Textbook Question
Chapter 11, Problem 25P
Figure 11.44 shows the BOMs for two products, A and B. Table 11.12 shows the MPS quantity start date for each one. Table 11.13 contains data from inventory records for items C, D, and E. There are no safety stock requirements for any of the items.
- Determine the material requirements plan for items C, D, and E for the next 8 weeks.
- What specific managerial actions are required in week 1?
- Suppose that a very important customer places an emergency order for a quantity of product A. TO satisfy this order, a new MPS of 200 units of product A is now required in week 5. Determine the changes to the material requirements plan if this order is accepted and note any problems that you detect.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
. Consider the bill of materials (BOM) in Figure 11.33.a. How many immediate parents (one level above) doesitem I have? How many immediate parents does item Ehave?b. How many unique components does product A have at alllevels?c. Which of the components are purchased items?d. How many intermediate items does product A have at alllevels?e. Given the lead times (LT) in weeks noted on Figure 11.33,how far in advance of shipment must a purchasecommitment be for any of the purchased items identifiedin part (c)?
Figure shows the BOMs for two products, A and B. Table 1 shows the MPS quantity start date for each one. Table 2 contains data from inventory records for items C, D, and E. There are no safety stock requirements for any of the items.a. Determine the material requirements plan for items C, D, and E for the next 8 weeks.b. What specific managerial actions are required in week 1?c. Suppose that a very important customer places an emergency order for a quantity of product A. To satisfy this order, a new MPS of 200 units of product A is now required in week 5. Determine the changes to the material requirements plan if this order is accepted and note any problems that you detect.
MPS Quantity Start Dates
Date
Product
1
2
3
4
5
6
7
8
A
125
95
150
130
B
80
70
Inventory Record Data
Item
Data Category
C
D
E
Lot-sizing rule
L4L
POQ 1P = 32
FOQ = 800
Lead time
3 weeks
2 weeks
1 weeks
Scheduled receipts
200 (week 2)
None
800 (week 1)
Beginning…
Assume you are the manager of a shop that assembles power tools. You have just received an order for 55
chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows:
Item Lead Time (weeks) On Hand
Saw
A
B
C
D
E
F
2
1
2
2
1
1
2
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned order receipt
Planned order release
Ĉ
E(3) & E(2) LT = 1 week
Lot size: Lot-for-Lot
15
10
5
65
20
10
30
Skip Extension Tip: Double click to open in new tab
Show Transcribed Text
Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no
cells blank - be certain to enter "0" wherever required.)
Components
A(2), B(1), C(4)
E(3), D(1)
D (2), F(3)
E(2), D (2)
Beg. Inv.
1
2
3
190
5
210
6
Chapter 11 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 11 - Consider the master flight schedule of a major...Ch. 11 - For an organization of your choice, such as where...Ch. 11 - Consider a service provider that is in the...Ch. 11 - Complete the MPS record in Figure 11.29 for a...Ch. 11 - Complete the MPS record in Figure 11.30 for a...Ch. 11 - Prob. 3PCh. 11 - Figure 11.31 shows a partially completed MPS...Ch. 11 - Tabard Industries forecasted the following demand...Ch. 11 - Figure 11.32 shows a partially completed MPS...Ch. 11 - The forecasted requirements for an electric hand...
Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The table given below shows a partially completed MPS record for product A. What is the remaining ATP inventory (discrete) for week 7 after the company receives a 20 units of customer order for week 6? Order policy: 60 units Lead time: 1 week Item: A Quantity on hand: 30 Week 3 30 7. 34 11 4. Forecast requirements Customer orders (booked) Projected on-hand inventory MPS quantity MPS start ATP inventory 22 24 18 27 36 28 26 12 24 O a 59 Ob. 29 OcO Od. 49 Oe. 39arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 9. Subscripts indicate quantity required for each parent. Assumelot-for-lot ordering. c) Develop a net material requirements plan for F (enter your responses as whole numbers). Week Lead Time Item 2 3 4 5 6 7 8 9 (weeks) F Gross req Insert answer insert answer 2 On hand insert answer insert answer Net req insert answer insert answer Order receipt insert answer insert answer Order release insert answer insert answerarrow_forwardShown below is a partially completed MPS record for hand drills. a. Develop the MPS record for the hand drills. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Hand drills Quantity on Hand: 30 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start 1 15 20 N 40 25 3 15 15 Week Available-to- promise (ATP) inventory b. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order? The order should ship on week (Enter your response as an integer.) 4 20 20 Order Policy: 60 units Lead Time: 1 week 5 55 0 6 35 0arrow_forward
- Shown below is a partially completed MPS record for ball bearings. Part 2 a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity on Hand: 400 Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 350 350 450 250 300 250 350 400 350 Customer orders (booked) 300 350 250 300 150 150 150 150 100 50 Projected on-hand inventory enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here MPS quantity 500 enter your response here enter your response here enter your response here enter your…arrow_forwardA factory has just received an order for 100 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Item Lead Time (weeks) On Hand Inventory Scheduled receipts Order Policy Direct Components End item 2 30 lot for lot A(4), B(3), C(2) A 3 20 54 at week 3 lot for lot D(2) B 2 10 68 at week 4 lot for lot D(5) C 1 100 multiple of 60 D 1 20 min. of 500 Develop the material requirements plan (please print out an empty MRP table to work with), and determine what the "projected available balance" is for component D at week 8. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardWhat are the net requirements of each item in the MPS? Item Net Requirements X A B C D E F Garrow_forward
- A) Completely fill in the Transportation table including the Production Plan. B) Create a Summary Table of the plan (including ending inventories). C) Calculate the cost of the Production Plan.arrow_forwardWhat is the lead time (in weeks) to respond to a customerorder for product A, based on the BOM shown in Figure 11.34,assuming no existing inventories or scheduled receipts?arrow_forwardWhat is the net requirement using a Material Requirements Planning program if the gross requirement is 1,250 and the inventory on hand is 50?arrow_forward
- Refer to this product tree If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed?arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forwardTable B shows a partially completed MPS record for ball Develop the MPS for ball Four customer orders arrived in the following sequences (Table B). Table A Order Quantity Week desired 1 500 4 2 400 5 3 300 1 4 300 7 Assume that you must commit to the orders in the sequence of arrival and cannot change the desired shipping dates or your MPS. Which orders should you accept? Table B Item: Ball bearings Quantity on hand: 400 Order policy: 500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 400 450 300 350 200 300 450 400 Customer order booked 300 350 250 250 200 150 100 100 100 100 Projected on-hand inventory MPS quantity 500 MPS start Available to promise (ATP)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.