eXcel The BOM for product A given below
Part | on Hand | Week of land Time |
A | 75 | 1 |
B | 150 | 2 |
C | 50 | 1 |
D | 100 | 2 |
Assume the master
- a. Develop a materials plan for this product.
- b. What actions should be taken immediately?
- c. Project the inventory ahead for each part.
- d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the bill of materials (BOM) in Figure 11.33.a. How many immediate parents (one level above) does item I have? How many immediate parents does item E have?b. How many unique components does product A have at all levels?c. Which of the components are purchased items?d. How many intermediate items does product A have at all levels?e. Given the lead times (LT) in weeks noted on Figure 11.33, how far in advance of shipment must a purchase commitment be for any of the purchased items identified in part (c)?
a. Write the product structure diagram as an indented bill-of-materials list.
Note:-
Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
Answer completely.
14.) A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure 14. From the information shown, generate:
a) An indented bell of material for product A.
b) Net requirements for each part to produce 10 As in week 8 using lot-for-lot.
Figure 14:
Chapter 15 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Product M is made of two units of N and two of P. N is made of two units of R and four units of S. Ris made of one unit of S and three units of T. P is made of two units of T and four units of U. a. Show the bill-of-materials (product structure tree). b. If 100 Ms are required, how many units of each component are needed? c. Show both a single-level parts list and an indented parts list.arrow_forwardGiven the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.arrow_forwardThe BOM for product A is given below:Assume the master schedule calls for 200 units of product A in week 5 and 250 units in week 6. a. Develop a materials plan for this product. b. What actions should be taken immediately? c. Project the inventory ahead for each part. d. If you were suddenly notified that part D will take three weeks to get instead of two weeks, what actions would you take?arrow_forward
- Product A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day to assemble, subassemblies take two days and compo-nents take three days. When should an order be re-leased for C3 if the 100 A’s are needed by day 7?arrow_forwardProduct A is assembled from two units of S1 and threeunits of S2. S1 is made of one unit of C1, four units of C2,and one unit of C3. S2 is made of three units of C2 and twounits of C3.a. Draw a product structure diagram for product A.b. How many C3’s are needed to fill an order for 100 A’s?c. Assume no inventory on hand, products take one day toassemble, subassemblies take two days and components take three days. When should an order be released for C3 if the 100 A’s are needed by day 7?arrow_forwardThe gross requirements for item A are specified for the beginning of weeks 1 through 12 in the table that follows. Item A, Level 0 01 02 03 04 05 06 07 08 09 10 11 12 0 60 0 50 0 70 0 40 0 60 0 50 60 ? ? ? ? ? ? ? ? ? ? ? ???????????? Gross requirements. Projected on hand Planned order release The lead time is 2 weeks. The current on hand inventory, at the beginning of week 1 is 60 units. If the order cost is $80 per order and the inventory cost is $1 per unit per period, and the order quantity is the computed part period (or a multiple of the computed part period) when it is necessary to place an order, what is the total cost for the 12 week period? Answer:arrow_forward
- The BOM for product A is shown in Figure 11.45. The MPS forproduct A calls for 120 units to be started in weeks 2, 4, 5, and8. Table 11.14 shows data from the inventory records.a. Develop the material requirements plan for the next8 weeks for each item.b. What specific managerial actions are required in week 1?Make sure you address any specific difficulties youencounter in the inventory records.arrow_forwardA part structure, lead time (weeks), and on-handquantities for product A are shown in Figure 14. 14. From theinformation shown, generate:a) An indented bill of material fo r product A b) Net requirements for each part to produce I0 As in week 8using lot-for-lot. IParrow_forwarda) Given the product structure and master production scheduleshown in Figure 14.12, develop a gross requirements plan forall items.b) G iven the product structure, master production schedule, andinven tory status shown in Figure 14.12, develop a net requirementsplan (planned order release) for all items.arrow_forward
- a. One hundred twenty units of end item Z are needed at the beginning of week 7. Prepare a material requirements plan for component C. Take into account that on hand there are 40 units of Z,70 units of A, 100 units of B, and 30 units of C. Also, there is a scheduled receipt of 20 units ofcomponent C in week 4. Lead times are two weeks for Z and B, and one week for the other components. Lot-for-lot ordering will be used for all items b. Ninety-five units of end item E are needed at the beginning of week 7. Prepare a material requirements plan for component D. Take into account that 5 units of E are currently on hand, as well as50 units of B, 100 units of C, and 80 units of D. Also, 30 units of C have been outsourced and areexpected to arrive in week 4. Lead times are two weeks for E and C, and one week for the othercomponents. Assume lot-for-lot ordering except for D, where multiples of 40 must be used.arrow_forwardWhat will be projected on hand inventory of item S in week6?arrow_forwardAssignment: Bill of Materials (BOM) How many units will be needed from B, C, D, E, F, and G if we want to produce 50 units of product A. Product (A) Level A Ci3) 1 Bi2) Ep) Fa Ej2) D12) 3 Di2) 2.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY