A firm makes a basic scissors consisting of three parts: the left side, the right side, and the screw that holds the sides together. At the present time, the firm has the following numbers of parts on hand and on order. The lead times for reorder of each part are also shown along with a BOM and a sketch of the scissors.
0 | On Hand | Weeks of Lead Time | Scheduled Receipts |
Scissors | 100 | 1 | |
Left side | 50 | 2 | 100 in week 2 |
Right side | 75 | 2 | 200 in week 2 |
Screw | 300 | 1 | 200 in week 1 |
- a. Assume the master
schedule calls for 200 scissors to be shipped in week 4 and 500 in week 5: work out a complete materials plan. - b. Suppose the supplier of right-hand sides calls to say that deliveries of the 200 parts on order will be one week late. What effect will this have on the materials plan?
- c. If demand for scissors is uncertain and has a standard deviation of 50 units, what would you recommend the firm do to maintain a 95 percent service level for scissors?
- d. If the delivery of the scissors parts is unreliable and the standard deviation of delivery' lead time is one week for each of the parts, what would you recommend the firm do to maintain its production schedule?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider the following information.
PART X
Gross Requirements
Scheduled Receipts
Projected On-Hand Inventory 100
Q = 60, LT= 3 weeks, Safety Stock = 5
1
70
70
PART X
Gross Requirements
Scheduled Receipts
Projected On-Hand Inventory 100
Planned Order Releases
1
70
70
100
2
0
>
X
WEEK
3
40
Compute the planned order releases and projected on-hand inventory for component part X. Round your answers to the nearest whole number. If your
answer is zero, enter "0".
2
0
4
0
100
WEEK
3
40
5
160
60
4
0
40
0
X
5
160
Check My Work
-60
0
Shown below is a partially completed MPS record for ball bearings.
a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being
not applicable.)
Item: Ball bearings
Quantity
on Hand: 400
Forecast
Customer
orders (booked)
Projected on-hand
inventory
MPS quantity
MPS start
1
550
300
350
500
2
250
350
0
0
3
450
250
50
500
4
450
200
100
500
Order Policy: 500 units
Lead Time: 1 week
Week
5
250
150
350
500
6
400
100
450
500
7
200
50
250
0
8
250
100
To o
9
450
50
50
10
450
150
100
500 500
This question is based on the following information pertaining to material Pogi: Usage 50 – 100 lbs. per day Lead time 8 – 12 days Size of the order 600 lbs. No. of days in a year 340 What is the average stock level?
A. 1,250 B. 1,200 C. 1,000 D. 9252. What is the maximum stock level?
2,500
2,000
1,400
1,2003. What is the minimum stock level?
450
800
850
1,000 4. What is the re-order level?
1,200
1,600
1,750
1,800
Chapter 15 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Complete the master production schedule based on the following information On-hand Inventory - 160 schedule production whenever projected on-hand inventory drops below - 30 MPS lot size - 300 Week 1 2 3 4 5 6 7 8Forecast 120 100 130 110 140 140 170 180 Customer Orders 110 100 75 50 32 11 5 0Projected On-Hand Inventory 160MPSAvailable-to-Promisearrow_forwardBhatti Company produces plastic photo frames. Two departments, molding and finishing, are involved in the manufacturing. The molding department fills the molds with hot liquid plastic that is left to cool and then opens them. The finishing department removes the plastic frame from the mold and strips the edges of the frames of extra plastic. The following information is available for the month of January: January 1 Quantity (pounds) January 31 Quantity (pounds) Work-in-Process Inventory Cost Cost Molding department Finishing department None None 5,000 $ 15,000 2,000 The WIP Inventory in the finishing department is estimated to be 40% complete for conversion both at the beginning and end of January. Costs of production for January follow: Direct Costs of Production Materials Conversion Molding department Finishing department $ 450,000 $ 90,000 80,290 The molding department started 50,000 pounds of product in January. The firm uses the FIFO method of process costing. Required: 1. Prepare…arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 4,500 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 8,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 3,500 Week 1 2 3 Gross requirements 4,500 1,000…arrow_forward
- Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 100 units Lead Time: 1 week January February Quantity on Hand: 80 Week 1 2 3 4 5 6 7 8 Forecast 65 70 65 45 50 45 45 55 Customer orders (booked) 40 10 90 0 35 75 0 0 Projected on-hand inventory nothing nothing nothing nothing nothing nothing nothing nothing MPS quantity nothing nothing nothing nothing nothing nothing nothing nothing MPS start nothing nothing nothing nothing nothing nothing nothing nothingarrow_forwardAssume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forwardThe annual demand of ABC Inc. sole product totaled 450,000 units. Due to uncertainty in supply of items, the maximum possible lead time for the orders is 2 weeks and 1 day. A safety stock of 6,250 units is determined. What is the normal lead time? (Use 360 days) Choices: 1 week and 5 days 1 week 9 days 10 daysarrow_forward
- 1. Decorative door (DD) consists of a wooden door (WD) and a handle (H). The wooden door consists of an isolation filling (IS) and three wooden plates (WP). Currently 30 handles and 100 wooden doors are on inventory. Final assembly takes 1 week. The handle has a lead time of 3 weeks. All other parts of decorative door have 1-week lead times. There are no scheduled receipts. All components use the lot-for-lot technique. The master schedule requires 80 units of decorative door in week 5 and 120 in week 8. Produce the MRP for the upcoming 8 weeks. a) Draw the bill of materials b) Produce the MRP for the upcoming eight weeks c) Produce a list of all planned order releasesarrow_forwardidentified order processing time risk and purpose solution using Plan-Do-Check-Act cycle.arrow_forwardK- Product A is made from components B, D, and E. Item B is a subassembly that requires 2 units of C and 3 units of D. Item E also is an intermediate item, made from F. All other usage quantities are 1. Choose the correct BOM for product A COA OC (B11) 00 (0 (1)) om E()) G COC FU OB. OD 00 Bib (D) 60 10 (011) C (20) 819 FIT)arrow_forward
- Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: 1 week Quantity on Hand: 40 Week 1 4 5 6 7 8 Forecast 20 18 28 28 21 33 36 41 Customer orders 17 19 7 11 11 (booked) Projected on-hand inventory MPS quantity LO 3.arrow_forwardConsider the following information. PART X Gross Requirements Scheduled Receipts Projected On-Hand Inventory 130 Q-60, LT-3 weeks, Safety Stock - 20 Compute the planned order releases and projected on-hand inventory for component part X. Round your answers to the nearest whole number. If your answer is zero, enter "0". PART X Gross Requirements Scheduled Receipts Projected On-Hand Inventory 130 Planned Order Releases 1 50 50 1 50 130 0 2 0 WEEK 3 70 99 2 0 130 120 ®® 4 0 WEEK 3 70 30 0 5 130 x 4 0 30 5 130 20 0arrow_forwardComplete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Quantity on Hand: 80 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 1 70 40 ☐☐ January 2 70 65 80 Order Policy: 100 units Lead Time: 1 week February Week 4 40 0 5 45 35 50 70 45 0 8 50 0arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY