Question
Chapter 4.4, Problem 9P
a
Summary Introduction
To determine:
Annual cost of transportation, loading and unloading cost when shipping of truck is done per week, when shipping is done if truck is fully loaded and when shipping is done if 3 trucks are loaded.
Introduction:
Transportation cost is the cost incurred when goods are transported from one place to another.
Loading and unloading cost is incurred when goods are carried in and out of the transport.
b
Summary Introduction
To determine:
Reason for favoring policy with highest annual cost than with the lowest cost of transportation.
Introduction:
Optimal situation of a firm arises when cost of production and transportation is minimized or profit is maximized.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
ABC Corporation recently decided to switch to just-in-time (JIT) inventory system. At the beginning of this switch, the firm has 40 units of product in inventory. The firm has 2,500 labor hours available in the first month of this switch. These hours could produce 700 units of the product. Customer demand for this month is 500 units. If JIT principles are correctly followed, how many units should the firm produce in the first month of the switch?
a. 40
b. 740
c. 500
d. 460
e. 660
f. 200
Flemming Accessories produces paper slicers used in offices and in art stores. The minislicer has been one of its most popular items: Annual demand is 6,750 units and is constant throughout the year. Kristen Flemming, owner of the firm, produces the minislicers in batches. On average, Kristen can manufacture 125 minislicers per day. Demand for these slicers during the production process is 30 per day. The setup cost for the equipment necessary to produce the minislicers is $150. Carrying costs are $1 per minislicer per year. How many minislicers should Kristen manufacture in each batch?
In a large microelectronics plant, the assembly cell for circuitboards has a demand for 200 units an hour. Two feeder cellssupply parts A and B to the assembly cell (one A and one Bfor each board). Standard containers that look like dividedtrays are used. A container will hold 20 As or 10 Bs. It takes10 minutes to fill up a container with As and 20 minutes tofill up a container with Bs. Transit time to the assembly cell is5 minutes for both A and B. No safety factor is used. Set up akanban control system for the assembly process.
Chapter 4 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 4.4 - Prob. 1PCh. 4.4 - Prob. 2PCh. 4.4 - Prob. 3PCh. 4.4 - Prob. 4PCh. 4.4 - Prob. 5PCh. 4.4 - Prob. 6PCh. 4.4 - Prob. 7PCh. 4.4 - Prob. 8PCh. 4.4 - Prob. 9PCh. 4.5 - Prob. 10P
Ch. 4.5 - Prob. 11PCh. 4.5 - Prob. 12PCh. 4.5 - Prob. 13PCh. 4.5 - Prob. 14PCh. 4.5 - Prob. 15PCh. 4.5 - Prob. 16PCh. 4.6 - Prob. 17PCh. 4.6 - Prob. 18PCh. 4.6 - Prob. 19PCh. 4.6 - Prob. 20PCh. 4.7 - Prob. 21PCh. 4.7 - Prob. 22PCh. 4.7 - Prob. 23PCh. 4.7 - Prob. 24PCh. 4.7 - Prob. 25PCh. 4.8 - Prob. 26PCh. 4.8 - Prob. 27PCh. 4.8 - Prob. 28PCh. 4.9 - Prob. 29PCh. 4.9 - Prob. 30PCh. 4 - Prob. 31APCh. 4 - Prob. 32APCh. 4 - Prob. 33APCh. 4 - Prob. 34APCh. 4 - Prob. 35APCh. 4 - Prob. 36APCh. 4 - Prob. 37APCh. 4 - Prob. 38APCh. 4 - Prob. 39APCh. 4 - Prob. 40APCh. 4 - Prob. 41APCh. 4 - Prob. 42APCh. 4 - Prob. 43APCh. 4 - Prob. 44APCh. 4 - Prob. 45AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Jack Ltd is a market leader in the manufacture of apple juice. They operate a reorder level system of inventory management, and the following information is available for green apples: Average usage 800 per dayMinimum usage 540 per dayMaximum usage 1260 per dayLead time for replenishment 16 - 20 per day Reorder quantity 19,500 apples a. Calculate the reorder level 1. Calculate the maximum level of inventory 2. Calculate the minimum (buffer) inventory levelarrow_forwardA service garage uses 204 boxes of cleaning cloths a year. The boxes cost $12 each. The cost to place one order is $15, and the cost to hold one box in inventory for a year is $2.40. The EOQ isarrow_forwardThe ROP is an important input in determining the EOQ. True Falsearrow_forward
- A company processes feathers and ships them loose in a covered truck. The linehaul cost for an average shipment is $600, and the truck carries 2000 pounds offeathers. A bright new graduate has just been hired and has suggested that theyshould bale the feathers into 500-pound bales. This would make them easier tohandle and also allow them to be compressed into about one-tenth of the space theynow occupy. How many pounds of feathers can the truck now carry? What is thepresent line haul cost per pound? What will it be if the proposal is adopted?arrow_forwardMerlita works for a local ceramics company. She just completed her accountancy degree and learned the EOQ model in one of her subjects. She suggested to her employer to adopt it. The company sells 20,000 pieces of specialty ceramic items each year. Traditionally, they have produced these items four times a year, making 5,000 pieces at a time. They carry no safety stock as customers do not mind waiting for orders. The average piece of ceramic items costs P400 to make and costs the company P20 to carry in inventory for a year. The set up costs for each production run total P80. The company should a. Continue the existing system due to P38,950 advantage. b. Adopt EOQ due to savings of P35,675. c. Adopt EOQ due to savings of P42,320. d. Continue the existing system due to P41,820 advantage.arrow_forwardThere are 500 wood pallets for the transportation of the final product cases. Each pallet has a cost of$88. If the pallet holds 329 cases each, what will be unit cost?arrow_forward
- The Ostrya Virginiana furniture company produces wooden chairs. The demand for chairs is 500 units per month. The setup cost for production is $300, and the holding cost is $12 per chair per year. The production rate is 100 chairs per day. Assume 30 working days per month. Determine the following: a) D, S, H, p, u b) EPQ c) Run timearrow_forwardZilong’s EOQ for Material A is 500 units. This EOQ is based on: Annual demand 5,000 units Ordering costs P12.50 What is the annual carrying cost per unit for Material Aarrow_forwardWalmart experiences a demand of 5 units per day for its LED TVs. The lead time for re-stocking LED TVs is 10 days. What is the Re-Order Point? (Assume that the demand and lead time are known with certainty, that is, they are not uncertain) 50 units 2 units 50 days 2 daysarrow_forward
- In the EOQ model, always the minimum inventory equals zero. True Falsearrow_forwardDETERMINING THE NUMBER OF KANBAN CONTAINERS Hobbs Bakery produces short runs of cakes that are shipped to grocery stores. The owner, Ken Hobbs,wants to try to reduce inventory by changing to a kanban system. He has developed the following dataand asked you to finish the project.Production lead time = Wait time + Material handling time + Processing time = 2 daysDaily demand = 500 cakesSafety stock = 12 dayContainer size (determined on a production order size EOQ basis) = 250 cakesarrow_forwardThe daily demand for printer paper at the School of Business is approximately normal with a mean of 15.2 boxes and a standard deviation of 1.6 per day. The Administrative Assistant reviews the inventory every 30 days, and the lead time is 5 days. The division set a policy of satisfying 96% of the demand for paper. If there are 125 boxes of printer paper in inventory at the beginning of this review period, how many boxes of printer paper should be ordered? What is the variance of demand during the review period plus the lead-time period? What is the standard deviation of demand during the review period plus the lead-time period? A. Variance = 76.80 Standard deviation = 8.76 B. Variance = 89.60 Standard deviation = 9.47 C. Variance = 9.47 Standard deviation = 89.60 D. Variance = 12.8 Standard deviation = 3.58arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.