Excursions in Modern Mathematics (9th Edition)
Excursions in Modern Mathematics (9th Edition)
9th Edition
ISBN: 9780134468372
Author: Peter Tannenbaum
Publisher: PEARSON
bartleby

Videos

Textbook Question
Book Icon
Chapter 8, Problem 57E

Consider the project described by the project digraph shown in Fig. 8 - 4 2 .

a. Find the critical path and critical time for the project.

b. Find the critical-time priority list.

c. Schedule the project with N = 2 processors using the critical-path algorithm. Show the timeline and the project finishing time.

d. Find an optimal schedule for N = 2 processors.

e. Use the relative error formula ε = Fin OptOpt to find the relative error of the schedule found in (c).

Chapter 8, Problem 57E, Consider the project described by the project digraph shown in Fig.8-42. a. Find the critical path

Figure 8 - 4 2

Blurred answer
Students have asked these similar questions
Find the optimal value of the given model
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B C D Time (weeks) 5 8 3 2 Immediate. Predecessor(s) Dave's earliest start (ES) and earliest finish (EF) are: A A Activity Activity E F G H ES Time (weeks) 5 EF 5 5 10 6 Immediate Predecessor(s) B B C, E D, F
the operation times for the major functional units in this implementation are the following:                             Memory units: 200 picoseconds (ps) ALU and adders: 50 ps Register file (read or write): 25 ps Assuming that the multiplexors, control unit, PC accesses, sign extension unit, and wires have no delay, which of the following implementations would be faster and by how much? An implementation in which every instruction operates in 1 clock cycle of a fixed length. An implementation where every instruction executes in 1 clock cycle using a variable length clock, which for each instruction is only as long as it needs to be. (Such an approach is not terribly practical, but it will allow us to see what is being sacrificed when all the instructions must execute in a single clock of the same length.) To compare the performance, assume the following instruction mix: 20% loads, 15% stores, 40% ALU instructions, 20% branches, and 5% jumps.

Chapter 8 Solutions

Excursions in Modern Mathematics (9th Edition)

Ch. 8 - Prob. 11ECh. 8 - Consider the digraph with vertex-set V={V,W,X,Y,Z}...Ch. 8 - Prob. 13ECh. 8 - Prob. 14ECh. 8 - Prob. 15ECh. 8 - A mathematics textbook consists of 10 chapters....Ch. 8 - Prob. 17ECh. 8 - The digraph in Fig. 8-29 is an example of a...Ch. 8 - Prob. 19ECh. 8 - Wobble, a start-up company, is developing a search...Ch. 8 - A project consists of eight tasks labeled A...Ch. 8 - A project consists of eight tasks labeled A...Ch. 8 - Prob. 23ECh. 8 - Prob. 24ECh. 8 - Prob. 25ECh. 8 - A ballroom is to be set up for a large wedding...Ch. 8 - Prob. 27ECh. 8 - Prob. 28ECh. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Prob. 31ECh. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Prob. 33ECh. 8 - Exercises33 and 34 refer to the Martian Habitat...Ch. 8 - Prob. 35ECh. 8 - Prob. 36ECh. 8 - Prob. 37ECh. 8 - Using the priority list G,F,E,D,C,B,A, schedule...Ch. 8 - Prob. 39ECh. 8 - Using the priority list G,F,E,D,C,B,A, schedule...Ch. 8 - Prob. 41ECh. 8 - Prob. 42ECh. 8 - Prob. 43ECh. 8 - Use the decreasing-time algorithm to schedule the...Ch. 8 - Prob. 45ECh. 8 - Use the decreasing-time algorithm to schedule the...Ch. 8 - Prob. 47ECh. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project digraph shown in Fig.8-40....Ch. 8 - Consider the project digraph shown in Fig.8-40....Ch. 8 - Prob. 53ECh. 8 - Consider the project digraph shown in Fig.8-41....Ch. 8 - Schedule the Apartments Unlimited project given in...Ch. 8 - Schedule the project given in Exercise26 Table8-5...Ch. 8 - Consider the project described by the project...Ch. 8 - Consider the project digraph shown in Fig.8-43,...Ch. 8 - Prob. 59ECh. 8 - Symmetric and totally asymmetric digraphs. A...Ch. 8 - Prob. 61ECh. 8 - Let W represent the sum of the processing times of...Ch. 8 - You have N=2 processors to process M independent...Ch. 8 - You have N=3 processors to process M independent...Ch. 8 - You have N=2 processor to process M+1 independent...
Knowledge Booster
Background pattern image
Math
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, subject and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:9781133382119
Author:Swokowski
Publisher:Cengage
2.1 Introduction to inequalities; Author: Oli Notes;https://www.youtube.com/watch?v=D6erN5YTlXE;License: Standard YouTube License, CC-BY
GCSE Maths - What are Inequalities? (Inequalities Part 1) #56; Author: Cognito;https://www.youtube.com/watch?v=e_tY6X5PwWw;License: Standard YouTube License, CC-BY
Introduction to Inequalities | Inequality Symbols | Testing Solutions for Inequalities; Author: Scam Squad Math;https://www.youtube.com/watch?v=paZSN7sV1R8;License: Standard YouTube License, CC-BY