Concept explainers
A furniture factory makes two types of wooden tables, large and small. See the flowchart below.
Setup Time, Minutes | Run Time per Piece, Minutes | Capacity, Pieces per Hour | |
Wood cutting | 30 | 5 | 15 |
Male four legs | 60 | 10 | 10 |
Male tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart.
- a. What is the capacity of the system, and what is the bottleneck?
- b. What are the throughput times for batches of large and small tables?
- c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?
a)
To determine: The capacity of the process.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.
Determine the capacity:
As both large wooden table and small wooden table have same capacities, the capacity of the system is minimum of the capacity of the resources. The minimum capacity resource is 8 tables per hour and the process is making tops.
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
b)
To determine: The average throughput time.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time.
Determine the average throughput time:
Small tables | Large tables | |
Batch size | 100 | 50 |
Wood cutting | 530 | 280 |
Make four legs | 1,060 | 560 |
Make tops | 1,260 | 660 |
Finish the wood | 820 | 420 |
Assemble and ship | 1,720 | 870 |
Total time | 4,330 | 2,230 |
Hence, the average throughput time for small tables is 4,330 minutes and the average throughput time for large tables is 2,230 minutes.
Working note:
Wood cutting for small tables:
It is calculated by adding the setup time to the multiplied value of run time and batch size.
Wood cutting for large tables:
It is calculated by adding the setup time to the multiplied value of run time and batch size.
Note: The calculation is carried out for all the processes.
Compute the throughput time for small tables:
While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.
Compute the throughput time for large tables:
While adding the time taken, the maximum amount should be chosen from the process of making four legs and tops, as they can be done in parallel.
c)
To determine: The number of tables in the system.
Introduction:
Flow rate is the number of flow units through a business procedure per unit time. Flow rate refers to the number of customers who will be served per hour or the parts produced per minute.
Explanation of Solution
Given information:
A furniture factory makes large and small wooden tables. The given information is tabulated below:
Setup time (Minutes) | Run time per piece (Minutes) | Capacity (Pieces per hour) | |
Wood cutting | 30 | 5 | 15 |
Make four legs | 60 | 10 | 10 |
Make tops | 60 | 12 | 8 |
Finish the wood | 20 | 8 | 12 |
Assemble and ship | 20 | 17 | 14 |
Small wooden tables are finished in the batches of 100 and large wooden tables are finished in the batches of 50. A batch includes fixed setup time and run time. Both small tables and large tables have the same processing time. The factory is producing at the rate of six small tables per hour.
Formula to determine the average number of tables in the system:
Here
I refers to the number of orders in the systems.
T refers to the average throughout time.
R refers to the average flow rate in the process.
Determine the average number of tables in the system:
It calculated by multiplying the average throughput time with the average flow rate in the process.
Hence, the average number of tables in the system is 433 tables.
Want to see more full solutions like this?
Chapter 6 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- Judy’s Cake Shop makes fresh cakes to customer orders. After receiving the order by Judy’s assistant, which takes 2 minutes, Judy then takes 8 minutes tomix the ingredients for the cake and loads a cake pan for baking. Then the cake is put into the oven for 30 minutes. The oven can hold three cakes at one time. When the cake is taken out of the oven, it is cooled for 1 hour. The assistant then takes 2 minutes to pack the cake for pickup and bills the customer, which takes 3 minutes.a. What is the capacity of the process, and what is the bottleneck?b. What is the throughput time for a typical cake?c. If on average five orders are taken per hour, how many cakes are there in the process (on average)?arrow_forward. Aquatica makes underwater camera housings for divers. The process begins with a solid rectangular block of aluminum that is used to make a single housing. A computer numerically controlled (CNC) machine drills into the block to make the metal “frame” of the housing. Each block requires 15 minutes of drilling. The frame is then chemically treated in a series of baths. There is ample capacity in the treating stage. Finally, a worker must manually attach the various buttons and components to the metal housing. This assembly takes 120 minutes per housing per worker and Aquatica has 6 workers trained to do this task. The CNC machine requires a 30-minute setup time before the production of a batch can begin. a. If the CNC machine produces 14 housings between setups, what would be its capacity (in housings per hour)? b. Assuming the process is supply-constrained, what is the utilization (as a number between 0 and 1) of the CNC machine if it operates in batches of 14 housings? c. Assuming…arrow_forwardA production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 6 units/hr Sawing 2.5 units/hr Sanding Drilling 1.8 units/hr Welding 7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hr Assembly 0.7 units/hrarrow_forward
- Amy Xia's p lant was designed to produce 7,000 hammers per day but is limited to making 6,000 hammers per day because of the time needed to change equipment betweenstyles of hammers. What is the utilization?arrow_forward. Kinga Doll Company manufactures eight versions of its popular girl doll, Shari. Thecompany operates on a 40-hour workweek. The eight versions differ in doll skin, hair,and eye color, enabling most children to have a doll with a similar appearance to them.It currently sells an average of 4000 dolls (spread equally among its eight versions) perweek to boutique toy retailers. In simplified terms, doll making at Kinga involves threebasic operations: molding the body and hair, painting the face, and dressing the doll.Changing over between versions requires setup time at the molding and painting stationsdue to the different colors of plastic pellets, hair, and eye color paint required. Table 7.5lists the setup times for a batch and the activity times for each unit at each step.a. What is the process capacity in dolls per hour with a batch size of 500 dolls? b. What is the utilization of molding in dolls per hour with a batch size of 800 dolls? c. Which batch size would minimize inventory…arrow_forwardRecall "Tommy's Dresses to go" case. Three years after, this company still rents designer dresses to customers, but it has managed to streamline its internal processes and expand to different segments of demand. Now, customers can rent clothes for anywhere between 1 days to 30 days, and each customer is sent only one (1) dress (instead of 2 dresses described in the case). The company alsó takes only 13 number of days to turn around a dress (i.e., this the duration starting with return from a customer, to again being rented out to a customer). The current demand is an average of 1,000 customers per day, and the company owns total of 30 thousand dresses. What is the average rental duration? (i.e., what is the average number of days, a customer keeps a dress).arrow_forward
- Jason Carter works for a producer of soaps that come inpackages of 6 each. His job is to fi ll the packages with soap, andhe is expected to process 30 packages an hour. Th e facility whereJason works uses a kanban production system in which eachcontainer holds 5 packages of soap. It takes 20 minutes to receivethe packages he needs from the previous workstation. How manykanbans are needed for the fi lling process?arrow_forwardDeja Brew, Inc., produces and sells 1,000 pallets of tea. Selling price per pallet: $700 Variable cost per pallet: $100 Annual fixed costs: $20,000 How many units would Deja Brew, Inc., need to sell to make $10,000? Round to the nearest whole pallet.arrow_forwardPurple Swift manufactures birdhouses in lots of 10. Each birdhouse takes 30 minutes to paint. After 10 birdhouses are painted, the company switches paint color which requires a one hour changeover. Assume that the company should changeover at the very beginning of the process. The company works 8 hours per shift, one shift per day, 225 days per year. Currently the company has one point booth. What is Purple Swift's paint capacity cushion if it builds 2,000 birdhouses per year? Purple Swift's paint capacity cushion is%. (Enter your response rounded to one decimal place.) ew an example Get more help. MacBook Pro Clear all Check answerarrow_forward
- C&A Furniture uses a four-step process to make its famous wood table: Processing Time Process Milling Table top Milling Table stand Assembly Finishing The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands. If the batch size is 10, what is the capacity of the process in tables per minute? A) 0.077 B) 0.05 C) 0.067 10 5 15 20 D) 0.048arrow_forwardYost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated and assembled at four different processing stations (W, X, Y, Z). The operation is a batch process with small setup times that can be considered negligible. The product information (price, weekly demand, and processing times) and process sequences are shown in Figure. Raw materials and purchased parts (shown as a per-unit consumption rate) are represented by inverted triangles. YPI is able to make and sell up to the limit of its demand per week with no penalties incurred for not meeting the full demand. Each workstation is staffed by one highly skilled worker who is dedicated to work on that workstation alone and is paid $15 per hour. The plant operates one 8-hour shift per day and operates on a 5-day work week (i.e., 40 hours of production per person per week). Overhead costs are $9,000/week. Which of the four workstations, W, X, Y, or Z, has the highest aggregate workload, and thus…arrow_forwardNew Mode Y Delay A Yost-Perry Industries (YPI) manufactures a mix of affordable guitars (A, B, C) that are fabricated and assembled at four different processing stations (W, X, Y, Z). The operation is a batch process with small setup times that can be considered negligible. The product information (price, weekly demand, and processing times) and process sequences are shown below. Purchased parts and raw materials (shown as a per-unit consumption rate) are represented by inverted triangles. YPI is able to make and sell up to the limit of its demand per week with no penalties incurred for not meeting the full demand. Each workstation is staffed by one highly skilled worker who is dedicated to work on that workstation alone and is paid $15 per hour. The plant operates one 8-hour shift per day and operates on a 5-day work week (i.e., 40 hours of production per person per week). Overhead costs are $9,000/week. Q Q Product A $11 Q Step 1 Station W (12 min) Step 2 Station Z (13 min) Purchased…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,