Tasks | Label (P-time) | precedent tasks |
Bathrooms (clean) | B(2) | P |
Carpets (shampoo) | C(1) | S, W |
Filters (replace) | F(0.5) | |
General cleaning | G(2) | B, F, K |
Kitchen (clean) | K(3) | P |
Lights (replace bulbs) | L(0.5) | |
Paint | P(6) | L |
Smoke Detectors (battery) | S(0.5) | G |
Windows (wash) | W(1) | G |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Apply the backflow algorithm to the digraph below
T9 (6)
T5 (12)
T1 (3)
T6 (10)
T8 (4)
T10 (5)
Т2 (2)
End
ТЗ (8)
T7 (9)
T4 (11)
Task 5 has a critical time of
Task 2 has a critical time of
Use the decreasing time algorithm to create a priority list for the digraph below, then schedule the project
with two processors.
T1 (5)
T4 (11)
T7 (7)
T2 (7)
Т5 (9)
T8 (12)
End
ТЗ (12)
T6 (7)
Т9 (8)
Task 5 is done b v Select an answer
tarting at time
Processor 1
Processor 2
Task 8 is done by Delect anI answer
j starting at time
The finishing time for the schedule is
[2B] (Please type and draw your answers digitally).The given table below (1st picture) shows the 5 different places that you would like to visit on a particular day. The table below shows the estimated distance (in kilometers per hour) it takes you to travel from one place to another. If you will visit each of these places exactly once, determine the shortest time possible it would take you to do using the Edge-Picking Algorithm. Example (2nd photo) already provided in the photos below.
Chapter 8 Solutions
Excursions in Modern Mathematics (9th Edition)
Ch. 8 - For the digraph shown in Fig. 8-25, find a.the...Ch. 8 - For the digraph shown in Fig. 8-26, find Figure...Ch. 8 - For the digraph in Fig. 8-25, find a.all path of...Ch. 8 - For the digraph in Fig. 8-26, find a.a path of...Ch. 8 - For the digraph in Fig. 8-25, find a.all cycles of...Ch. 8 - For the digraph in Fig. 8-26, find a.all cycles of...Ch. 8 - Prob. 7ECh. 8 - For the digraph in Fig.8-26, find a.all vertices...Ch. 8 - a.Draw a digraph with vertex-set V={A,B,C,D} and...Ch. 8 - a.Draw a digraph with vertex-set V={A,B,C,D} and...
Ch. 8 - Prob. 11ECh. 8 - Consider the digraph with vertex-set V={V,W,X,Y,Z}...Ch. 8 - Prob. 13ECh. 8 - Prob. 14ECh. 8 - Prob. 15ECh. 8 - A mathematics textbook consists of 10 chapters....Ch. 8 - Prob. 17ECh. 8 - The digraph in Fig. 8-29 is an example of a...Ch. 8 - Prob. 19ECh. 8 - Wobble, a start-up company, is developing a search...Ch. 8 - A project consists of eight tasks labeled A...Ch. 8 - A project consists of eight tasks labeled A...Ch. 8 - Prob. 23ECh. 8 - Prob. 24ECh. 8 - Prob. 25ECh. 8 - A ballroom is to be set up for a large wedding...Ch. 8 - Prob. 27ECh. 8 - Prob. 28ECh. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Prob. 31ECh. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Prob. 33ECh. 8 - Exercises33 and 34 refer to the Martian Habitat...Ch. 8 - Prob. 35ECh. 8 - Prob. 36ECh. 8 - Prob. 37ECh. 8 - Using the priority list G,F,E,D,C,B,A, schedule...Ch. 8 - Prob. 39ECh. 8 - Using the priority list G,F,E,D,C,B,A, schedule...Ch. 8 - Prob. 41ECh. 8 - Prob. 42ECh. 8 - Prob. 43ECh. 8 - Use the decreasing-time algorithm to schedule the...Ch. 8 - Prob. 45ECh. 8 - Use the decreasing-time algorithm to schedule the...Ch. 8 - Prob. 47ECh. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project digraph shown in Fig.8-40....Ch. 8 - Consider the project digraph shown in Fig.8-40....Ch. 8 - Prob. 53ECh. 8 - Consider the project digraph shown in Fig.8-41....Ch. 8 - Schedule the Apartments Unlimited project given in...Ch. 8 - Schedule the project given in Exercise26 Table8-5...Ch. 8 - Consider the project described by the project...Ch. 8 - Consider the project digraph shown in Fig.8-43,...Ch. 8 - Prob. 59ECh. 8 - Symmetric and totally asymmetric digraphs. A...Ch. 8 - Prob. 61ECh. 8 - Let W represent the sum of the processing times of...Ch. 8 - You have N=2 processors to process M independent...Ch. 8 - You have N=3 processors to process M independent...Ch. 8 - You have N=2 processor to process M+1 independent...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, subject and related others by exploring similar questions and additional content below.Similar questions
- Use the critical path algorithm to create a priority list for the digraph below. T4 (5) Т6 (11) T1 (8) End T2 (10) T5 (6) T7 (7) ТЗ (12) Priority list: Give the priority as a list of task numbers. For example, you'd enter something like: 1,2,3,4,5,6,7,8,9,10arrow_forwardUse the critical path algorithm to create a priority list for the digraph below. T1 (2) T4 (12) Т6 (5) End T2 (7) T5 (4) T7 (11) Т3 (9) Priority list: Give the priority as a list of task numbers. For example, you'd enter something like: 1,2,3,4,5,6,7,8,9,10arrow_forwardGiven a graph G = (V,E) find the minimum number of edges that will cover every vertex (Edge Cover). Detail and analyze an approximate algorithm to this problem.arrow_forward
- find the mximum possible order of S5arrow_forwardWhat is a Prim Algorithm? What is the step to apply this algorithm? Please help Sir, thx.arrow_forward[(1B)] The given table below shows the 6 different places that you would like to visit on a particular day. The table below shows the estimated amount of time (in minutes) it takes you to travel (by any means of transportation) from one place to another. If you will visit each of these places exactly once, determine the shortest time possible it would take you to do using the Edge-Picking Algorithm. Examples already provided in the photos below. Home Hospital Mall Esplanade Pet Shop Market Home --- 30 15 17 10 3 Hospital 30 --- 17 20 25 23 Mall 15 17 --- 2 25 18 Esplanade 17 20 2 --- 27 20 Pet Shop 10 25 25 27 --- 7 Market 3 23 18 20 7 ---arrow_forward
- 1. A student wants to know the effect of 2 parameter settings (Number of iterations and learning rate) on the computation time of an algorithm. Experiments were carried out by trying 3 different values for each parameter, then seeing the response to computation time. If we know the experimental results as shown in the following figure, what information can we get? Boxplot of Speed (sec) Boxplot of Speed (sec) 0,8 0,8- 0,7 0,7- 0,6 0.6 0,5 0,5- 0,4 0,4- 0,3 0,3- 0,2 0,2- 0,50 learning rate 500 1000 1500 0,05 0,95 Niteration Speed (sec)arrow_forward10. Use the decreasing time algorithm to create a priority list for the digraph below, then schedule the project with two processors. ***Picture*** Task 6 is done by = ***Processor 1 or 2 *** starting at time = ______ Task 9 is done by = ***Processor 1 or 2 *** starting at time =________ The finishing time for the schedule is _____________arrow_forward4. [Ocean Weather] Information about ocean weather can be extracted from radar returns with the aid of a special algorithm. A study is conducted to estimate the difference in wind speed as measured on the ground and via the Seasat satellite. To do so, wind speeds (miles per hour) are measured on the ground and via the Seasat satellite simultaneously at 12 special times. The data is shown in the following table. The table also shows the difference between the wind speed on the ground and that via the Seasat satellite at each time, as well as some summary statistics. Difference Time Ground (x) Satellite (y) d= x – y 1 4.46 4.08 0.38 3.99 3.94 0.05 3 3.73 5.00 -1.27 4 3.29 5.20 -1.91 4.82 3.92 0.90 6 6.71 6.21 0.50 7 4.61 5.95 -1.34 8. 3.87 3.07 0.80 3.17 4.76 -1.59 10 4.42 3.25 1.17 11 3.76 4.89 -1.13 12 3.30 4.80 -1.50 d = -0.41 Sd = 1.14 It is claimed that the wind speed measured on the ground is lower than that measured via the Satellite on average. Set up your hypotheses to test this…arrow_forward
- Can I please get some assistance with this Prim's algorithm?arrow_forwardHow exactly does one go about utilizing numerical methods to solve a set of equations that have been arranged in a system? Provide your own explanation of the algorithm used in at least one of the methods.arrow_forwardDetermine which characteristics of an algorithm the following procedures have and which they lack. procedure sum(n: positive integer) sum:= 0 while i<10 sum:= sum + iarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Linear Algebra: A Modern IntroductionAlgebraISBN:9781285463247Author:David PoolePublisher:Cengage Learning
Linear Algebra: A Modern Introduction
Algebra
ISBN:9781285463247
Author:David Poole
Publisher:Cengage Learning
Orthogonality in Inner Product Spaces; Author: Study Force;https://www.youtube.com/watch?v=RzIx_rRo9m0;License: Standard YouTube License, CC-BY
Abstract Algebra: The definition of a Group; Author: Socratica;https://www.youtube.com/watch?v=QudbrUcVPxk;License: Standard Youtube License