Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:
a. Draw the network diagram for the project.
b. Determine the project’s critical path and duration.
c. What is the slack for each activity?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Draw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and Oarrow_forwardPlease show the step-by-step solution how you get your answer.arrow_forwardThe project information of the project Automated Warehouse Order Picking System is presented as following. Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical path. How many days will the project take? ID A B C D E F G H 80 130 85 95 Activity Define requirements Assign team Design hardware Code software Build & test hardware Develop patent request Test software Integrate systems Predecessor None A A B C C D E (F-S, lag 20d),F,G Time (days) 5 сл сл 5 20 20 10⁰ 15 15 40arrow_forward
- Based on Table below, discuss how to complete the following project case:a. Create a network model in the form of Activity and Arrow (AoA) and Activity on Node (AoN) for the marketing product project of a company using the CPM method (manual and optimization software)! b. Analyze the critical path and critical duration for the company's project! Activity Description Predecessor Duration (day) A Production Planning — 18 B Market Survey and Market Research — 20 C Production Analysis A 28 D Modeling Product A, B 31 E Sales Brochures A, B 21 F Cost Analysis C, E 33 G Product Experiment D, E 42 H Sales Training B, E 29 I Cost Pricing H 26 J Project Report F, G, I 50arrow_forward(Note: Task N is a dummy task. It must be included in the relationships, but its duration is 0. Be sure its duration is set to 0) Please see attached chart and diagram. 1. Set the Project start on Monday 11/1/20. Thursday 11/26/20, Friday 11/27/20, 12/25/20, and 1/1/21 are holidays. 2. Determine critical path and its duration. When the project will end (date)? 3. There is a possibility that the starting task K may be delayed by 3 days. Will this impact the project completion date? If yes, when will be the new finish date? (After checking this out, please restore the project to its original schedule). 4. Assign the following resources to the tasks. All resources will be full time. (Set the leveling to manual first).arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. What is the probability that project can be completed two months early?arrow_forward
- The managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. Draw the project network, and compute the expected time and variance for each activity. Develop an activity schedule for this project, compute activity slack time and identify critical path.arrow_forwardI only need help with part d-2, please help! The following CPM network has estimates of the normal time in weeks listed for the activities: a. Identify the critical path. A-C-D-E-G A-C-D-F-G A-B-D-E-G A-B-D-F-G b. What is the length of time to complete the project? 25 weeks c. Which activities have slack, and how much? C, 1 week; E, 2 weeks. D, 1 week; E, 2 weeks. B, 2 weeks; E, 2 weeks. C, 2 weeks; F, 3 weeks. Here is a table of normal and crash times and costs. ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST A 7 6 $ 7,000 $ 8,000 B 2 1 5,000 7,000 C 4 3 9,000 10,200 D 5 4 3,000 4,500 E 2 1 2,000 3,000 F 4 2 4,000 7,000 G 5 4 5,000 8,000 d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion? A, C A, E B, D B, C d-2. What would be the total incremental cost? I only need help with this question please.arrow_forwardI need solve this in project managementarrow_forward
- The following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?arrow_forwardA project network is shown below, with three time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in days)) for each activity in the network. a. Compute the expected time for each activity in the project network. b. Identify and list all possible paths in the project network. Compute the expected duration for each path in the project network. c. Identify the critical path(s) in the project network. What is the expected project completion time? d. Compute the variance of each activity on the critical path(s). e. Determine the project variance and project standard deviation. Use the PERT analysis results in 2(c) and 2(e) to answer questions (f), (g), (h), and (i) below:f. What is the probability that the project can be completed within 22 days of its start? g. What is the probability that the project can be completed within 16 days of its start? h. Determine the project deadline that gives this project a 78% chance of on-time completion. i. Determine the project deadline…arrow_forward13.42 Activity A is worth $100, is complete, and actually cost $150 Activity B is worth $500, is 75% complete, and has actually cost $400 so far Activity C is worth $500, is 25% complete, and has actually cost $200 so far. What is the estimated cost to completion for the project?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.