Question
Chapter 7, Problem 3AME
Summary Introduction
Interpretation: The number of week’s activity ‘A’ can be delayed, until it becomes an activity in the critical path and the consequences of activity ‘A’ becoming critical are to be determined.
Concept Introduction: The longest time period that a particular activity in a project could be delayed without making an impact on its completion date is known as activity slack. This, in other words mean that activities in the critical path cannot have slack as they cannot be delayed. Slack details of activities are useful as they can be used to identify activities that require close attention.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Mangement
Project management is a discipline that involves planning, organizing, and overseeing the execution of a project from initiation to completion. It encompasses defining project goals, outlining tasks, allocating resources, and managing budgets and timelines. A successful project manager must possess strong leadership skills, effective communication, and the ability to mitigate risks and solve problems efficiently. Collaboration among team members is crucial, as is the flexibility to adapt to unexpected challenges that may arise during the project lifecycle. Continuous monitoring and evaluation ensure that the project stays on track, meeting objectives and delivering value to stakeholders.
Question: How can project managers encourage effective collaboration and communication among team members to ensure the successful and timely completion of a project?
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary
for the completion of this project are listed in the following table:
Total Cost
Normal Time
Crash Time Normal
with
Immediate
Activity
(weeks)
(weeks)
Cost
Crashing Predecessor(s)
$2,200
$2,100
$2,900
$2,900
A
4
3
1
C
3
3
$500
$500
$2,500
$1,000
$3,200
$2,800
$1,375
$4,600
$2,100
8.
E
6.
3
G
4
$1,600
D, E
a) Based on the given information regarding the activities for the project, the project length =
weeks.
%3D
b) The total cost required for completing this project on normal time = $
%3D
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
The cost of the project based on the first activity selected for crashing will increase by $
d) The maximum weeks by which the project can be reduced by crashing =
weeks.
%3D
Total cost of crashing the project to minimum (or…
The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table.
What is the Late Start on Activity C?
What is the slack on Activity C?
What is the slack on Activity B?
What is the critical path?
What is the Early Finish on Activity H?
Chapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Given the information below, what are the estimated expected (mean) times (in weeks) for activities A-H? What are the estimated standard deviations (in weeks) in the times for activities A-H?arrow_forwardDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Normal Activity Time (weeks) Time (weeks) Cost ABCDEFG 4 2 3 8 6 3 4 3 1 3 4 3 2 2 $2,100 $2,300 $600 $2,400 $800 $3,400 $1,400 Total Cost with Crashing Immediate Predecessor(s) $2,750 $2,900 $600 $2,680 $1,100 $4,600 $1,900 a) Based on the given information regarding the activities for the project, the project length b) The total cost required for completing this project on normal time = $ 13000. | | A B C D, E = 16 weeks. c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 70. d) The maximum weeks by which the project can be reduced by crashing = 7 weeks. Total cost of crashing the…arrow_forwardIf Activity C has an expected time estimate of 8 days, which of the following statements is TRUE? * The activity time estimates for Activity C are: 1, 7, and 19 days Activity C can be delayed for a maximum of 5 days Activity C should not be delayed The activity time estimates for Activity C are: 2, 4, and 9 daysarrow_forward
- A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.arrow_forwardYou are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track? Activity Time Immediate Predecessor A 10 Weeks None B 6 Weeks A C 7 Weeks A D 6 Weeks B E 8 Weeks C F 3 Weeks D G 4 Weeks Farrow_forwardConsider the following project activities with a normal unit: (The normal unit is Day) Activity Name Immediate Predecessor (list number/ name, separated by ‘,’) Normal Time A 6 B A 2 C A 4 D B, C 3 E D 1 F D 7 G E 4 H F, G 2 I F 6 J I 1 K H, J 5 Fill the following table: Activity Name Activity Time Earliest Expected Competition Time (TE) Latest Expected Competition Time (TL) Slack (TL-TE) A 6 B 2 C 4 D 3 E 1 F 7 G 4 H 2 I 6 J 1 K 5 Project Completion Time = Days The Critical Path is=arrow_forward
- The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost (S) Immediate Predecessors A 2 10 2 0 None B 3 15 2 23 A C 5 25 4 30 B D 3 20 1 24 C E 6 30 4 45 C F 1 5 1 0 E G 7 35 6 50 F H 10 50 7 80 D, Garrow_forwardYou are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can you determine from this data? A. The activity's float and duration B. Only the activity float C. Only the activity duration D. Neither the activity's float nor its durationarrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A Carrow_forward
- Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Activity Normal Time (days) Crash Time (days) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 6 $6,000 $6,400 B $1,200 $3,000 C 11 $4,000 $6,000 a) Activity that should be crashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = $_____ (Enter your response as an integer.) 7 4 2 9 A B ---arrow_forwardProblem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?arrow_forwardYou are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY