OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9780077835439
Author: Roger G Schroeder, M. Johnny Rungtusanatham, Susan Meyer Goldstein
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 6, Problem 6P

A furniture factory makes two types of wooden tables, large and small. See the flowchart below.

  Setup Time, Minutes Run Time per Piece, Minutes Capacity, Pieces per Hour
Wood cutting 30 5 15
Male four legs 60 10 10
Male tops 60 12 8
Finish the wood 20 8 12
Assemble and ship 20 17 14

Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart.

  1. a. What is the capacity of the system, and what is the bottleneck?
  2. b. What are the throughput times for batches of large and small tables?
  3. c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The capacity of the process.

Introduction:

Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.

Explanation of Solution

Given information:

A furniture factory makes large and small wooden tables. The given information is tabulated below:

Setup time (Minutes) Run time per piece (Minutes) Capacity (Pieces per hour)
Wood cutting 30 5 15
Make four legs 60 10 10
Make tops 60 12 8
Finish the wood 20 8 12
Assemble and ship 20 17 14

Small wooden tables are finished in batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.

Determine the capacity:

As both large wooden table and small wooden table have same capacities, the capacity of the system is minimum of the capacity of the resources. The minimum capacity resource is 8 tables per hour and the process is making tops.

Setup time (Minutes) Run time per piece (Minutes) Capacity (Pieces per hour)
Wood cutting 30 5 15
Make four legs 60 10 10
Make tops 60 12 8
Finish the wood 20 8 12
Assemble and ship 20 17 14

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The average throughput time.

Introduction:

Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.

Explanation of Solution

Given information:

A furniture factory makes large and small wooden tables. The given information is tabulated below:

Setup time (Minutes) Run time per piece (Minutes) Capacity (Pieces per hour)
Wood cutting 30 5 15
Make four legs 60 10 10
Make tops 60 12 8
Finish the wood 20 8 12
Assemble and ship 20 17 14

Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.

Determine the average throughput time:

Small tables Large tables
Batch size 100 50
Wood cutting 530 280
Make four legs 1,060 560
Make tops 1,260 660
Finish the wood 820 420
Assemble and ship 1,720 870
Total time 4,330 2,230

Hence, the average throughput time for small tables is 4,330 minutes and the average throughput time for large tables is 2,230 minutes.

Working note:

Wood cutting for small tables:

It is calculated by adding the setup time to the multiplied value of run time and batch size.

Wood cutting for small tables=Setup time+(Run time×Batch size)=30+(5×100)=30+500=530

Wood cutting for large tables:

It is calculated by adding the setup time to the multiplied value of run time and batch size.

Wood cutting for small tables=Setup time+(Run time×Batch size)=30+(5×50)=30+250=280

Note: The calculation is carried out for all the processes.

Compute the throughput time for small tables:

While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.

Throughput time=530+1,260+820+1,720=4,330

Compute the throughput time for large tables:

While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.

Throughput time=280+660+420+870=2,230

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The number of tables in the system.

Introduction:

Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.

Explanation of Solution

Given information:

A furniture factory makes large and small wooden tables. The given information is tabulated below:

Setup time (Minutes) Run time per piece (Minutes) Capacity (Pieces per hour)
Wood cutting 30 5 15
Make four legs 60 10 10
Make tops 60 12 8
Finish the wood 20 8 12
Assemble and ship 20 17 14

Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time. The factory is producing at the rate of six small tables per hour.

Formula to determine the average number of tables in the system:

I=T×R

Here

I refers to the number of orders in the systems.

T refers to the average throughout time.

R refers to the average flow rate in the process.

Determine the average number of tables in the system:

It calculated by multiplying the average throughput time with the average flow rate in the process.

I=T×R=(4,33060)×6=72.167×6=433 tables

Hence, the average number of tables in the system is 433 tables.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to   use my forecast numbers to generate a Master Production Schedule (MPS)  I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022  April 2023  I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.
Solve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.
Help with question?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY