Textbook Question
Book Icon
Chapter 15, Problem 6P

A firm makes a basic scissors consisting of three parts: the left side, the right side, and the screw that holds the sides together. At the present time, the firm has the following numbers of parts on hand and on order. The lead times for reorder of each part are also shown along with a BOM and a sketch of the scissors.

Chapter 15, Problem 6P, A firm makes a basic scissors consisting of three parts: the left side, the right side, and the

0 On Hand Weeks of Lead Time Scheduled Receipts
Scissors 100 1  
Left side 50 2 100 in week 2
Right side 75 2 200 in week 2
Screw 300 1 200 in week 1
  1. a. Assume the master schedule calls for 200 scissors to be shipped in week 4 and 500 in week 5: work out a complete materials plan.
  2. b. Suppose the supplier of right-hand sides calls to say that deliveries of the 200 parts on order will be one week late. What effect will this have on the materials plan?
  3. c. If demand for scissors is uncertain and has a standard deviation of 50 units, what would you recommend the firm do to maintain a 95 percent service level for scissors?
  4. d. If the delivery of the scissors parts is unreliable and the standard deviation of delivery' lead time is one week for each of the parts, what would you recommend the firm do to maintain its production schedule?
Blurred answer
Students have asked these similar questions
Consider the following information. PART X Gross Requirements Scheduled Receipts Projected On-Hand Inventory 100 Q = 60, LT= 3 weeks, Safety Stock = 5 1 70 70 PART X Gross Requirements Scheduled Receipts Projected On-Hand Inventory 100 Planned Order Releases 1 70 70 100 2 0 > X WEEK 3 40 Compute the planned order releases and projected on-hand inventory for component part X. Round your answers to the nearest whole number. If your answer is zero, enter "0". 2 0 4 0 100 WEEK 3 40 5 160 60 4 0 40 0 X 5 160 Check My Work -60 0
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Quantity on Hand: 400 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start 1 550 300 350 500 2 250 350 0 0 3 450 250 50 500 4 450 200 100 500 Order Policy: 500 units Lead Time: 1 week Week 5 250 150 350 500 6 400 100 450 500 7 200 50 250 0 8 250 100 To o 9 450 50 50 10 450 150 100 500 500
This question is based on the following information pertaining to material Pogi: Usage 50 – 100 lbs. per day Lead time 8 – 12 days Size of the order 600 lbs. No. of days in a year 340 What is the average stock level?              A. 1,250             B. 1,200             C. 1,000             D. 9252. What is the maximum stock level?        2,500        2,000        1,400        1,2003. What is the minimum stock level?       450       800       850      1,000 4. What is the re-order level?        1,200        1,600        1,750        1,800
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY