Question
Chapter 15, Problem 8P
a)
Summary Introduction
To construct: A materials plan to decide how many phones can be made and delivered with the available inventory of phones and phone parts.
b)
Summary Introduction
To develop: An inventory projection of parts and products on a week by week basis for the material plan shown in part (a)
c)
Summary Introduction
To work: The impact on the material plan, if additional 100 circuit boards can be acquired in the first week.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Suppose you are in charge of a large mailing to the alumniof your college inviting them to contribute to a scholarshipfund. The letters and envelopes have been individually ad-dressed (mailing labels were not used). The letters are to beprocessed (matched with correct envelope, time estimated tobe 0.2 minutes each), folded (0.12 minutes each), and stuffedinto the correct envelope (0.10 minutes each). The envelopesare to be sealed (0.05 minutes each), and a large commemo-rative stamp is to be placed in the upper right-hand corner ofeach envelope (0.10 minutes each).a. Make a process chart for this activity, assuming that it is aone-person operation.b. Estimate how long it will take to stuff, seal, and stamp 2,000envelopes. Assume that the person doing this work is paid$8 per hour. How much will it cost to process 2,000 letters?c. Consider each of the following process changes. Whichchanges would reduce the time and cost of the currentprocess?▪ Each letter has the same greeting, “Dear…
A luxury hotel has been receiving a lot of complaints from guests recently. The manager worries that if these complaints continue, the hotel will start to lose clients. Therefore, you have been hired as a consultant to correct the problem(s). A list and count of the major complaints by week for the last month is as follows:
Week 1
Error on bill 10
Room not ready at check-in 8
Room service delivery late 3
Long line at check-out 10
Week 2
Error on bill 12
Noise in hallway 2
Long line at check-out 5
Room dirty 10
Week 3
Not enough towels in room 5
Error on bill 7
Room service delivery late 6
Not enough close-up parking 2
Week 4
Room dirty 7
Error on bill 9
Room not ready at check-in 10
Long line at check-in 9
You have decided to use a few of the “Tools of Quality” to present your finding to hotel management. Prepare a report to management that includes the…
Ishikawa diagram is a method for stating and identifying the problem. It can be also known as:
i. Fishbone diagram
ii. Fishwhale diagram
iii. Herringbone diagram
iv. Fishikawa diagram
А.
i and ii
В.
i, ii and iii
C.
i, iii and iv
D.
All above
Chapter 15 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Pete works for Home Depot at the paint counter. Customers often ask to match a color already in their home—a fabric, a rug, or an older paint. He has a talent for this and can do it quickly if the base colors are standardized. His first step is a visual check of his base colors—a white, a blue, a red, and a yellow. Identify what kind of steps is this and explain why?arrow_forwardWhat is the Mean absolute percent error (MAPE)?arrow_forwardA #2 pencil (P) is made from a wood subassembly (WS), a band (B) to hold the eraser on and an eraser (E). The wood subassembly is made from 2 wood halves (WH) and a piece of lead (L), the wood halves are made from wood blanks (WB). (For this question we will ignore the need for glue and paint.) The lead times for each of these are given below Lead Time (Weeks) P 2 WS 4 B 6 E 2 WH 2 L 2 WB 1 If nothing is in inventory (that is, all on hand quantities are equal to zero), and it is now the beginning of period 20, then when is the earliest that we can promise to ship No. 2 pencils?arrow_forward
- Define the mean absolute percent error (MAPE)?arrow_forwardCase Study Training at Hailey’s Construction Shobana, Hailey’s Construction, Sales Manager, read the memo she has just received from Kavelan , the Training Manager, and said to herself,” No way! I’m not going to let Kavelan get away with this. Last month, hhe insisted that 15 of the salespeople spend three days on a course on Quality Control conducted by a trainer. I had my hesitations, but I sent them anyway. On their return, they grumbled constantly about what a bore it was and how their time had been wasted because the content was totally irrelevant to their jobs. Now Kavelan wants another 10 participants. Well, he can just find them somewhere else!” Question 1 Describe the mistakes Hailey’s Construction Training Manager madearrow_forwardCase study Training at Hailey’s Construction Shobana, Hailey’s Construction, Sales Manager, read the memo she has just received from Kavelan , the Training Manager, and said to herself,” No way! I’m not going to let Kavelan get away with this. Last month, hhe insisted that 15 of the salespeople spend three days on a course on Quality Control conducted by a trainer. I had my hesitations, but I sent them anyway. On their return, they grumbled constantly about what a bore it was and how their time had been wasted because the content was totally irrelevant to their jobs. Now Kavelan wants another 10 participants. Well, he can just find them somewhere else!” Question 2 Elaborate what should the Training Manager do to ensure that the managers of every department willingly send their staff for the training programmes. include example alsoarrow_forward
- The OSHA inspection follows a six-step process. Four of the steps are listed in varying orders below. Select the option that places the given steps in the correct order. Responses Preparation, Walkaround, Results, Settlement/Appeal Preparation, Walkaround, Results, Settlement/Appeal Walkaround, Preparation, Results, Settlement/Appeal Walkaround, Preparation, Results, Settlement/Appeal Results, Walkaround, Settlement/Appeal, Preparation Results, Walkaround, Settlement/Appeal, Preparation Preparation, Settlement/Appeal, Walkaround, Resultsarrow_forwardDefine the term Plan-Do-Check-Act?arrow_forwardExplain or define each of these terms:d. Expected value of perfect informationarrow_forward
- As manager of The Fitness Center, Dana is constantly try-ing new initiatives to keep her clients fit. Recent studies show that using several different cardio regimens for shortperiods of time is more effective than an extended periodof time on one type of equipment. Dana has taken some ofthe existing cardio equipment and arranged them in a lineas follows: stationary bike, treadmill, stair stepper. Clients would select this part of the gym for cardio “circuit train-ing,” spending 15 minutes at each piece of equipment for a total cardio workout time of 45 minutes.a. If the reliability of the bike is 96%, the treadmill is 95%,and the stair stepper is 92%, what is the probability thata client can complete his or her workout uninterruptedby faulty equipment?b. Dana has added a second cardio “line” for circuittraining with the same type of equipment as the firstline. This equipment, however, is older with reliabilitiesof 80% each. If only one client were using the cardiocircuit training…arrow_forwardBook pdf : https://drive.google.com/file/d/1ojDaUwQu0gxTIn7oJnINvLmeqv5_FMz7/view?usp=drivesdk Question as in the attached photo from page 218 Question 5 Note: Give full explanation with clear indication to the problem’s aspect. Use information provided in table 7.8 , 7.7 (*) Use the weighted-point evaluation system to cal- culate weighted performance scores for each of the software firms. Would the results change if each dimension had a weight of one-third? (**) In Chapter 2, we described order qualifiers as per- formance dimensions on which customers demand a minimum level of performance. Basically, if a supplier fails to meet the minimum requirements on any of the qualifiers, that supplier would be eliminated from contention. How would you incorporate the concept of order qualifiers into the weighted-point evaluation system?arrow_forwardWhat is a fishbone diagram, and why would you use one? Think of a problem you have experienced at school or work, and draw a sample fishbone diagram with at least two levels.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY