Chapter 9, Problem 25P

a)

Summary Introduction

To draw: The precedence diagram of the operation.

b)

Summary Introduction

To determine: The cycle time of the operation.

c)

Summary Introduction

To determine: The theoretical minimum number of workstations.

d)

Summary Introduction

To assign: The various tasks to workstations.

e)

Summary Introduction

To determine: The overall actual efficiency of the assembly line.

Blurred answer
Students have asked these similar questions
An assembly plant for the Blood Pressure RX, a portableblood pressure device, has 400 minutes available daily in theplant for the device, and the average demand is 80 units per day.Final assembly requires 6 separate tasks. Information concerningthese tasks is given in the following table.                                                                                                         a) Draw a precedence diagram of this operationb) Given the demand, what is the cycle time for this operation?c) What is the theoretical minimum number of workstations?f d) Assign tasks to workstations.e) What is the overall actual efficiency of the assembly line?
An assembly line must be designed to produce 40 containers per hour. The following data give the necessary information Table 1 TASK IMMEDIATE PREDECESSOR TASK TIME (sec) A None 60 B A 12 C B 35 D A 55 E D 10 F E 50 G F, C 5 Draw the precedence diagram. ii. Compute the cycle time (in seconds) to achieve the desired output rate. iii. What is the theoretical minimum number of stations? iv. Assign the tasks to workstation?  v. What is the efficiency of the line? PLEASE ANSWER THE FOLLOWING QUESTIONS: iV, & v.
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40- hourworkweek: a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this operation? c) What is the theoretical minimum number of workstations? d) Assign tasks to workstations. e) How much total idle time is present each cycle? f) What is the efficiency of the assembly line with five stations? With six stations? TASK PERFORMANCE TIME (sec) PREDECESSORS A 20 None 30 15 15 A E 10 В. С 30 D, E
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY