introduction: Master production schedule (MPS) is a plan for production of each commodity in each time period. It can be viewed in manufacturing sector upon which plan indicates a demand of the product along with its time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An end item’s demand forecasts for the next 10 weeks are 30,20, 35, 50, 25, 25, 0, 40, 0, and 50 units. The current on-handinventory is 80 units. The order policy is to produce in lots of100. The booked customer orders for the item, starting withweek 1, are 22, 30, 15, 9, 0, 0, 5, 3, 7, and 0 units. At present,no MPS quantities are on-hand for this item. The lead time is2 weeks. Develop an MPS for this end item.
An end item’s demand forecasts for the next 10 weeks are 30, 30, 30, 30, 20, 20, 30, 30, 30, and 30 units. The current onhand inventory is 100 units. The order policy is to produce in lots of 75. The booked customer orders for the item, starting with week 1, are 15, 38, 7, 5, 0, 3, 10, 0, 0, and 0 units. The lead time is 2 weeks.a. Develop an MPS for this end item.b. The marketing department has received five orders for this item in the following sequence:Order 1 is for 20 units to be delivered in period 1Order 2 is for 75 units to be delivered in period 4Order 3 is for 90 units to be delivered in period 6Order 4 is for 75 units to be delivered in period 7Order 5 is for 90 units to be delivered in period 10Assuming that the prospective MPS you developed in part (a) does not change, which orders would you be able to accept based on the available to promise (ATP)?
Musa's Cashmere Sweaters has authorized the following MPS for her exclusive line of cashmere sweaters. She wants to use the MPS record for promising future orders. Current order promises are included. The MPS order quantity is 60 units. Beginning Inventory is 0. Complete the following MPS record.
Period
1
2
3
4
5
6
7
8
9
10
11
12
Forecast
15
15
15
15
20
20
20
20
25
25
25
25
Customer orders
12
10
8
25
40
0
15
30
30
0
0
40
Projected available
Available-to-promise
MPS
60
Chapter 11 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Electro Fans has j ust received an order for one thousand 20-inch fans d ue week 7. Each fan consists of a housing assembly, two grill s, a fan assembly, and an electrical unit.The housing assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub and five blades. The electrical unit consists of a motor, a switch, and a knob.The following ta ble gives lead times, on-hand inventory, and scheduled receipts.a) Construct a product structure.b) Construct a time-phased product structure.c) Prepare a net material requirements plan.arrow_forward3. The MPS planner at Murphy Motors uses MPS time-phased records for planning end-item pro- duction. The planner is currently working on a schedule for the P24, one of Murphy's top-selling motors. The planner uses a production lot size of 70 and a safety stock of 5 for the P24 motor. Item: P24 Forecast Orders On hand Week 12345678 30 30 30 40 40 40 45 45 13 8 4 Projected available balance Available-to-promise MPS 20 a. Complete the MPS time-phased record for product P24. b. Can Murphy accept the following orders? Update the MPS time-phased record for accepted orders. Order 1234 4 Amount 40 30 30 25 Desired Week 4 6 2 3arrow_forwardGiven the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for period 4? Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- 3. The MPS planner at Murphy Motors uses MPS time-phased records for planning end-item pro- duction. The planner is currently working on a schedule for the P24, one of Murphy's top-selling motors. The planner uses a production lot size of 70 and a safety stock of 5 for the P24 motor. Week On hand 30 30 30 1 2 3 4 5 6 7 8 40 40 40 45 45 13 8 4 Item: P24 Forecast Orders Projected available balance 20 Available-to-promise MPS a. Complete the MPS time-phased record for product P24. b. Can Murphy accept the following orders? Update the MPS time-phased record for accepted orders. Amount 40 Order Desired Week 1 4 2 6 3 30 2 4 25 3 30 4882 7623arrow_forwarda. Given the following master schedule, fill in the projected available and availableto promise rows: b. A customer wants an order of 100 in period 4. What can you tell him?c. The customer from part (b) cancels his request, but then says he wants 120 in period 5.What do you tell him now?d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs fora sales promotion. What do you tell them and why?e. What action (if any) should be taken in period 11? Why is it okay to take theaction?arrow_forwardFor the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? For the Axle table above, what are the Gross Requirements in the week of 9/7? For the Axle table above, what are the Gross Requirements in the week of 9/14? For the Axle table above, what are the Planned Order Releases in the week of 8/17?arrow_forward
- Suppose we are formulating a Master Production Schedule (MPS) for an item. The lot-size policy for this item calls for a fixed quantity of 300 units. Lead time for this item is three weeks. Week O inventory for this item is 400 units. There are no safety stock requirements. Here are the demand forecast and the booked orders for this item.... Week 1 2 3 4 5 6 Forecast 120 120 100 100 100 120 Booked 115 121 71 0 0 0 When the master schedule is complete. what will be the Projected On-Hand in Week 4?arrow_forwardTuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 110. The projected demand, lot size, and time standards are shown in the following table: i Item Demand forecast Lot size Standard processing time Standard setup time Touring 4,000 units/year 130 units 0.20 hour/unit 2 hours/lot Mountain 10,000 units/year 110 units 0.50 hour/unit 3 hours/lot The shop currently works 8 hours a day, 5 days a week, 48 weeks a year. It operates five workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing the firm's current capacity cushion? The number of workstations required next year is. (Enter your response rounded up to the next whole number.)arrow_forwardFigure shows a partially completed MPS record for 2 inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?Order Amount (Units) Week Requested1 15 22 30 53 25 34 75 7arrow_forward
- 14.26. Calculate the available-to-promise row in the following matrix: Period On Hand = 100 1 2 3 4 5 6 Forecast 50 100 50 100 50 100 Customer Orders 50 125 75 175 45 15 Master Production 200 200 Schedule Available-to-Promisearrow_forward. Case: Flamingo Educational Services Flamingo Educational Services, a company located in the Tema metropolis, is a nationwide market leader in the publishing and distribution of textbooks for first and second cycle schools. Somehow, Flamingo does not use forecasts for production planning. Instead, the operations manager decides which books to produce and the batch size, based on orders and the amounts in inventory. The books that have the fewest amounts in inventory get the highest priority. Demand is uneven, and the company has experienced being overstocked on some items and out of others. Being under-stocked has occasionally created tensions with managers of the retail bookstores the company works with. Flamingo is on the verge of losing a lucrative contract with the Ghana Education Service over a complaint that the books produced over the last four months have defective binding as well as slight but noticeable variations in print quality and sizes of the…arrow_forwardFigure below shows a partially completed MPS record for ball bearings.a. Develop the MPS for ball bearings.b. Four customer orders arrived in the following sequence:Order Quantity Week Desired1 500 42 400 53 300 14 300 7Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,