Interpretation:The network diagram is to be drawn.
Concept Introduction:Network diagram is a graphical representation of tasks in symbols and lines for easy understanding. The networking technique is a method for planning, programming and controlling of work in progress. It is helpful for effective management. It helps the management for decisions.
B
Interpretation:The critical path and duration of the project are to be determined.
Concept Introduction:Critical path is a technique which has various stages. It is used to calculate the optimum time is requiredto complete a task. It is the longest length of time for completion of the project.
C
Interpretation:The slack for each activity is to be determined.
Concept Introduction:Slack is the time evaluatedwhich causes the delay during any activity. For calculation, the earliest and the latest time of activity are required.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
- (Use the information below to solve Q11 - Q20) Given the following information regarding a project: Predecess ors None None a a b b Activity a b C d e CD f OC g h Duration 3 1 3 4 4 5 23 c, e f Which of the following is NOT a path in the network? O a-d O a-c-g b-c-g O b-e-g b-f-harrow_forwardEarned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: No Type Cumulative Budgeted Cost (CBC) 2 Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) 1 3 TOTAL RM i. ii. iii. iv. 64,000 68,000 54,000 100,000 Percentage 64.0 Cost performance Index (CPI) [hint: CEV/CAC] Cost variance (VC) [hint: CEV-CAC] 68.0 54.0 a) Based on question 2(a), calculate and elaborate the various of indicators of cost performance for this project based on the respective below: 100.0 Forecasted cost of completion (FCAC) with action taken [hint: TBC/CPI] Forecasted cost of completion (FCAC) without any action taken [hint: CAC + [TBC-CEV]arrow_forwardA project manager has compiled a list of major activities that will be required to install a new CCTV system in the office. The list includes estimated completion time for activities and precedence relationship. Determine the Critical Path Activities Compute for Total Project Duration Note: Use MS Excel QM Activity Immediate Predecessor Estimated Times (weeks) 2-4-6 A D A 6-8-10 E D 7-9-12 E 2-3-5 IF A 3-4-8 F 5-7-9 2-2-3 2-3-6 J 3-4-5 K 4-5-8 5-8-12 M 1-1-1 IN M 6-7-11 8-9-13 End |Н, G, К, Оarrow_forward
- The following information is known about a project toupgrade a point-of-sale system at Kids and Tots Apparel.Activity Activity Time (days) Immediate Predecessor(s)A 7 —B 2 A C 4 AD 4 B, CE 4 DF 3 EG 5 Ea. Draw the network diagram for this project.b. Determine the critical path and project duration.c. Calculate the slack for each activity.arrow_forwardHow can a business analyst communicate requirements (and associated models) for a project in project management.arrow_forwardReliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project. b. Determine the project’s critical path and duration. c. What is the slack for each activity?arrow_forward
- Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardQl: For the project listed below, find the following items: 1- Total project finishing time, 2- Critical path 3- Free float for each task. 4- If Activity B is delayed by 7 weeks. As a project manager explains how this will affect the total project critical path. Dependency or Predecessor Activity الفعالية Duration in Weeks المدة بالأسابيع Activities الاعتمادية او الفعاليات السابقة C 6. 4 3 A 7 С, В, Р U 4 T 2 A 3 A 6. Uarrow_forwardCreate a Network Diagram and Critical Path using the Data. Determine the minimum project duration. The duration of each activity is in days.arrow_forward
- A project consisting of the following activities: Activities predece.Activities day TE M K J H G E C B G KJ G I,F D D E,C B,A| B,A A 1 3 4 6. 5 2 3 9 6 2 4 3 5 1- Draw the network diagram of the project 2- Calculate (Es) and (Lc) the project events 3- Select the critical path 4 - What is the minimum time required to complete the project?arrow_forward(please try to do math in handwritten) Use the following project data for problem 1 through 5 Activity name Predecessor Activity Activity Duration N 3 M 2 P M,N 4 3 P,Q R,S 2. 1. Prepare an AON Network Diagram 2. Identify all possible paths. Provide that information in a table. The heading of your table should as follow: Path Duration 3. Perform a forward pass and a backward pass. Display your result in an AON diagram.Usethe follow legend for your node(s) Activity ES EF Duration LS LF 4. Prepare a table summarizing the results of your Activity Schedule. The heading of your table should as follows: Activity name ES Slack EF LS LF 5. Identify the critical path. What is the project duration? 2. 4.arrow_forwardscenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website' : Activity Description Duration (days) Preceding Activities A Determine user needs 8 Review s/w and languages Purchase software 10 Design format and style 10 E Write programs A F Review outcome product with user 12 G Make revisions 4 C H Select server site E I Install on server 14 D, F Test G, H, I 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if activity D revised to take 14 instead of 10 days?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.