A toy firm produces drums sequentially on three machines—A, B, and C—with cycle times of 3, 4, and 6 minutes, respectively.
(a) Determine the optimum efficiency and output rates for adding one, two, ... , six more machines.
(b) assume now that two identical lines are operating, each with machines A, B, and C. If new machines can be shared between the lines, how should one, two and then three new machines be added What are the resulting efficiencies and outputs of the two lines? is it always best to equally share extra machines between the two lines?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Similar questions
- A toy firm produces drums sequentially on three machines- A, B, and C- with cycle times of three, four, and six minutes, respectively. a) Determine the optimum efficiency and output rates for adding one, two... six more machines b) Assume now that two identical lines are operating, each with machines A, B, and C. If new machines can be shared between the lines, how should one, two, and then three new machines be added? What are the resulting efficiencies and outputs of the two lines? Is it always best to equally share extra machines between the two lines?arrow_forwardIn a multi-station serial process system, the capacity of the system is the equal to the capacity of the station that has the highest capacity among all stations. True Falsearrow_forwardA veterinary office with three processes (examination, greeting, and checkout) has two types of customers (boarding and medical). A veterinary office has a demand of 2 boarding customers per hour and 5 medical customers per hour. Boarding customers visit the greeting and checkout processes while medical customers visit all three processes. What is the total demand at the checkout process each hour? customers per hourarrow_forward
- .A team of 10 unloaders is employed in good reception bay of a large warehouse. During an 8 hour day 40 lorries arrive and it takes the team 10 minutes to unload each lorry. Each team member is paid RM3 per hour and it costs RM10 per hour to keep lorries waiting. Studies show that increasing the team to 14 men would reduce the unloading time to 7 minutes. Would it be worthwhile increasing the team to 14?arrow_forwardKnott's Industries manufactures standard and super premium backyard swing sets. Currently it has four identical swing-set-making machines, which are operated 275 days per year and 8 hours each day. A capacity cushion of 20 percent is desired. The following information is also known Annual Demand Standard Processing Time Average Lot Size Standard Setup Time per Lot a. Does Knott's have sufficient capacity to meet annual demand? Knott's does Standard Model 20,000 5min 50 30 min Super Premium Model 10,000 17 min 30 45 min have sufficient capacity to meet annual demand because 3 machines are needed. (Enter your response rounded up to the next whole number.) b. If Knott's was able to reduce the setup time for the Super Premium Model from 45 minutes to 30 minutes, would there be enough current capacity to produce 20,000 units of each type of swing set? If Knott's was able to reduce the setup time for the Super Premium Model from 45 minutes to 30 minutes, there would not be enough capacity to…arrow_forwardWhen a patient enters the Valley Health Clinical Laboratory to have his blood drawn and a Chemistry Panel and CBC run, he spends, on average 2 minutes at patient check-in, 45 minutes in the waiting area, 5 minutes having his medical history updated, and 8 minutes having his blood taken. If the clinical laboratory has 3 full-time Lab Techs, operates 8 hours per day and demand is 75 patients per day, what is the takt time? Assume that the med techs take a 30 minute lunch. Please enter your response using this format: ## minutesarrow_forward
- A machine operates with the following production cycle: 15 minutes of setup,45 minutes of production. While in production the machine produces 2 parts per minute.What is the capacity of the machine in parts per minute?arrow_forwardThe utilization of baggers is Food Goblin Supermarkets use both cashiers and baggers to serve customers at check out. During the first 7 hours of each workday (Monday-Friday), 6 cashiers and 2 baggers serve approximately 25 customers per hour. A cashier and a bagger who require approximately 6 minutes at checkout and 4 minutes at bagging serve each customer. a. The utilization of cashiers is 41.7%. (Enter your response rounded to one decimal place.) %. (Enter your response rounded to one decimal place.) v an example Part 2 of 3 Get more help. O Points: 0 of 3 Clear all Check answer Oarrow_forwardIn the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 14.35 hours. The time in the welding operation is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 2 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 2 hour waiting for the setup of the welding machine, 0.35 hour waiting for the other pieces of the batch to go through welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? percentarrow_forward
- A small call center normally has four employees answering calls while open. On average, seven calls arrive every four minutes. Under normal operating conditions, each employee on average handles each call in 3.3 minutes. But today, one employee has the flu, so the center needs to operate with three employees during this time. The manager is nervous that it may be supply-constrained and so she directs her employees to hurry up their processing of calls today. What is the maximum average processing time for each call that they need to achieve today so that they have a stable queue? Note: Round your answer to 2 decimal places. Answer is complete but not entirely correct. Maximum average processing time 4,73 minutesarrow_forwardUnder ideal conditions, a service bay at a Fast Lube can serve 7 cars per hour. The effective capacity of a Fast Lube service bay is 5.5 cars per hour, with efficiency known to be 0.88. The minimum number of service bays Fast Lube needs to achieve an anticipated production of 150 cars per 8-hour day = service bays (enter your response rounded up to the next whole number).arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.