Chapter 8, Problem 58E

Consider the project digraph shown in Fig . 8-43 , with the processing time given in hours.

a. Find the critical path and critical time for the project.

b. Find the critical-time priority list.

c. Schedule the project with N = 2 processors using the critical-path algorithm. Show the timeline and the project finishing time.

d. Explain why any schedule for N = 2 processors with finishing time Fin = 22 must be an optimal schedule.

e. Schedule the project with N = 3 processors using the critical-path algorithm. Show the timeline and the project finishing time.

f. Explain why the schedule found in (e) is an optimal schedule for three processors.

Chapter 8, Problem 58E, Consider the project digraph shown in Fig.8-43, with the processing time given in hours. a.Find the

Figure 8-43

Blurred answer
Students have asked these similar questions
the operation times for the major functional units in this implementation are the following:                             Memory units: 200 picoseconds (ps) ALU and adders: 50 ps Register file (read or write): 25 ps Assuming that the multiplexors, control unit, PC accesses, sign extension unit, and wires have no delay, which of the following implementations would be faster and by how much? An implementation in which every instruction operates in 1 clock cycle of a fixed length. An implementation where every instruction executes in 1 clock cycle using a variable length clock, which for each instruction is only as long as it needs to be. (Such an approach is not terribly practical, but it will allow us to see what is being sacrificed when all the instructions must execute in a single clock of the same length.) To compare the performance, assume the following instruction mix: 20% loads, 15% stores, 40% ALU instructions, 20% branches, and 5% jumps.
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!     You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.    Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer…
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!     You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.    Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer…

Chapter 8 Solutions

Excursions in Modern Mathematics (9th Edition)

Ch. 8 - Prob. 11ECh. 8 - Consider the digraph with vertex-set V={V,W,X,Y,Z}...Ch. 8 - Prob. 13ECh. 8 - Prob. 14ECh. 8 - Prob. 15ECh. 8 - A mathematics textbook consists of 10 chapters....Ch. 8 - Prob. 17ECh. 8 - The digraph in Fig. 8-29 is an example of a...Ch. 8 - Prob. 19ECh. 8 - Wobble, a start-up company, is developing a search...Ch. 8 - A project consists of eight tasks labeled A...Ch. 8 - A project consists of eight tasks labeled A...Ch. 8 - Prob. 23ECh. 8 - Prob. 24ECh. 8 - Prob. 25ECh. 8 - A ballroom is to be set up for a large wedding...Ch. 8 - Prob. 27ECh. 8 - Prob. 28ECh. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Prob. 31ECh. 8 - Exercises 29 through 32 refer to a project...Ch. 8 - Prob. 33ECh. 8 - Exercises33 and 34 refer to the Martian Habitat...Ch. 8 - Prob. 35ECh. 8 - Prob. 36ECh. 8 - Prob. 37ECh. 8 - Using the priority list G,F,E,D,C,B,A, schedule...Ch. 8 - Prob. 39ECh. 8 - Using the priority list G,F,E,D,C,B,A, schedule...Ch. 8 - Prob. 41ECh. 8 - Prob. 42ECh. 8 - Prob. 43ECh. 8 - Use the decreasing-time algorithm to schedule the...Ch. 8 - Prob. 45ECh. 8 - Use the decreasing-time algorithm to schedule the...Ch. 8 - Prob. 47ECh. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project described by the digraph...Ch. 8 - Consider the project digraph shown in Fig.8-40....Ch. 8 - Consider the project digraph shown in Fig.8-40....Ch. 8 - Prob. 53ECh. 8 - Consider the project digraph shown in Fig.8-41....Ch. 8 - Schedule the Apartments Unlimited project given in...Ch. 8 - Schedule the project given in Exercise26 Table8-5...Ch. 8 - Consider the project described by the project...Ch. 8 - Consider the project digraph shown in Fig.8-43,...Ch. 8 - Prob. 59ECh. 8 - Symmetric and totally asymmetric digraphs. A...Ch. 8 - Prob. 61ECh. 8 - Let W represent the sum of the processing times of...Ch. 8 - You have N=2 processors to process M independent...Ch. 8 - You have N=3 processors to process M independent...Ch. 8 - You have N=2 processor to process M+1 independent...
Knowledge Booster
Background pattern image
Math
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, subject and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Discrete Mathematics and Its Applications ( 8th I...
Math
ISBN:9781259676512
Author:Kenneth H Rosen
Publisher:McGraw-Hill Education
Text book image
Mathematics for Elementary Teachers with Activiti...
Math
ISBN:9780134392790
Author:Beckmann, Sybilla
Publisher:PEARSON
Text book image
Calculus Volume 1
Math
ISBN:9781938168024
Author:Strang, Gilbert
Publisher:OpenStax College
Text book image
Thinking Mathematically (7th Edition)
Math
ISBN:9780134683713
Author:Robert F. Blitzer
Publisher:PEARSON
Text book image
Discrete Mathematics With Applications
Math
ISBN:9781337694193
Author:EPP, Susanna S.
Publisher:Cengage Learning,
Text book image
Pathways To Math Literacy (looseleaf)
Math
ISBN:9781259985607
Author:David Sobecki Professor, Brian A. Mercer
Publisher:McGraw-Hill Education
Minimum cuts and maximum flow rate; Author: Juddy Productions;https://www.youtube.com/watch?v=ylxhl1ipWss;License: Standard YouTube License, CC-BY